Combined synopsis and solicitation, total small business set-aside
Wiley Hall Dean's office, Reception office, Deans bathroom and hallway corridor
6923G225Q000011
Maritime Administration, 6923G2 DOT Maritime Administration. Remediation Services.
Awarded
Coastal Environmental Technologies Ltd.
$37,532.00 obligated so far on USAspending
Get the next one like this from Maritime Administration by email, the day it is posted.Find my opportunities
This one was awarded in 2025
14 like it are open now in remediation services
- 620-26-206 Asbestos Abatement
Department of Veterans Affairs, 242-Network Contract Office 02
SolicitationSDVOSBNAICS 562910Montrose, NY36C24227R0010Due tomorrowNov 27 - Sources Sought Notice: Asbestos and Lead Management Services
National Institutes of Health, NIH a E Construction
Sources soughtSmall businessNAICS 562910Bethesda, MDSSN-ALMS-2027Due tomorrowNov 27 - Remedial Investigation (RI) and Optional Feasibility Study (FS) for Per- and Polyfluoroalkyl Substances (PFAS)
Department of the Army, W075 Endist Sacramento
Sources soughtNAICS 562910Monterey, CAW9123826X1CUSDue in 4 daysNov 30
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Combined synopsis and solicitation. A streamlined commercial-item buy where the notice itself is the solicitation. Glossary
- Who may compete
- Total small business set-aside. Only small businesses may compete. Small, under NAICS 562910 (remediation services), means no more than $25 million in average annual receipts, counted with affiliates. Open Small business opportunities
- Time to respond
- Bidders had 15 days from the day the solicitation was posted, July 22, 2025, to the deadline. The deadline moved 2 times: it was first July 29, 2025 and ended as August 6, 2025.
- How it ended
- Awarded to Coastal Environmental Technologies Ltd. on August 12, 2025, 6 days after offers were due. The contracting office reported 8 offers (full and open competition after exclusion of sources).
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
The purpose of this modification is to respond request for information as well as extend
the date and time of offer due as follows:
a. Offers submission due date is hereby extended to August 6th, 2025 @0900.
b. Response to request for information posted on attachment
A contractor shall provide a New York and/or Environmental Protection Agency (EPA) qualified and licensed lead abatement specialist to provide all management, tools, supplies, notification(s), equipment and labor necessary to perform lead abatement at Wiley Halls Dean, Reception Offices, Deans Bathroom and Hall #4 in accordance with all federal, state and local laws and regulations. See SOW for additional details.
Statement of Work (SOW)
Wiley Hall 2ⁿᵈ Deck Dean & Reception Offices Lead Paint Abatement / Remediation
1. Description of Services
A contractor shall provide a New York and/or Environmental Protection Agency (EPA) qualified and
licensed lead abatement specialist to provide all management, tools, supplies, notification(s),
equipment and labor necessary to perform lead abatement at Wiley Hall’s Dean, Reception Offices,
Dean’s Bathroom and Hall #4 in accordance with all federal, state and local laws and regulations.
2. General Requirements
a. Abatement and disposal shall be in accordance with all federal, state and local laws and
regulations including but not limited to requirements established by 40 CFR Part 745, EPA
(Renovation, Repair, and Painting (RRP) Rule), D.O.T. (49 C.F.R. § 173), and RCRA.
b. The contractor shall possess and provide current proof of all federal, state and local
trainings, license(s) and certification(s) including but not limited to the RRP, be registered with
the EPA and be licensed as a lead abatement contractor through either New York and/or EPA.
c. The contractor shall submit a “Occupant Protection Plan” to the Contracting Officer
Representative (COR), Public Safety Department, and Department of Public Works (DPW).
d. The designated work area(s) must be sealed from neighboring occupied areas of the
Quarter/academy with the appropriate barriers (i.e., plastic) and hazard notifications (warning
signs) per federal, state and local laws and regulations throughout the duration of the project
until final clearance has been achieved.
e. All work must be completed using wet methods per federal, state and local laws and regulations.
f. Apply a lead encapsulation paint or primer, over all surfaces to be painted, in accordance with
manufacturer’s instructions. The contractor shall use an EPA approved lead encapsulant and provide
SDS for all products used throughout the project.
g. Given the sensitive nature of these areas (occupied resident), USMMA is requiring all work to be
done in a negative pressure enclosure to minimize impact to building occupants and operations.
h. All work must be completed using HEPA vacuum with a minimum filter requirement capable of
capturing particulates of 0.3 microns with 99.97% efficiency and in
conjunction with all federal, state and local laws and regulations.
i. Throughout the duration of the abatement/remediation project, the work area(s) must be
contained until a formal lead clearance is completed. USMMA’s contracted hygienist shall be on-site
to conduct oversight of the lead abatement process, perform air monitoring, and the final lead
clearance. The clearance levels for dust wipes per the EPA’s Hazard Standards and Clearance Levels
for Lead in Paint, Dust and Soil requirements are as followed:
a. 10 ug/ft2 – floors
b. 100 ug/ft2 – window sills and troughs
j. All work and clearances must be coordinated with the USMMA’s MARAD, COR, Public Safety
Department, DPW and contracted IH. If clearance levels are not achieved in accordance with federal,
state and local laws and regulations, the contractor shall perform an environmental re-cleaning and
undergo another lead clearance process at no additional cost incurred to the government. If
required, this process will be repeated until acceptable levels are achieved in accordance with all
federal, state and local laws and regulations.
k. The work area must be cordoned off per federal and state laws and regulations with clearly
visible barriers (i.e., caution tape) where only authorized and trained individuals related to the
abatement project may enter.
l. Establish a containment area in accordance with federal and state laws and regulations, to
fully separate the work area from other areas of the building. Maintain and identify emergency
exit(s) from the work area or establish alternate exit(s) compliant with all federal, state and
local laws and regulations.
m. The contractor will ensure academy occupants are protected at all times and prevent any
potential lead and/or lead dust contamination in accordance with all federal, state and local laws
and regulations.
n. All electrical equipment shall be run through Ground Fault Interrupt Circuit (GFCI) throughout
the course of the project.
o. The contractor shall be responsible for installation and connection of all temporary utilities
required to complete the abatement. The contractor shall ensure all electrical equipment run
through Ground Fault Interrupt Circuit (GFCI) throughout the duration of the project. DPW personnel
will show the contractor where to connect to water and power. The contractor shall provide and
install temporary GFCI panels for electrical service.
p. The contractor shall secure infrastructure equipment (i.e., HVAC system) and all other relevant
equipment to prevent contamination in neighboring areas per federal, state and local laws and
regulations.
q. Provide accurate and complete waste manifest(s) for lead disposal in accordance with all
federal, state and local laws and regulations.
r. Provide copies of all federal, state and local notifications.
s. Provide accurate records of abatement completion.
3. Additional Notes
a. Start Date: To be determined (Upon USMMA Contracting Officer’s (CO) award of contract).
Completion Date: 4 days after award of contract.
The completion date includes but is not limited to the submittal process, performance of the work,
final air clearance, inspection, waste disposal and waste manifest delivery.
b. A full work plan must be prepared in advance and submitted to the COR, Public Safety, DPW, and
contracted IH for approval. The plan must be approved at least two
(2) business days prior to commencement of work.
c. All work must be scheduled with the COR at least 48 hours prior to commencement.
d. The academy must be immediately notified of any service and/or activity interruptions. Any
potential unforeseen interruptions or issues must be immediately related to the COR, Public Safety
Department, and DPW.
e. A pre-bid onsite walkthrough with the DPW, COR, and Public Safety Department will be conducted
to identify and mark the proposed area where removal / abatement will take place. The contractor
will become familiar with on-sight conditions and restrictions. The square footage identified in
the SOW are approximations and will need to be assessed and verified by the contractor during the
walkthrough and incorporated into the bid submission. The contractor is responsible for verifying
quantities and locations where all work is to be performed. Failure to do so shall not relieve the
contractor of its obligation to furnish all labor and materials necessary to perform the work.
f. All work including but not limited to on-site assessment(s) and document review(s), must be
completed between normal business hours of operation (7am – 4pm), Monday – Friday, unless
additional approval is granted by the CO and COR.
g. Any debris generated during abatement activities will be removed by the contractor daily from
the affected area(s) and academy premises. Area(s) will be left neat and clean daily and after work
is completed, suitable for all normal academy activities.
3
h. Contractor must properly dispose of waste in accordance with all RCRA requirements.
Documentation of this disposal shall be provided to the COR and Public Safety.
i. The contractor will be required to abate (remove) the paint materials from the indicated areas.
If the paint cannot be removed while still leaving a clean, smooth and paintable surface, the
contractor will be required to remove building material (i.e. wood pieces) in its entirety for the
selected areas and replace with similar material that meet all regulatory and industry standards.
j. Square Footage of removal areas include:
• Dean’s Office (207): ~ 399 SF
• Reception’s Office (206): ~ 378 SF
• Dean’s Bathroom (207A): ~76 SF
• Hall #4 (208B): ~25 SF
These areas will be outlined at the time of the on-site walkthrough. Abatement shall occur to
include removal of the selected areas and outlining materials (i.e., paint or marker).
k. The contractor shall assume full responsibility and liability for compliance with all applicable
federal, state and local regulations related to any and all aspects of the project.
l. The contractor is responsible for ensuring client satisfaction throughout the duration of the
project. Any discrepancies, issues and concerns identified by the client originating from the
contractor will be addressed, documented and corrected in a timely manner.
Note: The contractor is responsible for any subcontractors that may be used throughout this
project. Subcontractors are required to adhere to all the requirements set forth within this SOW.
4
4. Images of Area of Concern
Dean’s Office (207): ~ 399 SF
Reception’s Office (206): ~ 378 SF Dean’s Bathroom (207A): ~76 SF Hall #4 (208B): ~25
PLEASE SEE ATTACHED SITE PICTURES
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- FBO NOTICE SF 1449 6923G225Q000011 WILEY HALL LEAD ABATEMENT.pdf4.3 MB, July 22, 2025
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- UEI
- PF82SXJ1J5C5
- CAGE
- 1PSL7
- Vendor location
- Brentwood, NY
- Contract
- 6923G225P000147, purchase order
- Obligated
- $37,532.00
- Actions
- 3 between August 12, 2025 and September 30, 2025
- Competition
- Full and Open Competition After Exclusion of Sources, 8 offers received
- Set-aside reported
- Small Business Set Aside - Total
- Described as
- A Contractor Shall Provide a New York And/Or Environmental Protection Agency (Epa) Qualified and Licensed Lead Abatement Specialist to Provide All Management, Tools, Supplies, Notification(S), Equipment and Labor Necessary to Perform Lead Abatement a
- Match
- solicitation number 6923G225Q000011 equals the FPDS solicitation identifier; same awarding office 6923G2 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
July 22, 2025
Combined synopsis and solicitation
Due July 29, 2025 at 9:00 AM EDT. SAM.gov, notice 94fc620484d8425da6b7133e17c47436
4 revisions on SAM
- July 31, 2025: publish, combined synopsis and solicitation
- July 25, 2025: publish, combined synopsis and solicitation
- July 24, 2025: publish, combined synopsis and solicitation
- July 22, 2025: publish, combined synopsis and solicitation
July 24, 2025
Combined synopsis and solicitation
Due July 31, 2025 at 9:00 AM EDT. SAM.gov, notice 40a49e6cd9b24dd1920fc8d622eaa8eb
4 revisions on SAM
- July 31, 2025: publish, combined synopsis and solicitation
- July 25, 2025: publish, combined synopsis and solicitation
- July 24, 2025: publish, combined synopsis and solicitation
- July 22, 2025: publish, combined synopsis and solicitation
July 25, 2025
Combined synopsis and solicitation
Due July 31, 2025 at 9:00 AM EDT. SAM.gov, notice 20bda56906a74524891c0303f7c3bc05
4 revisions on SAM
- July 31, 2025: publish, combined synopsis and solicitation
- July 25, 2025: publish, combined synopsis and solicitation
- July 24, 2025: publish, combined synopsis and solicitation
- July 22, 2025: publish, combined synopsis and solicitation
July 31, 2025
Combined synopsis and solicitation
Due August 6, 2025 at 9:00 AM EDT. SAM.gov, notice b20c9bdfadfe449ba8cfe675b46df978
4 revisions on SAM
- July 31, 2025: publish, combined synopsis and solicitation
- July 25, 2025: publish, combined synopsis and solicitation
- July 24, 2025: publish, combined synopsis and solicitation
- July 22, 2025: publish, combined synopsis and solicitation
Points of contact
- CARMEN I. FELIZFELIZC@USMMA.EDU5167266149
- Amit S. NarineNarineA@usmma.edu5167266032