# S. J. Amoroso Construction Co., LLC

Canonical: https://sealedbidder.com/vendors/s-j-amoroso-construction-co-llc-ku19cnlck2k7

- UEI: KU19CNLCK2K7
- CAGE: 4FBW4
- Location: Redwood City, CA
- Awards in window: 6 (73 transactions), $268,225,739 obligated, January 8, 2024 to July 21, 2026

## Awarding agencies

- Department of the Army: 3 awards, $198,173,369
- Department of Veterans Affairs: 3 awards, $70,052,370

## Industries

- 236220 Commercial and Institutional Building Construction: $268,225,739

## Competition

- Full and Open Competition: 6 awards

## Solicitations won

- Boiler Plant west Los Angeles (36C10F24R0018), $68,877,000. https://sealedbidder.com/opportunities/36c10f24r0018
- DVA Livermore Phase A Community Living Center (W9123824R0002), $166,034,000. https://sealedbidder.com/opportunities/w9123824r0002
- Mod #6 PAD B100 CathLab-Hybrid (36C26122C0022), $86,602. https://sealedbidder.com/opportunities/36c26122c0022

## Largest awards

- W9123825C0001 (definitive contract): $178,332,315, W075 Endist Sacramento. Dva Livermore Pha - CLC. https://www.usaspending.gov/award/CONT_AWD_W9123825C0001_9700_-NONE-_-NONE-/
- 36C10F25C0001 (definitive contract): $69,636,302, Office of Construction & Facilities MGMT. New Boiler Plant at the VA Medical Center, West Los Angeles, Ca. https://www.usaspending.gov/award/CONT_AWD_36C10F25C0001_3600_-NONE-_-NONE-/
- W912PL19C0001 (definitive contract): $12,380,481, W075 Endist Los Angeles. Contract for Community Living Center, Long Beach, Ca 90822. R00159/CC488 Time Extension -Weather Delay (Feb 2024). Total Contract Price Is Unchanged. the Contract Completion Date Shall Be Extended by 15 Calendar Days by Reason of This Modification.. https://www.usaspending.gov/award/CONT_AWD_W912PL19C0001_9700_-NONE-_-NONE-/
- W9123819C0013 (definitive contract): $7,460,573, W075 Endist Sacramento. Construct Cboc Fund Cite a. https://www.usaspending.gov/award/CONT_AWD_W9123819C0013_9700_-NONE-_-NONE-/
- 36C26122C0022 (definitive contract): $406,068, 261-Network Contract Office 21. VA Palo Alto Building 100 Catheterization Laboratory / Hybrid Operating Room Suite Renovation and Installation of Rooftop Ahu. https://www.usaspending.gov/award/CONT_AWD_36C26122C0022_3600_-NONE-_-NONE-/
- 36C10F26P0007 (purchase order): $10,000, Office of Construction & Facilities MGMT. Payment of Stipend for Solicitation Participation for Sepulveda Ar Design-Build. https://www.usaspending.gov/award/CONT_AWD_36C10F26P0007_3600_-NONE-_-NONE-/

---
Source: USAspending.gov award data, keyed by UEI. Obligations in the window only. Cite https://sealedbidder.com/vendors/s-j-amoroso-construction-co-llc-ku19cnlck2k7.