# Pinal Construction, LLC

Canonical: https://sealedbidder.com/vendors/pinal-construction-llc-jckcjkmfytp5

- UEI: JCKCJKMFYTP5
- CAGE: 859K8
- Location: Casa Grande, AZ
- Awards in window: 6 (6 transactions), $782,465 obligated, February 7, 2024 to August 17, 2026

## Awarding agencies

- Public Buildings Service: 1 awards, $519,000
- Agricultural Research Service: 5 awards, $263,465

## Industries

- 238320 Painting and Wall Covering Contractors: $519,000
- 236220 Commercial and Institutional Building Construction: $165,125
- 237110 Water and Sewer Line and Related Structures Construction: $54,215
- 562998 All Other Miscellaneous Waste Management Services: $24,875
- 237310 Highway, Street, and Bridge Construction: $19,250

## Competition

- Competed Under SAP: 5 awards
- Not Competed Under SAP: 1 awards

## Solicitations won

- SunShade Panel Powder Coating (47PD5526Q0034). https://sealedbidder.com/opportunities/47pd5526q0034
- CAG Perimeter Fence Relocation (89503126QWA000397), $35,650. https://sealedbidder.com/opportunities/89503126qwa000397
- Solicitation for Upgrade of Three Greenhouses for USDA ARS in Maricopa, AZ (12905B25Q0013). https://sealedbidder.com/opportunities/12905b25q0013
- 12905B24Q0218 Questions/Responses 3rd Upload - Combo Synopsis/Solicitation Evaporation Pond Maintenance/Cleaning USDA-ARS Maricopa AZ (12905B24Q0218). https://sealedbidder.com/opportunities/12905b24q0218
- USDA-ARS-PWA Install ABC Road/Ramp and Sidewalks Maricopa AZ (12905B24Q0026). https://sealedbidder.com/opportunities/12905b24q0026

## Largest awards

- 47PD5526C0032 (definitive contract): $519,000, PBS Project Delivery West - Branch E. Remove, Repair, Powder Coat, Re-Install Sunshade Panels at Mariposa Lpoe, Nogales Az. https://www.usaspending.gov/award/CONT_AWD_47PD5526C0032_4740_-NONE-_-NONE-/
- 12905B25P0019 (purchase order): $165,125, USDA ARS Pwa Aao Acq/Per Prop. Upgrade/ Rebuild of Three Greenhouses. https://www.usaspending.gov/award/CONT_AWD_12905B25P0019_12H2_-NONE-_-NONE-/
- 12905B24P0132 (purchase order): $34,560, USDA ARS Pwa Aao Acq/Per Prop. Replacement of Lab Wastewater Discharge Piping.. https://www.usaspending.gov/award/CONT_AWD_12905B24P0132_12H2_-NONE-_-NONE-/
- 12905B24P0182 (purchase order): $24,875, USDA ARS Pwa Aao Acq/Per Prop. Evap Pond Maintenance & Cleaning. https://www.usaspending.gov/award/CONT_AWD_12905B24P0182_12H2_-NONE-_-NONE-/
- 12905B24P0028 (purchase order): $19,655, USDA ARS Pwa Aao Acq/Per Prop. Repair Main Water Supply Pipe. https://www.usaspending.gov/award/CONT_AWD_12905B24P0028_12H2_-NONE-_-NONE-/
- 12905B24P0033 (purchase order): $19,250, USDA ARS Pwa Aao Acq/Per Prop. Install Abc Access Road/Ramp to Concrete Pads. https://www.usaspending.gov/award/CONT_AWD_12905B24P0033_12H2_-NONE-_-NONE-/

---
Source: USAspending.gov award data, keyed by UEI. Obligations in the window only. Cite https://sealedbidder.com/vendors/pinal-construction-llc-jckcjkmfytp5.