Vendor, Columbus, GA
Columbus Barricades, Inc.
UEI P8NLNNTHZ3L9, CAGE 4KDS3
46 awards and $17,614,918 obligated between January 26, 2024 and May 28, 2026, 87% under full and open competition, against 2.0 offers on average where reported.
Industries
NAICS on the awards, by dollars.
| Highway, Street, and Bridge ConstructionNAICS 237310 | $17,614,918 |
How it wins
Awards by competition, set-aside and type.
| Full and Open Competition After Exclusion of Sources | 40 |
| Competed Under SAP | 6 |
| Small Business Set Aside - Total | 1 |
| Delivery Order | 45 |
Hear when Columbus Barricades, Inc. wins an award and when a contract it holds is about to end.Follow it
Contracts ending soon
Contracts Columbus Barricades, Inc. holds whose performance ends in the next 19 months, by published end date. Each one is a recompete to prepare for.
- Ending
- 5
- Obligated so far
- $4,451,587
- Soonest
- December 31, 2026
The 5 contracts, the office behind each one and the dates are in the workspace. See them
Competes with
Vendors selling highway, street, and bridge construction to Department of the Army, by dollars.
| R. C. Construction Co., Inc.Greenwood, MS | $182,365,788 |
| JV Ske Italy 2012Vicenza | $58,002,977 |
| R&i Construction, Inc.Aiea, HI | $41,813,289 |
| Mountain Point, LLCChantilly, VA | $36,473,879 |
| FM Mccarthy, LLCChicago, IL | $35,554,433 |
| Strabag Epitoipari Zartkoruen Mukodo ReszvenytarsasagBudapest | $35,378,306 |
Awards
Every award in the window, by dollars obligated.
| Contract | Awarding office | Described as | Obligated |
|---|---|---|---|
| W911SF25FA124Delivery Order, September 16, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Jecelin, 82ND Division Road, Shoulder Improvements and Bike Lane Addition as Shown in the 35% Design Drawings.NAICS 237310, PSC Z1LB | $2,044,850 |
| W911SF24F0191Delivery Order, September 24, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | 1001 Construct Acft Turf Fields 3NAICS 237310, PSC Z1LB | $1,605,309 |
| W911SF25FA102Delivery Order, August 29, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Motor Pool, Building 2781 as Shown in the 35% Design Drawings and Per the Scope of Work.NAICS 237310, PSC Z1LB | $1,288,912 |
| W911SF25FA148Delivery Order, September 29, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Lindsey Creek Shoulders, Upatoi Creek to Marne Road as Shown in the 5% Design Drawings Per the Statement of Work.NAICS 237310, PSC Z1LB | $1,185,535 |
| W911SF25FA137Delivery Order, September 19, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Construct Sidewalk, 2ND Armor Division Road as Shown in the 35% Design Drawings.NAICS 237310, PSC Z1LB | $913,618 |
| W911SF25FA126Delivery Order, September 16, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Sightseeing Road Culvert as Shown in the 35% Design Drawings.NAICS 237310, PSC Z1LB | $841,454 |
| W911SF24F0129Delivery Order, September 10, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Construct AcftNAICS 237310, PSC Z1LB | $741,035 |
| W911SF26FA033Delivery Order, May 11, 2026, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Statement of Work (Sow)NAICS 237310, PSC Z1AB | $669,427 |
| W911SF26FA036Delivery Order, May 11, 2026, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair the Failing Asphalt Surface of Cusseta Road Along the Sections That Are Identified in the Drawing Sheets. This Repair Also Includes tNAICS 237310, PSC Z1LB | $661,069 |
| W911SF24F0189Delivery Order, September 24, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | 1001 Construct Bike Trail, Cif to WTCNAICS 237310, PSC Z1LB | $590,897 |
| W911SF25F0022Delivery Order, February 27, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repave Rykus Ave and Gravel RoadsNAICS 237310, PSC Z1LB | $573,836 |
| W911SF25FA128Delivery Order, September 18, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Lindsey Creek Shoulders, Acp to Upatoi Creek as Shown in the 35% Design Drawings.NAICS 237310, PSC Z1LB | $572,106 |
| W911SF25FA130Delivery Order, September 18, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Outfall, Legacy Blvd.NAICS 237310, PSC Z1LB | $526,519 |
| W911SF24F0049Delivery Order, August 21, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Restriping Lindsey Creek ParkwayNAICS 237310, PSC Z1LB | $515,996 |
| W911SF24F0133Delivery Order, September 13, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repave Camp Darby and Rogers Roads,NAICS 237310, PSC Z1LB | $506,484 |
| W911SF24F0178Delivery Order, September 20, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Slope Failure, Eastern Horse BowlNAICS 237310, PSC Z1LB | $441,679 |
| W911SF24F0130Delivery Order, September 10, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Replace Inground Scales LaafNAICS 237310, PSC Z1LB | $440,047 |
| W911SF25FA104Delivery Order, September 5, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Kall River Tank Drivers Course as Shown in the 35% Drawings and Sketches Per the Scope of Work.NAICS 237310, PSC Z1LB | $361,355 |
| W911SF25FA136Delivery Order, September 19, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repave Interior Asp Roads, B6000.NAICS 237310, PSC Z1LB | $356,923 |
| W911SF23F0170Delivery Order, July 16, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Install Davis Hill RD Recreation TrailNAICS 237310, PSC Z1LB | $337,155 |
| W911SF26FA010Delivery Order, April 13, 2026, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Scope of Work.NAICS 237310, PSC Z1LB | $330,246 |
| W911SF24F0179Delivery Order, September 20, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Brown Ramp Trench BoxesNAICS 237310, PSC Z1LB | $310,403 |
| W911SF25FA127Delivery Order, September 19, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Hourglass Road, Tricolor Road as Shown in the 35% Design Drawings.NAICS 237310, PSC Z1LB | $266,921 |
| W911SF24F0123Delivery Order, September 6, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repave Burroughs Range Access RoadNAICS 237310, PSC Z1LB | $264,437 |
| W911SF24F0187Delivery Order, September 24, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | 1001 Construct Bike Trail, RiverwalkNAICS 237310, PSC Z1LB | $233,545 |
| W911SF24F0122Delivery Order, September 10, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Lindsey Creek RampsNAICS 237310, PSC Z1LB | $232,456 |
| W911SF24F0188Delivery Order, September 24, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Construct Bike Trail, Marne RD toNAICS 237310, PSC Z1LB | $203,412 |
| W911SF22F0153Delivery Order, April 12, 2024, Competed Under SAP | W6QM Micc-Ft BenningDepartment of the Army | Repair PRKG Area Hanger Atc Tower Additional Unforeseen WorkNAICS 237310, PSC Z1LB | $182,886 |
| W911SF23F0162Delivery Order, January 5, 2026, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Restripe Parking Lot B6. This Is a Modification to Extend the Pop to 30 June 2026.NAICS 237310, PSC Z1LB | $171,609 |
| W911SF24F0182Delivery Order, September 23, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Upgrade Power/Berm Mat 202 CarmouchNAICS 237310, PSC Z1LB | $116,158 |
| W911SF24F0119Delivery Order, September 6, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Restriping Dilboy, Vibbert, and Wold AveNAICS 237310, PSC Z1LB | $116,088 |
| W911SF25FA026Delivery Order, May 29, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Iaw the Sow Attached Furnish All Labor, Equipment, Incidentals Supervision and Transportation for Work Necessary to Geotechnical Analysis anNAICS 237310, PSC Y1EB | $64,148 |
| W911SF23F0097Delivery Order, September 18, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Culvert, Craig DriveNAICS 237310, PSC Z1LB | $41,650 |
| W911SF23F0194Delivery Order, February 25, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Pavement Contract-Base Ordering PeriodNAICS 237310, PSC Z1LB | $28,971 |
| W911SF22F0202Delivery Order, February 15, 2024, Competed Under SAP | W6QM Micc-Ft BenningDepartment of the Army | Repair Marchant RoadNAICS 237310, PSC Z1LB | $17,679 |
| W911SF23F0193Delivery Order, January 5, 2026, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Tennis and Pickleball Court. Modification to Extend the Pop to 30 June 2026.NAICS 237310, PSC Z1LB | $11,940 |
| W911SF22F0031Delivery Order, December 6, 2024, Competed Under SAP | W6QM Micc-Ft BenningDepartment of the Army | 3001 Repair Covered Box Trench SystemNAICS 237310, PSC Z1LB | $0 |
| W911SF23F0060Delivery Order, January 26, 2024, Competed Under SAP | W6QM Micc-Ft BenningDepartment of the Army | Repair Runway 15-33 from Sta 15+33 to 56NAICS 237310, PSC Z1LB | $0 |
| W911SF23F0128Delivery Order, December 30, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Modification to Extend the Pop to 31 March 2026.NAICS 237310, PSC Z1LB | $0 |
| W911SF23F0134Delivery Order, March 24, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Lincoln & IngersollNAICS 237310, PSC Z1LB | $0 |
| W911SF23F0135Delivery Order, February 24, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repave Sightseeing Rd/Benjamin STNAICS 237310, PSC Z1LB | $0 |
| W911SF23F0140Delivery Order, July 16, 2024, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Repair Installation Roads Riordan StreetNAICS 237310, PSC Z1LB | $0 |
| W911SF23F0203Delivery Order, April 4, 2025, Full and Open Competition After Exclusion of Sources | W6QM Micc-Ft BenningDepartment of the Army | Pavement Contract-Base Ordering PeriodNAICS 237310, PSC Z1LB | $0 |
| W911SF23D0002June 12, 2024, Full and Open Competition After Exclusion of Sources, 2 offers | W6QM Micc-Ft BenningDepartment of the Army | Pavement Contract-Base Ordering PeriodNAICS 237310, PSC Z1LB | $0 |
| W911SF21F0054Delivery Order, May 29, 2024, Competed Under SAP | W6QM Micc-Ft BenningDepartment of the Army | Repair Keel Section of LaafNAICS 237310, PSC Z1LB | -$66,526 |
| W911SF20F0199Delivery Order, May 28, 2024, Competed Under SAP | W6QM Micc-Ft BenningDepartment of the Army | Repair Failing Pipe at LaafNAICS 237310, PSC Z1LB | -$85,309 |
- Places of performance
- Georgia
- Product and service codes
- Z1LB Maintenance Of Highways/Roads/Streets/Bridges/RailwaysZ1AB Maintenance Of Conference Space And FacilitiesY1EB Construction Of Maintenance Buildings
- Transactions
- 72 across 46 awards