# Barry Williams Electric Inc.

Canonical: https://sealedbidder.com/vendors/barry-williams-electric-inc-jkrfpndspcd5

- UEI: JKRFPNDSPCD5
- CAGE: 3LTA0
- Location: Waco, TX
- Awards in window: 170 (257 transactions), $9,165,567 obligated, February 12, 2024 to November 23, 2026

## Awarding agencies

- Federal Aviation Administration: 170 awards, $9,165,567

## Industries

- 238210 Electrical Contractors and Other Wiring Installation Contractors: $6,654,394
- 335910 Battery Manufacturing: $2,511,173

## Competition

- Competed Under SAP: 93 awards
- Full and Open Competition: 77 awards

## Largest awards

- 6973GH25F01106 (delivery order): $835,724, 6973GH Franchise Acquisition SVCS. Iija Funds. Site Specific Installation Cost for Eg and FST Replacement, Erms Installation and Full Power System Study at Oilton, TX (Qza) Arsr JCN:23007873. https://www.usaspending.gov/award/CONT_AWD_6973GH25F01106_6920_6973GH22D00007_6920/
- 6973GH26F00257 (delivery order): $439,031, 6973GH Franchise Acquisition SVCS. Replace the Existing Engine Generator (Eg) with a Kohler 40KW Propane Eg, Install the Erms Wiring, Update the Existing Uninterrupted Power System (Ups) with an Eaton 93PM-L Ups, Modify the Lightning Protection Grounding Bonding System (Lpgbs), and Co. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00257_6920_6973GH22D00007_6920/
- 6973GH26F01322 (delivery order): $421,557, 6973GH Franchise Acquisition SVCS. Site: Watford City, ND (Qwa) Arsr Jcn: 24012600 _______________________________________________ "coordination Must Be Made Within Four (4) Calendar Days After Reciept of Task Order" _______________________________________________ Poc:. https://www.usaspending.gov/award/CONT_AWD_6973GH26F01322_6920_6973GH22D00007_6920/
- 6973GH26F00542 (delivery order): $402,192, 6973GH Franchise Acquisition SVCS. Iija Funds. Eg Install, Full Power System Study and Erms Funding at Chelsea, Ok (Qaf) Atcbi JCN:23007870. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00542_6920_6973GH22D00007_6920/
- 6973GH23F01839 (delivery order): $369,557, 6973GH Franchise Acquisition SVCS. Bil Funding, Additional Designs to Incorporate Advanced Metering at Lubbock, TX (Lbbc) Atct Jcn: 19003435. https://www.usaspending.gov/award/CONT_AWD_6973GH23F01839_6920_6973GH22D00007_6920/
- 6973GH26F00338 (delivery order): $328,674, 6973GH Franchise Acquisition SVCS. Iija Funded. Nashwauk, MN (Qjd) Arsr JCN:19004780 This Unilateral Award Is for the Construction Cost of the Ups and Ups Ancillary Equipment Removal and Installation and Electrical, Lighting, and Service Supply Equipment Upgrade at Nashwauk, MN (Qjd). https://www.usaspending.gov/award/CONT_AWD_6973GH26F00338_6920_6973GH22D00007_6920/
- 6973GH25F01432 (delivery order): $312,000, 6973GH Franchise Acquisition SVCS. To Fund the Fuel Storage Tank (Fst) Replacement at LCH Asr.. https://www.usaspending.gov/award/CONT_AWD_6973GH25F01432_6920_6973GH22D00007_6920/
- 6973GH26F00872 (delivery order): $302,291, 6973GH Franchise Acquisition SVCS. Iija Funded This Unilateral Award Is for the Construction Cost of the Ups and Ups Ancillary Equipment Removal and Installation at Warrenton, VA (Pct) Tracon Which Includes a Partial Power Systems Study of the Facility. JCN:18065275. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00872_6920_6973GH22D00007_6920/
- 6973GH22F01699 (delivery order): $294,485, 6973GH Franchise Acquisition SVCS. Iija Funds. Site Specific Funding for the Outdoor Eg with Subbase Tank Installation, Erms Installation and Full Power System Studies at Albuquerque, NM (Abqf) Asr JCN:22002452. https://www.usaspending.gov/award/CONT_AWD_6973GH22F01699_6920_6973GH22D00007_6920/
- 6973GH24F00921 (delivery order): $247,402, 6973GH Franchise Acquisition SVCS. DC Systems Battery Equipment Purchase and Installation at DAL-FT Worth, TX (D10) Cpds, JCN:20011703, Houston, TX (Zhu) Cpds, JCN:22006503, Albuquerque, NM (Zab) Cpds, JCN:22006491, & Fort Worth, TX (Zfw) Cpds, JCN:21002094 *quotes Do Not Matc. https://www.usaspending.gov/award/CONT_AWD_6973GH24F00921_6920_6973GH24D00021_6920/
- 6973GH24F00906 (delivery order): $246,416, 6973GH Franchise Acquisition SVCS. Bil Funds. Initial Installation Funding for the Indoor Eg, Propane FST and Erms at the Westminster, MD (Emi) Vor. JCN:23009034. https://www.usaspending.gov/award/CONT_AWD_6973GH24F00906_6920_6973GH22D00007_6920/
- 6973GH22F01650 (delivery order): $209,256, 6973GH Franchise Acquisition SVCS. Iija Funds. Site-Specific Pricing to Remove the Existing 175KW Indoor Eg and All Its Associated Parts and Replace with a 200KW Outdoor with Subbase Eg 277/480V, 3PH Iaw the Approved Drawings Dated 1/10/2025 and the 2022 125KW Eg Outdoor Baseline, Er. https://www.usaspending.gov/award/CONT_AWD_6973GH22F01650_6920_6973GH22D00007_6920/
- 6973GH26F00896 (delivery order): $200,354, 6973GH Franchise Acquisition SVCS. Ops Funded Demo and Install for Electrical Refurbishment Project at (Gjt)arsr in Grand Junction, Co., Jcn: 18062203 Per Ndp, Pmo. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00896_6920_6973GH22D00007_6920/
- 6973GH23F01841 (delivery order): $189,566, 6973GH Franchise Acquisition SVCS. Bil Funds. Adding Advanced Metering Into the Eg Design for Salina, KS (Slnc) Atct Jcn: 19003449. https://www.usaspending.gov/award/CONT_AWD_6973GH23F01841_6920_6973GH22D00007_6920/
- 6973GH22F01709 (delivery order): $186,677, 6973GH Franchise Acquisition SVCS. Iija Funds. Site Specific Installation, Erms and Power Systems Studies for San Antonio, TX (Ant) Als JCN:22002701. https://www.usaspending.gov/award/CONT_AWD_6973GH22F01709_6920_6973GH22D00007_6920/
- 6973GH24F00794 (delivery order): $181,058, 6973GH Franchise Acquisition SVCS. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Birmingham, Al (Bhm) Asr Per the RFQ-24-14 Bid Package. JCN:18065584. https://www.usaspending.gov/award/CONT_AWD_6973GH24F00794_6920_6973GH22D00007_6920/
- 6973GH24F00389 (delivery order): $170,884, 6973GH Franchise Acquisition SVCS. Bil Funds. Ups Installation. JCN:18066554, Qha Arsr, Cummington Ma. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at (Qha) Arsr Per RFQ-24-08 Bid Package.. https://www.usaspending.gov/award/CONT_AWD_6973GH24F00389_6920_6973GH22D00007_6920/
- 6973GH24F00424 (delivery order): $168,209, 6973GH Franchise Acquisition SVCS. Ups Installation. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at Charlottesville, VA (Cho) Asr Per RFQ-24-09 Bid Package. JCN:18065451. https://www.usaspending.gov/award/CONT_AWD_6973GH24F00424_6920_6973GH22D00007_6920/
- 6973GH22F01655 (delivery order): $164,285, 6973GH Franchise Acquisition SVCS. Bil Funding, Site Specific Costs for the 100KW Eg Installation, Erms Install, Upgrade to a Full Power System Study and the Installation of the Advanced Metering at Longview, TX (Ggga) Atct. JCN:22001757. https://www.usaspending.gov/award/CONT_AWD_6973GH22F01655_6920_6973GH22D00007_6920/
- 6973GH24F01306 (delivery order): $148,950, 6973GH Franchise Acquisition SVCS. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Longview, TX (Ggg) Asr Per the RFQ-24-20 Bid Package Includes Full Afha. JCN:21001003. https://www.usaspending.gov/award/CONT_AWD_6973GH24F01306_6920_6973GH22D00007_6920/
- 6973GH23F01641 (delivery order): $145,623, 6973GH Franchise Acquisition SVCS. Site Specific Installation Cost Requirements, Including the Removal of the Existing 1,000-Gallon Aboveground Storage Tank (Ast), Aboveground Supply and Return Fuel Lines to the Day Tank, Fuel Monitoring System, and Demolition of the Existing Concrete. https://www.usaspending.gov/award/CONT_AWD_6973GH23F01641_6920_6973GH22D00007_6920/
- 6973GH23F00961 (delivery order): $140,394, 6973GH Franchise Acquisition SVCS. Iija Funds, Site Specific Requirements, Includes the Removal of 2,000-Gallon Ast, Aboveground Supply and Return Fuel Lines to the Day Tank, Fuel Monitoring System, and Concrete FST Pad; and Installation of 1,000-Gallon Ast, Aboveground Supply and Ret. https://www.usaspending.gov/award/CONT_AWD_6973GH23F00961_6920_6973GH22D00007_6920/
- 6973GH26F00244 (delivery order): $138,869, 6973GH Franchise Acquisition SVCS. FST Funded. 2024 DC Bus Demo Baseline Scope: Site Survey Travel and Report, Design and Install Funding at Lynchburg, VA (Lyha) Rcag JCN:24016521. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00244_6920_6973GH22D00007_6920/
- 6973GH26F00237 (delivery order): $137,412, 6973GH Franchise Acquisition SVCS. FST 2024 DC Bus Demo Baseline Site Survey Travel & Report, Design and Install Funding at Gage, Ok (Gaga) Rcag JCN:24016524. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00237_6920_6973GH22D00007_6920/
- 6973GH26F00246 (delivery order): $137,412, 6973GH Franchise Acquisition SVCS. FST Funds. 2024 DC Bus Demo Baseline Scope: Site Survey Travel and Report, Design and Install Funding at Cedar Rapids, Ia (Cid) Rcag Jcn: 24016529. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00246_6920_6973GH22D00007_6920/
- 6973GH25F01253 (delivery order): $124,910, 6973GH Franchise Acquisition SVCS. Iija DC Systems Battery Equipment Purchase and Installation. JCN:25016040 & Loc:qsj Rclr, JCN:25015952 & Loc:qxw Rclr, JCN:25016042 & Loc:qsg Rclr, JCN:25016039 & Loc:qlh Rclr, JCN:25016041 & Loc:qsk.. https://www.usaspending.gov/award/CONT_AWD_6973GH25F01253_6920_6973GH24D00021_6920/
- 6973GH24F00509 (delivery order): $110,772, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Keller, TX (Ftwg) Arsr Per the RFQ-24-13 Bid Package. JCN:18032986. https://www.usaspending.gov/award/CONT_AWD_6973GH24F00509_6920_6973GH22D00007_6920/
- 6973GH25F00044 (delivery order): $107,800, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Texarkana, Ar (Txk) Arsr Per the RFQ-24-24 (AR1) Bid Package. Jcn: 18066399 Includes Option #1 Full Arc Flash Hazard Analysis (Afha) of the Facilit. https://www.usaspending.gov/award/CONT_AWD_6973GH25F00044_6920_6973GH22D00007_6920/
- 6973GH25F00280 (delivery order): $102,439, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Fayetteville (Fyv) Asr (AR2) Per the RFQ-25-02 Bid Package. Jcn: 21000078 Includes Option #1 Full Arc Flash Hazard Analysis (Afha) of the Facility.. https://www.usaspending.gov/award/CONT_AWD_6973GH25F00280_6920_6973GH22D00007_6920/
- 6973GH23F00587 (delivery order): $100,271, 6973GH Franchise Acquisition SVCS. Site Specific Installation of 2000-Gallon Ast at Eagle Peak, TX (Qnw) Atct Jcn: 18026736. https://www.usaspending.gov/award/CONT_AWD_6973GH23F00587_6920_6973GH22D00007_6920/
- 6973GH23F00090 (delivery order): $99,154, 6973GH Franchise Acquisition SVCS. Bil: Site Specific Installation of a 1,5000 - Gal Ast Tank at Byhalia, MS (Qyb) Arsr. Jcn: 18027753. https://www.usaspending.gov/award/CONT_AWD_6973GH23F00090_6920_6973GH22D00007_6920/
- 6973GH25F00307 (delivery order): $97,525, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Amarillo, TX (Ama) Asr Per the RFQ-25-03 Bid Package. Jcn: 18066403 Includes Option #1 Full Arc Flash Hazard Analysis (Afha) of the Facility.. https://www.usaspending.gov/award/CONT_AWD_6973GH25F00307_6920_6973GH22D00007_6920/
- 6973GH23F00070 (delivery order): $95,578, 6973GH Franchise Acquisition SVCS. Bil: FST Diesel Site Specific for Haleyville, Al (Qpc) Arsr. Jcn: 18028142. https://www.usaspending.gov/award/CONT_AWD_6973GH23F00070_6920_6973GH22D00007_6920/
- 6973GH24F01028 (delivery order): $93,006, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Atlanta, Ga, Atld Asde Per the RFQ-24-15 Bid Package. JCN:24010012. https://www.usaspending.gov/award/CONT_AWD_6973GH24F01028_6920_6973GH22D00007_6920/
- 6973GH25F00278 (delivery order): $88,674, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Little Rock, Ar (Litc) Atct (AR2) Per the RFQ-25-02 Bid Package. Jcn: 18065822 Includes Option #1 Full Arc Flash Hazard Analysis (Afha) of the Faci. https://www.usaspending.gov/award/CONT_AWD_6973GH25F00278_6920_6973GH22D00007_6920/
- 6973GH24F01525 (delivery order): $88,458, 6973GH Franchise Acquisition SVCS. This Requisition Is for the Installation of Services for Efforts Associated to the System Support Facility (Ssf, Building 196)/Program Support Facility (Psf, Building 201) Uninterruptible Power Supply (Ups) Replacement.. https://www.usaspending.gov/award/CONT_AWD_6973GH24F01525_6920_6973GH22D00007_6920/
- 6973GH26F00670 (delivery order): $85,364, 6973GH Franchise Acquisition SVCS. Iija Funded. Corpus Christi, TX (Crpa) Asr JCN:18066426 This Unilateral Award Is for the Construction Cost of the Ups and Ups Ancillary Equipment Removal and Installation at Corpus Christi, TX (Crpa) Asr Which Includes a Partial Power Systems Study. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00670_6920_6973GH22D00007_6920/
- 6973GH24F00452 (delivery order): $83,987, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at Fargo, ND (Far) Asr Per RFQ-24-05 Bid Package Also Includes a Full Afha. JCN:24009272. https://www.usaspending.gov/award/CONT_AWD_6973GH24F00452_6920_6973GH22D00007_6920/
- 6973GH25F00279 (delivery order): $81,061, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Little Rock, Ar (Lit) Asr (AR2) Per the RFQ-25-02 Bid Package. Jcn: 19004777 Includes Option #1 Partial Arc Flash Hazard Analysis (Afha) of the Fac. https://www.usaspending.gov/award/CONT_AWD_6973GH25F00279_6920_6973GH22D00007_6920/
- 6973GH24F00919 (delivery order): $78,078, 6973GH Franchise Acquisition SVCS. Bil DC Systems Battery Equipment Purchase and Installation. Oberlin, Oh (Zob) Cpds, JCN:23004268. https://www.usaspending.gov/award/CONT_AWD_6973GH24F00919_6920_6973GH24D00021_6920/
- 6973GH25F00043 (delivery order): $77,285, 6973GH Franchise Acquisition SVCS. Bil Funds. Construction Cost of Ups and the Ups Ancillary Equipment Removal and Installation at the Fort Smith, Ar (Fsm) Asr Per the RFQ-24-24 (AR1) Bid Package. Jcn: 18065318 Includes Option #1 Full Arc Flash Hazard Analysis (Afha) of the Facilit. https://www.usaspending.gov/award/CONT_AWD_6973GH25F00043_6920_6973GH22D00007_6920/
- 6973GH23F00069 (delivery order): $71,367, 6973GH Franchise Acquisition SVCS. Bil Funds. Site Specific Diesel Installation at Huntsville, Al (Hsv) Als. Jcn: 1503243. https://www.usaspending.gov/award/CONT_AWD_6973GH23F00069_6920_6973GH22D00007_6920/
- 6973GH23F00717 (delivery order): $64,089, 6973GH Franchise Acquisition SVCS. Bil: Site Specific Change Order for Daisetta, TX (Das) Vor Jcn: 1500535. https://www.usaspending.gov/award/CONT_AWD_6973GH23F00717_6920_6973GH22D00007_6920/
- 6973GH23F00089 (delivery order): $61,713, 6973GH Franchise Acquisition SVCS. Bil Funds, Site Specific Installation at Huntsville, Al (Hsva) Asr. Jcn: 1503244. https://www.usaspending.gov/award/CONT_AWD_6973GH23F00089_6920_6973GH22D00007_6920/
- 6973GH25F01255 (delivery order): $56,573, 6973GH Franchise Acquisition SVCS. Iija DC Systems Battery Equipment Purchase and Installation. JCN:25015953 & Loc:qx7 Rclr, JCN:25016231 & Loc:rdd Rclr.. https://www.usaspending.gov/award/CONT_AWD_6973GH25F01255_6920_6973GH24D00021_6920/
- 6973GH26F00927 (delivery order): $50,067, 6973GH Franchise Acquisition SVCS. Ops Funded (Bgr)atct - Mdpe, Electrical Power Replacement (Mdpe), in Bangor, Me, JCN:25015948, Per Es, Pmo.. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00927_6920_6973GH22D00007_6920/
- 6973GH26F00272 (delivery order): $49,149, 6973GH Franchise Acquisition SVCS. Iija DC Systems Battery Equipment Purchase and Installation. JCN:23001388 & Loc:clea Rtr, JCN:23001391 & Loc:cleg Rtr. Funding BWC for Battery Replacement Projects at Clea and Cleg RTR Sites.. https://www.usaspending.gov/award/CONT_AWD_6973GH26F00272_6920_6973GH24D00021_6920/
- 6973GH23F00071 (delivery order): $48,769, 6973GH Franchise Acquisition SVCS. Iija Funds, Removal of a 2000 - Gal Boiler Ast, Stairs and Platform, Aboveground Supply and Return Fuel Lines, Fuel Monitor System and Components, and Fuel Piping Supports and Stanchions at Oakdale, PA (Pit) Arsr. Jcn: 18028053. https://www.usaspending.gov/award/CONT_AWD_6973GH23F00071_6920_6973GH22D00007_6920/
- 6973GH24F01189 (delivery order): $48,724, 6973GH Franchise Acquisition SVCS. 2024 Outdoor Eg Baseline Site Survey, Design and Install Funding for San Antonio, TX (Anta) Loc Jcn: 22001117. https://www.usaspending.gov/award/CONT_AWD_6973GH24F01189_6920_6973GH22D00007_6920/
- 6973GH26F01163 (delivery order): $47,419, 6973GH Franchise Acquisition SVCS. Eg Funding. Site Survey Travel, Report and Design for the 2025 Outdoor Eg Baseline for Corpus Christi, TX (Crp) Atct JCN:23000618. https://www.usaspending.gov/award/CONT_AWD_6973GH26F01163_6920_6973GH22D00007_6920/

---
Source: USAspending.gov award data, keyed by UEI. Obligations in the window only. Cite https://sealedbidder.com/vendors/barry-williams-electric-inc-jkrfpndspcd5.