# Advancing Resilience in Communities

Canonical: https://sealedbidder.com/vendors/advancing-resilience-in-communities-cp3bu1a33kl7

- UEI: CP3BU1A33KL7
- CAGE: 8RS73
- Location: Moon Township, PA
- Awards in window: 33 (102 transactions), $95,322,789 obligated, February 21, 2024 to November 20, 2026

## Awarding agencies

- Federal Emergency Management Agency: 33 awards, $95,322,789

## Industries

- 541330 Engineering Services: $95,322,789

## Competition

- Full and Open Competition: 33 awards

## Largest awards

- 70FA6024F00000021 (delivery order): $28,173,795, Mitigation Section. FEMA Zone 1 Standard Operations 3 (So 3) Architect and Engineering Services. https://www.usaspending.gov/award/CONT_AWD_70FA6024F00000021_7022_70FA6021D00000003_7022/
- 70FBR224F00000080 (delivery order): $16,595,866, Region 2: Emergency Preparedness an. Region 2 Fiscal Year 24 Production and Technical Services Risk Map Task Order. https://www.usaspending.gov/award/CONT_AWD_70FBR224F00000080_7022_70FA6021D00000003_7022/
- 70FA6026F00000042 (delivery order): $14,749,987, Mitigation Section. This Task Order Will Cover Two Types of Flood Mapping Services. the First Is to Complete Legacy Mapping Projects. the Second Is Demonstrate the Modern Mapping Methodology Developed by FEMA and the United States Army Corps of Engineers (Usace).. https://www.usaspending.gov/award/CONT_AWD_70FA6026F00000042_7022_70FA6021D00000003_7022/
- 70FBR124F00000038 (delivery order): $6,550,296, Region 1: Emergency Preparedness an. Zone 1 Region 1 2024 Risk Map Regional Task Order. https://www.usaspending.gov/award/CONT_AWD_70FBR124F00000038_7022_70FA6021D00000003_7022/
- 70FBR524F00000050 (delivery order): $6,532,178, Region 5 : Emergency Preparedness a. Region 5 Risk Map PTS Zone 1 Task Order for Architect and Engineering Services to Support Risk Mapping, Assessment, and Planning Program.. https://www.usaspending.gov/award/CONT_AWD_70FBR524F00000050_7022_70FA6021D00000003_7022/
- 70FBR324F00000026 (delivery order): $4,905,311, Regoin 3: Emergency Preparedness an. FEMA Region 3 FY24 Riskmap PTS. https://www.usaspending.gov/award/CONT_AWD_70FBR324F00000026_7022_70FA6021D00000003_7022/
- 70FA6024F00000048 (delivery order): $4,483,391, Mitigation Section. PTS Arc Zone 1 National Dam Safety Program Operations Support. https://www.usaspending.gov/award/CONT_AWD_70FA6024F00000048_7022_70FA6021D00000003_7022/
- 70FA6026F00000026 (delivery order): $3,686,251, Mitigation Section. Risk Map Architect and Engineering for National Dam Safety Program (Ndsp) Operations Support in Accordance with the PWS and Qasp Dated 7/17/2026. https://www.usaspending.gov/award/CONT_AWD_70FA6026F00000026_7022_70FA6021D00000003_7022/
- 70FA6025F00000008 (delivery order): $3,049,163, Mitigation Section. PTS Zone 1 Arc Building Sciences Operations Support. https://www.usaspending.gov/award/CONT_AWD_70FA6025F00000008_7022_70FA6021D00000003_7022/
- 70FA6024F00000053 (delivery order): $2,109,361, Mitigation Section. PTS Zone 1 Arc National Dam Safety Program (Ndsp) Technical Manuels. https://www.usaspending.gov/award/CONT_AWD_70FA6024F00000053_7022_70FA6021D00000003_7022/
- 70FA6024F00000018 (delivery order): $1,695,805, Mitigation Section. PTS Arc Zone 1 Building Science. https://www.usaspending.gov/award/CONT_AWD_70FA6024F00000018_7022_70FA6021D00000003_7022/
- 70FA6026F00000045 (delivery order): $1,299,942, Mitigation Section. National Dam Safety Program - Emergency Action Planning Support for High Hazard Dams Zone 1. https://www.usaspending.gov/award/CONT_AWD_70FA6026F00000045_7022_70FA6021D00000003_7022/
- 70FA6026F00000040 (delivery order): $899,923, Mitigation Section. Architect and Engineering in Accordance with the PWS and Qasp Dated 8/14/2026 for the Publication Update: FEMA P-550: Recommended Residential Construction in Coastal Areas. https://www.usaspending.gov/award/CONT_AWD_70FA6026F00000040_7022_70FA6021D00000003_7022/
- 70FA6026F00000009 (delivery order): $703,946, Mitigation Section. PTS Zone 1 Building Science Fire Hazards, United States Fire Administration Fire Study Phase II. https://www.usaspending.gov/award/CONT_AWD_70FA6026F00000009_7022_70FA6021D00000003_7022/
- 70FA6026F00000005 (delivery order): $551,501, Mitigation Section. National Dam Safety Program Guidance to Incorporate Dam Risks in Land Use, Hazard Mitigation and Floodplain Management Plans. https://www.usaspending.gov/award/CONT_AWD_70FA6026F00000005_7022_70FA6021D00000003_7022/
- 70FA6023F00000096 (delivery order): $340,933, Mitigation Section. The Purpose of This Bilateral, Within Scope, NO-COST Modification Is to Make Personnel Changes to the Task Order 70FA6023F00000096. the Changes Are as Follows: Appoint Betsy Hicks as Cor, Replacing Lauren Schmied. Change of Contracting Officer to Val. https://www.usaspending.gov/award/CONT_AWD_70FA6023F00000096_7022_70FA6021D00000003_7022/
- 70FBR524F00000031 (delivery order): $84,883, Region 5 : Emergency Preparedness a. Region 5 Fiscal Year 24 Production and Technical Services Risk Map Task Order. https://www.usaspending.gov/award/CONT_AWD_70FBR524F00000031_7022_70FA6021D00000003_7022/
- 70FA6022F00000044 (delivery order): $40,718, Mitigation Section. The Purpose of This Modification Is to Incorporate Updates to Attachment a Coastal Erosion Task Order Planned Activities and Deliverable Schedule.. https://www.usaspending.gov/award/CONT_AWD_70FA6022F00000044_7022_70FA6021D00000003_7022/
- 70FA6023F00000052 (delivery order): $0, Mitigation Section. Final Closeout. https://www.usaspending.gov/award/CONT_AWD_70FA6023F00000052_7022_70FA6021D00000003_7022/
- 70FBR122F00000035 (delivery order): $0, Region 1: Emergency Preparedness an. Modification P0001- Administrative Change to Formally Change the Contracting Officer (Co) Under the Task Order.. https://www.usaspending.gov/award/CONT_AWD_70FBR122F00000035_7022_70FA6021D00000003_7022/
- 70FBR123F00000041 (delivery order): $0, Region 1: Emergency Preparedness an. Modification P0001 to Formally Change the Contracting Officer (Co) Under the Task Order.. https://www.usaspending.gov/award/CONT_AWD_70FBR123F00000041_7022_70FA6021D00000003_7022/
- 70FBR222F00000211 (delivery order): $0, Region 2: Emergency Preparedness an. PTS Zone 1 Region 2 FY22 PTS Task Order - the Purpose of This Modification P00001 Is to Implement the Actions Contained in FY22 Task Order Change Request Arc-R2-Fy22-0011, Change the Contract Status from Excepted to Exempt and Change Assigned Cor.. https://www.usaspending.gov/award/CONT_AWD_70FBR222F00000211_7022_70FA6021D00000003_7022/
- 70FBR223F00000185 (delivery order): $0, Region 2: Emergency Preparedness an. Region 2 Fiscal Year 23 Production and Technical Services Risk Map Task Order - NO-COST Modification to Change the Contract Status from Excepted to Exempt in Accordance with Policy Guidance.. https://www.usaspending.gov/award/CONT_AWD_70FBR223F00000185_7022_70FA6021D00000003_7022/
- 70FBR322F00000052 (delivery order): $0, Regoin 3: Emergency Preparedness an. Cor Change; Region III FY22 Production and Technical Services. https://www.usaspending.gov/award/CONT_AWD_70FBR322F00000052_7022_70FA6021D00000003_7022/
- 70FBR323F00000016 (delivery order): $0, Regoin 3: Emergency Preparedness an. Cor Change; FEMA Region 3 FY23 Riskmap PTS. https://www.usaspending.gov/award/CONT_AWD_70FBR323F00000016_7022_70FA6021D00000003_7022/
- 70FBR522F00000045 (delivery order): $0, Region 5 : Emergency Preparedness a. This Modification Changes the Contracting Officer and Invoice Approver, Updates the Requirements for Monthly Reporting, and Updates the Tables from Sow to Correctly Remove Scope That Was Removed as Part of the Task Order Negotiations.. https://www.usaspending.gov/award/CONT_AWD_70FBR522F00000045_7022_70FA6021D00000003_7022/
- 70FBR523F00000069 (delivery order): $0, Region 5 : Emergency Preparedness a. This Modification Updates the Contracting Officer and Invoice Approver for This Task Order.. https://www.usaspending.gov/award/CONT_AWD_70FBR523F00000069_7022_70FA6021D00000003_7022/
- 70FA6021D00000003: $0, Mitigation Section. Exercise Option Period 3 for PTS Zone 1. https://www.usaspending.gov/award/CONT_IDV_70FA6021D00000003_7022/
- 70FBR223F00000035 (delivery order): -$9,754, Region 2: Emergency Preparedness an. The Purpose of This Modification Is to De-Obligated Excess Funds.. https://www.usaspending.gov/award/CONT_AWD_70FBR223F00000035_7022_70FA6021D00000003_7022/
- 70FBR222F00000114 (delivery order): -$86,781, Region 2: Emergency Preparedness an. De-Obligation of Excess Funding. https://www.usaspending.gov/award/CONT_AWD_70FBR222F00000114_7022_70FA6021D00000003_7022/
- 70FA6023F00000090 (delivery order): -$89,940, Mitigation Section. The Purpose of This Unilateral Modification Is to De-Obligate Excess Funds in Accordance with Memorandum Blanket De-Obligation of Excess Funds in Preparation for Financial System Transition Dated July 01, 2026.. https://www.usaspending.gov/award/CONT_AWD_70FA6023F00000090_7022_70FA6021D00000003_7022/
- 70FA6021F00000072 (delivery order): -$404,922, Mitigation Section. De-Obligation of Funds.. https://www.usaspending.gov/award/CONT_AWD_70FA6021F00000072_7022_70FA6021D00000003_7022/
- 70FA6022F00000047 (delivery order): -$539,062, Mitigation Section. The Purpose of This Unilateral Modification Is to De-Obligate Excess Funds in Accordance with Memorandum Blanket De-Obligation of Excess Funds in Preparation for Financial System Transition Dated July 01, 2026.. https://www.usaspending.gov/award/CONT_AWD_70FA6022F00000047_7022_70FA6021D00000003_7022/

---
Source: USAspending.gov award data, keyed by UEI. Obligations in the window only. Cite https://sealedbidder.com/vendors/advancing-resilience-in-communities-cp3bu1a33kl7.