Sources sought
ICD-705 Controlled Spaces Modernization and Sustainment Program - (Progressive Design-build (PDB) Other Transaction Agreement (OTA)
W912UM27S0TA1
Department of the Army, W2SN Endist FAR East. Commercial and Institutional Building Construction.
Response deadline
November 17, 2026 at 12:00 AM EST
Closed 9 days ago. Posted October 27, 2026, first published October 26, 2026. Scheduled to archive December 2, 2026.
Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities
This one closed 9 days ago
191 like it are open now in commercial and institutional building construction
- FY27 NRM - VISN Base Modernize Nurse Call - 539-23-101
Department of Veterans Affairs, 250-Network Contract Office 10
PresolicitationSDVOSBNAICS 236220Location not published36C25027B0009Due in 4 daysNov 30 - FY27 NRM - VISN Base Install Roof Equipment Railings - 539-22-206
Department of Veterans Affairs, 250-Network Contract Office 10
PresolicitationSDVOSBNAICS 236220Location not published36C25027B0008Due in 4 daysNov 30 - N4008426R7500 DB RMAC FACILITY IMPROVEMENT AT NETDC, SAN ANTONIO, ZAMBALES, PHILIPPINES
Department of the Navy, Navfacsyscom FAR East
SolicitationNAICS 236220Outside the USN4008426R7500Due in 5 daysDec 1
All 191 open in commercial and institutional building construction
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Sources sought. Market research. The agency wants to know who could do the work before it decides how to compete it. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 236220 (commercial and institutional building construction), means no more than $45 million in average annual receipts, counted with affiliates. What a set-aside is
- What comes next
- No solicitation has been published under this number yet. The sources sought of October 26, 2026 is the earliest notice of the purchase.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
SOURCES SOUGHT ANNOUNCEMENT
AND INDUSTRY DAY NOTICE
PROGRESSIVE DESIGN-BUILD (PDB)
OTHER TRANSACTION AGREEMENT (OTA)
ICD-705 Controlled Spaces Modernization and Sustainment Program
Osan Air Base, Republic of Korea
U.S. Army Corps of Engineers – Far East District
DISCLAIMER: This Sources Sought is issued solely for market research/intelligence and acquisition planning. It is not a solicitation, Request for Qualifications, or commitment to issue a solicitation or award any agreement or contract. No Statements of Qualifications or proposals are requested. Participation is voluntary; the Government will not reimburse response costs and will not accept unsolicited proposals. Responses will inform acquisition strategy, industry capability assessment, and project delivery options. Responding does not affect eligibility for any future solicitation.
THE OPPORTUNITY
The U.S. Army Corps of Engineers, Far East District (USACE FED) invites industry partners to help shape the acquisition strategy for a high-priority modernization and sustainment program involving ICD-705 controlled spaces at Osan Air Base, Republic of Korea. The Government is evaluating an innovative Progressive Design-Build (PDB) delivery method executed through an Other Transaction Agreement (OTA) under 10 U.S.C. § 2808a.
This approach enables early contractor involvement, collaborative design development, open-book pricing, and flexible risk allocation—advantages particularly valuable for complex, security-sensitive work performed in an active overseas operational environment with unique host-nation and ICD-705 constraints. The Government has not made a final acquisition strategy determination and seeks candid industry input on the benefits, limitations, risks, and commercial terms of a PDB OTA compared with traditional design-bid-build or design-build approaches.
WHY PROGRESSIVE DESIGN-BUILD / OTA?
ICD-705 controlled spaces, collective protection systems, and HVAC modernization on an active air base present technical, security, operational, and logistical complexities that benefit from early industry engagement. A PDB OTA structure may allow:
- Joint refinement of requirements and design while the facility remains operational;
- Early identification and mitigation of long-lead items, host-nation interfaces, and ICD-705 accreditation risks;
- Transparent, open-book cost development leading to a more reliable construction baseline (including potential GMP);
- Flexible commercial terms and governance tailored to the unique constraints of overseas military construction in the Republic of Korea.
The Government is particularly interested in industry’s practical experience with these methods on similar secure or operationally constrained projects, as well as any recommended alternatives that would better achieve mission, schedule, and cost objectives.
PROJECT SCOPE
The program encompasses modernization and sustainment work in two existing facilities at Osan Air Base:
Building A – Collective Protection, HVAC & ICD-705 Modernization
- Replace the existing M49 Collective Protection System (CPS) filter system with a new M98 CPS, including associated blast doors, seals, relief valves, electronic control systems, and other appurtenances, fully coordinated with applicable ICD-705 requirements.
- Replace or modernize principal components of the existing HVAC system to support ICD-705 environmental and security standards.
- Convert approximately 2,610 square feet of existing space to meet applicable ICD-705 requirements.
Building B – ICD-705 Conversion & Facility Sustainment
- Convert approximately 3,700 square feet of existing space to meet applicable ICD-705 requirements.
- Perform sustainment work on approximately 50,000 square feet, including roof repairs and existing office space improvements.
- Repair and/or replace components of the existing fire protection and fire alarm systems; air-handling units (AHUs), air-cooled condensing units (ACCUs), and associated HVAC infrastructure; bathroom fixtures and plumbing; plus associated incidental work required to complete the planned improvements.
Estimated program magnitude: $60–100 million. Construction funding for both facilities is anticipated for obligation in FY27, subject to availability of funds and applicable approvals. This Sources Sought is the Government’s primary tool to assess industry interest, capability, and preferred commercial practices before finalizing the acquisition approach.
ACQUISITION APPROACH UNDER EVALUATION
Industry feedback will help refine potential agreement structure, project phasing, pricing approach, governance, risk allocation, and other commercial terms.
Potential Phase 1 – Design and Preconstruction
The Government and selected contractor would collaborate to refine project requirements, develop the design, conduct constructability reviews, identify long-lead equipment, evaluate phasing and operational constraints, obtain subcontractor input, develop cost estimates, and mitigate technical and execution risks. Feedback is requested on the design maturity, site investigations, pricing information, and agreement terms needed to establish a reliable construction cost and schedule baseline.
Potential Phase 2 – Construction
Following design development and resolution of key technical and commercial risks, the contractor may be asked to propose a construction price, potentially including a Guaranteed Maximum Price (GMP) if appropriate to the final structure. Any transition to construction would be subject to the terms of the resulting agreement, Government acceptance, availability of funds, and required approvals. The Government seeks practical recommendations for off-ramp provisions, design deliverables, compensation, and transition arrangements should the parties be unable to reach agreement on construction pricing or other required terms.
Alternative acquisition strategies that industry believes would better support the program’s security, technical, schedule, cost, and operational requirements are welcome and encouraged.
INDUSTRY DAY
A Virtual Industry Day is to be determined. The SAM.gov posting will be updated with registration instructions and meeting information when available. Interested firms are strongly encouraged to add themselves to the Interested Vendors List associated with this announcement on SAM.gov to receive timely updates, including Industry Day details.
INFORMATION REQUESTED FROM INDUSTRY
Your candid, detailed feedback is critical to shaping a successful acquisition. The Government’s primary mechanism for obtaining market research is the Industry Questionnaire, which addresses capability and capacity, relevant experience, Progressive Design-Build experience, open-book pricing, technical capabilities (ICD-705, CPS, secure facilities), real estate and construction considerations in the Republic of Korea, schedule, security, risk, governance, and recommended commercial practices.
1. Complete the Industry Questionnaire: Access the Questionnaire Here (https://forms.osi.apps.mil/Pages/ResponsePage.aspx?id=unZN_HzxUEy5p48xY9J1gkOXdBFTSSpJlGbZL6EFB8NUN1FSQ0pXMEE3TU05UzlUQ09QNjNMSjNTTyQlQCN0PWcu) or complete the questionnaire attached.
2. Submit a Capability Statement (not to exceed 12 pages). Include:
- Company name and address, CAGE code and/or Unique Entity Identifier (UEI) from your SAM.gov registration. Clearly identify if you are a foreign firm, partner, or subsidiary located outside the United States.
- Business size status and any applicable socioeconomic categories under NAICS Code 236220 – Commercial and Institutional Building Construction (small business size standard: $45 million).
- Two completed projects of similar nature and complexity (examples: ICD-705 controlled spaces, collective protection system installation or modernization, secure facility conversion, complex HVAC/CPS upgrades in operational military facilities, or comparable high-security construction). For each project state whether you were Prime, Subcontractor, or partnering Architect-Engineer firm, and provide: start and end dates of construction, project cost, complexity of the work, and any significant challenges (e.g., coordination with multiple partners/agencies, operational constraints, climate, terrain, or host-nation requirements).
The Government especially values recommendations on commercial practices, agreement terms, project phasing, risk sharing, open-book pricing approaches, governance structures, and other considerations that could improve successful execution of this project under 10 U.S.C. § 2808a.
HOW TO RESPOND
Interested firms should complete the Industry Questionnaire and submit any supplemental Capability Statement via email no later than 2:00 p.m. Korea Standard Time (KST), Tuesday, 17 November 2026.
Primary Point of Contact(s):
Eugene A. Gibbs | Eugene.A.Gibbs@usace.army.mil
Mike M. Miyagi | Michael.M.Miyagi@usace.army.mil
Email subject line: W912UM27S0TA1 / [Your Company Name] Response
Add your firm to the Interested Vendors List on SAM.gov associated with this announcement to ensure you receive all future updates, including Industry Day registration details.
Attachments
Files and links listed on SAM.gov. Files we hold a copy of download from here; the rest open SAM's download, which needs no account. Links open the sites the agency named.
- PDB-OTA Process Overview Placemat.pdf331 KB, October 27, 2026
- Questionnaire LinkLink to forms.osi.apps.mil, October 27, 2026
- Sources_Sought_ICD705_Osan_PDB_OTA_27Oct26_V1.pdf228 KB, October 27, 2026
- ICD705_Osan_Industry_Questionnaire_Fillable_27Oct26_V2.pdf106 KB, October 27, 2026
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
October 27, 2026
Sources sought
Due November 17, 2026 at 12:00 AM EST. SAM.gov, notice 831a923981604e6b8de436d65a781a2a
2 revisions on SAM
- October 27, 2026: publish, sources sought
- October 27, 2026: publish, sources sought
October 27, 2026
Sources sought
Due November 17, 2026 at 12:00 AM EST. SAM.gov, notice d000ad231a124c06a28d15cf93e062f0
2 revisions on SAM
- October 27, 2026: publish, sources sought
- October 27, 2026: publish, sources sought
October 27, 2026
Sources sought
Due November 17, 2026 at 12:00 AM EST. SAM.gov, notice 4961c4af95e2444783d66f6766e12527
3 revisions on SAM
- October 27, 2026: publish, sources sought
- October 27, 2026: publish, sources sought
- October 27, 2026: publish, sources sought
Points of contact
- Eugene GibbsEugene.a.gibbs@usace.army.mil05033546139
- Michael M. Miyagimichael.m.miyagi@usace.army.mil05033546095