Sources sought
Maintenance Dredging of New York and New Jersey Harbor – Arthur Kill 50 foot Reach Federal Navigation Project
W912DS27S0009
Department of the Army, W2SD Endist New York. Other Heavy and Civil Engineering Construction.
Offers due
December 2, 2026 at 2:00 PM EST
6 days from now. Posted November 17, 2026.
Get an email when this is amended, when the deadline moves and when it is awarded.Watch it
Next from this buyer
- Civil Works Construction Management ServicesSources soughtNAICS 541618Jersey City, NJW912DS27S0007Due in 5 daysDec 1
- Military construction management servicesSources soughtNAICS 541618New YorkW912DS27S0008Due in 5 daysDec 1
- RFI USMMA Campus Modernization Program SATOC Seawall ProjectSources soughtNAICS 237990Kings Point, NYW912DS27S0006Closes in 8 daysDec 4
Similar, open now
- RFI USMMA Campus Modernization Program SATOC Seawall Project
Department of the Army, W2SD Endist New York
Sources soughtNAICS 237990Kings Point, NYW912DS27S0006Closes in 8 daysDec 4 - Dredge Entrance Channel (FY27) - Station Eatons Neck
US Coast Guard, Ceu Providence
PresolicitationSmall businessNAICS 237990Northport, NY70ZS0627BSLIS0031Closes in 47 daysJan 12, 2027 - United States Air Force Academy (USAFA) Varsity Baseball Stadium
Department of the Army, W071 Endist Omaha
PresolicitationSmall businessNAICS 237990ColoradoNAF128F27B0001Due tomorrowNov 27
All 142 open in other heavy and civil engineering construction
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Sources sought. Market research. The agency wants to know who could do the work before it decides how to compete it. A business that could do the work answers with a short capability statement. Answering does not commit it to bid, and the answers decide whether the purchase is set aside for small businesses. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 237990 (other heavy and civil engineering construction), means no more than $45 million in average annual receipts, counted with affiliates. What a set-aside is
- What comes next
- No solicitation has been published under this number yet. The sources sought of November 17, 2026 is the earliest notice of the purchase.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
Market Survey
Background Information
The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of the New York and New Jersey Harbor – Arthur Kill 50 foot Reach Federal Navigation Project to a depth of -50 feet Mean Lower Low Water (MLLW) plus 1 foot of allowable over-depth. The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of material from the critical shoal area. The dredged material would be dredged and subsequently placed at a suitable, contractor provided, state permitted upland placement site(s). The dredged material is expected to consist primarily of silt, clay, and some sand.
Based on the past dredging projects within the New York Harbor, and anticipated restrictions found in the New York State Department of Environmental Conservation Water Quality Certificate, the proposed work can only be performed by utilizing a mechanical clamshell dredge with environmental bucket. Additionally, tug-boats, sealed hull barges and survey vessels will be needed to perform the work during the dredging, transport, processing and placement activities. The dredging, transport and placement at a suitable, contractor provided, state permitted upland placement site(s) would be required to meet all federal, state, and local criteria required by the government agencies having jurisdiction where the dredging and placement sites are located. All necessary permits required for the dredged material placement will be provided by the contractor to the government.
The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government.
Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the Notice to Proceed and maintain an integrated production rate of at least 3,000 cubic yards per calendar day for the dredging and placement of the dredged material. The presence of the dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact.
The proposed work is anticipated to take place in the summer / fall of 2027.
SURVEY OF THE DREDGING INDUSTRY
The following confidential survey questionnaire is designed to apprise USACE of prospective dredging contractors’ project execution capabilities. Please provide your response to the following questions. All questions are in regard to the Arthur Kill 50 foot Reach maintenance dredging project.
General
1. Have you ever worked on dredging jobs similar in nature to this project? If so, please describe the project and for whom the work was performed. Identify a point of contact and phone number, as a reference of relevant experience.
2. Have you performed dredging within the waters of the Port of New York and New Jersey?
3. Do you have experience with the placement of dredged material at a suitable, contractor provided, state permitted upland placement site? Please list your experience.
4. What percentage of work (volume of material dredged, transported, processed and ultimately placed) can you perform with your own equipment or equipment owned by another dredging contractor?
5. Would you be willing to bid on the project previously described? If the answer is No, please explain why not.
6. Would you be bidding on this project as a sole contractor, prime contractor with subcontractor(s) or as a joint venture?
7. Is there a dollar limit on the size of contract that you would bid? If so, what is that limit?
8. What is the largest dredging contract, in dollars, on which you were the prime contractor?
9. What is your bonding capacity per contract? What is your total bonding capacity?
10. Do you have experience using USACE Resident Management System (RMS) 3.0 for delivering Submittals, Daily Dredging Reports and Pay Estimates?
11. In the event that the USACE transitions from Resident Management System (RMS) to an alternative construction management system during the contract, will the contractor be ready to adapt to the new management system?
12. Do you have experience applying USACE EM 385-1-1 (Mar 2024) and all requirements? Deficiencies observed on site will require immediate attention and action to meet all applicable safety codes.
Equipment
13. What type of dredge equipment do you own and/or operate that is suitable for the work described? Do you own a mechanical dredge with a closed environmental clamshell bucket? Please list each piece of equipment capable of performing the work described, i.e. dredging, transfer, transportation, processing and final placement of the material. For each dredge that you list, please specify its bucket size(s), and any other salient characteristics.
14. Identify which dredge(s), including support equipment (tug, crew boat, scows, etc.), you would employ on this project. Also, for each dredge, identify the maximum dredging depth.
15. Do you own material scows? If so, how many do you have available for use? Please list the name of the scow, its type (ocean-going, sealed hull, etc) and the capacity.
16. Do you have the capability to process the dredged material on your own? If so please explain. If not, what commercial provider of dredge material processing will you engage for this project? What is the daily processing capacity in either case?
17. Will you be able to meet a production rate of 3,000 cubic yards per calendar day and complete all work?
18. Do you have experience with the use of an automated Dredged Material Monitoring System (Black Box / Silent Inspector) employing a Dredged Material Inspector (DMI)?
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
November 17, 2026
Sources sought
Due December 2, 2026 at 2:00 PM EST. SAM.gov, notice 9f0b5e53c0004fb58b1b5d22a70352ff
1 revision on SAM
- November 17, 2026: publish, sources sought
Points of contact
- Orlando Nievesorlando.nieves@usace.army.mil
- Matthew Lubiakmatthew.e.lubiak@usace.army.mil