# Alvin Bush Dam Rock Wall Stabilization, Kettle Creek, Clinton County, PA

Canonical: https://sealedbidder.com/opportunities/w912dr26ba002

- Solicitation number: W912DR26BA002
- Notice type: Award notice (first published as presolicitation)
- Status: Awarded to Allison Park Contractors, Inc. for $17,055,100.00
- Department: Department of the Army
- Agency: Department of the Army
- Contracting office: W2SD Endist Baltimore (W912DR)
- NAICS: 237990 Other Heavy and Civil Engineering Construction
- Product or service code: Y1PZ Construction Of Other Non-Building Facilities
- Small business size standard: $45 million in average annual receipts (13 CFR 121.201, NAICS 237990)
- Location read from: the notice's place of performance: "ALBIN BUSH DAMKETTLE CREEK, CLINTON COUNTY, PA"
- First posted: January 28, 2026
- Last posted: June 10, 2026
- SAM.gov: https://sam.gov/workspace/contract/opp/07e66c43478344399bc8f26cd90220e8/view

## Reading this notice

- Kind of notice: Award notice. Who won, when, and for how much.
- Time to respond: Bidders had 70 days from the day the solicitation was posted, February 12, 2026, to the deadline. The deadline moved once: it was first February 11, 2026 and ended as April 23, 2026.
- Before the solicitation: The agency published a presolicitation on January 28, 2026, 15 days before the solicitation.
- How it ended: Awarded to Allison Park Contractors, Inc. on June 9, 2026, 47 days after offers were due.

## Description

Alvin Bush Dam Rock Wall StabilizationThe U.S. Army Corps of Engineers (USACE) Baltimore District is procuring a single award contract for a design-bid-build firm-fixed-price contract using the procedures of FAR 14 and 36. The magnitude of construction is between Between $25,000,000 and $100,000,000. Related Notices: W912DR25X13XJProject Scope:1. Alvin Bush Dam has a roadway alongside its spillway. The primary features of the dam include an earthen embankment; an uncontrolled spillway with concrete weir; and a gated outlet consisting of a control tower and concrete lined tunnel through bedrock. The wall is approaching 62 years old, is deteriorated, and has nearly eroded back to the state roadway.2. The scope of the project consists of constructing two reinforced concrete rock anchored walls to prevent continued progressive rock erosion which has led to fallen rock accumulation within the spillway and will ultimately lead to failure of Kettle Creek Road. The project also includes proposed drainage improvements, paving, grading, spoils, access roads, stairs, railing, fencing and other work incidental to the related work.3. Obtain the necessary permits to perform the work cited above. As a minimum, a permit from the Pennsylvania Department of Environmental Protection National Pollution will be required.Please see attachments for complete details.

## Attachments

- [dodprocurementtoolbox.com](https://dodprocurementtoolbox.com/) (link)
- [dodprocurementtoolbox.com](https://dodprocurementtoolbox.com/) (link)
- [dodprocurementtoolbox.com](https://dodprocurementtoolbox.com/) (link)

## Open now in the same industry

142 open in NAICS 237990.

- Borough of Millvale, Pennsylvania, Local Protection Project (LPP) PL84-99 Rehabilitation (W911WN27QA004), due December 8, 2026 at 11:00 AM EST. https://sealedbidder.com/opportunities/w911wn27qa004
- Allegheny River Lock and Dam 2 Interlock and Traffic Control System Replacement (W911WN27BA002), due December 8, 2026 at 11:00 AM EST. https://sealedbidder.com/opportunities/w911wn27ba002
- Department of Energy, AT Courtyard Construction and Site Utility Infrastructure (W911WN27R0005), due December 8, 2026 at 4:30 PM EST. https://sealedbidder.com/opportunities/w911wn27r0005

## Publications

- January 28, 2026: Presolicitation, due February 11, 2026 at 3:00 PM EST. Notice 14e355c97a1b42ff8c08d99142048df0. https://sam.gov/workspace/contract/opp/14e355c97a1b42ff8c08d99142048df0/view
- February 12, 2026: Solicitation, due April 23, 2026 at 11:00 AM EDT. Notice dcccbc15f3e44c23b6e8e63998a27bb1. https://sam.gov/workspace/contract/opp/dcccbc15f3e44c23b6e8e63998a27bb1/view
- April 2, 2026: Solicitation, due April 23, 2026 at 11:00 AM EDT. Notice 44693bea8c154c7a8cea77631c185d69. https://sam.gov/workspace/contract/opp/44693bea8c154c7a8cea77631c185d69/view
- April 9, 2026: Solicitation, due April 23, 2026 at 11:00 AM EDT. Notice 83a00d9975314dc9866f6dd962983255. https://sam.gov/workspace/contract/opp/83a00d9975314dc9866f6dd962983255/view
- April 27, 2026: Solicitation, due April 23, 2026 at 11:00 AM EDT. Notice a69b3a97b2b1485e8f5b7a4f6907ff25. https://sam.gov/workspace/contract/opp/a69b3a97b2b1485e8f5b7a4f6907ff25/view
- June 10, 2026: Award notice. Notice 07e66c43478344399bc8f26cd90220e8. https://sam.gov/workspace/contract/opp/07e66c43478344399bc8f26cd90220e8/view

## Points of contact

- Clark Miller, clark.b.miller@usace.army.mil, 4109625679

---
Source: SAM.gov Contract Opportunities bulk extract. Confirm deadlines on SAM.gov before responding. Cite https://sealedbidder.com/opportunities/w912dr26ba002.