Sources sought
Increase Contract ceiling on W58RGZ-24-D-0065
W58RGZ24D0065CeilingIncrease
Department of the Army, W6QK ACC-RSA. Other Aircraft Parts and Auxiliary Equipment Manufacturing.
Response deadline
October 20, 2026 at 12:00 PM EDT
Closed 36 days ago. Posted October 5, 2026. Scheduled to archive November 4, 2026.
Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities
This one closed 36 days ago
564 like it are open now in other aircraft parts and auxiliary equipment manufacturing
- V250 AND TMS KIT
Department of the Army, W6QK ACC-RSA
SolicitationNAICS 336413Ship to Redstone Arsenal, ALW58RGZ-25-Q-0016Due in 6 daysDec 1 - THRUST ACTUATOR
Department of the Army, W6QK ACC-RSA
PresolicitationNAICS 336413Ship to Redstone Arsenal, ALW58RGZ-27-R-A003Due in 7 daysDec 2 - OEM Boeing Company CH-47 Chinook Helicopter Weapon System, Sole Source Long Term Contract
Defense Logistics Agency, DLA Aviation at Huntsville, Al
PresolicitationNAICS 336413Ship to Huntsville, ALSPRRA127RA020Closes in 8 daysDec 3
All 564 open in other aircraft parts and auxiliary equipment manufacturing
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Sources sought. Market research. The agency wants to know who could do the work before it decides how to compete it. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 336413 (other aircraft parts and auxiliary equipment manufacturing), means no more than 1,250 employees, counted with affiliates. What a set-aside is
- What comes next
- No solicitation has been published under this number yet. The sources sought of October 5, 2026 is the earliest notice of the purchase.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
This is a notification that the Army Contracting Command, Redstone Arsenal, AL, intends to increase the contract ceiling from $388,588,385 to approximately $$685,398,349 on existing contract W58RGZ-24-D-0065 with L3 Technologies, Inc., Communications Systems-West, a subsidiary of L3Harris Technologies Inc. (L3T), Commercial and Government Entity (CAGE) Code: 06401, 640 N 2200 W, Salt Lake City, UT 84116-2925.
An increase to the contract ceiling will allow for the purchase of Manned/Unmanned Teaming (MUMT) hardware, as well as technical and engineering support for the Apache Attack Helicopter (AAH) to support United States Government (USG) operations and Foreign Military Sales (FMS).
This increase is primarily necessary due to increases in quantities of projected hardware procurements:
Coyote Modem: The original quantity (qty) was based on pure fleeting/full fielding to USG AC, spares and a small qty of Five Eye (FVEY) buys. The revised IGCE accounts for the Coyote Modems that were procured by the USG, includes the remainder that would need to be procured to pure fleet and some quantity that would be procured by FVEY. The USG did not have a Coyote Modem-Coalition (CM-C) variant at the time the original IGCE was prepared and could not account for FMS procurement then. This proposed ceiling increase accounts for those requirements.
RoadRunner: At the time the original IGCE was prepared RoadRunner had not been developed; therefore no cost was available. This proposed ceiling increase accounts for actual cost and updated requirements for the USG and FMS partners.
Rover6i: The original IGCE planned to buy Rover6Si for ACME kits at very low quantities. The revised IGCE assumes quantities equal to CM-C quantities and assumes that R6Si can be installed in the AC.
MUMT-X AAG-X subsystem, KuC Omni Ant Assy and KuC RFE Assy: The original IGCE quantity used was 200. This was based on projected USG and FMS partner orders. The revised IGCE assumes an increase in quantity to 648/432.
ACME kit: At the time the original IGCE was prepared ACME kit had not been developed; therefore no cost was available. This proposed ceiling increase accounts for actual cost and updated requirements for the USG and FMS partners.
CFSR support: FMS partners’ CFSR utilization is projected to be significantly higher in Years 3-5 than previously estimated.
Additional costs associated with program support, production, and integration are also included in the overall ceiling increase.
As stated in the ACC-RSA original Justification and Approval (J&A) for Other than Full and Open Competition dated 10 August, 2022, L3T is the only source that possesses the TDP suitable for full and open competition, corporate knowledge and technical expertise to provide the MUMT-X hardware, as well as technical and engineering support for the quick reaction services and capabilities for this requirement. No other contractor has the resources to perform the required technical and engineering support for the AAH-64 MUMT/MUMT-X sensor systems in the required timeframe.
However, this Sources Sought serves as the Government's open for competition notice as required by DFARS PGI 206.302-1(d) and the notice of proposed contract action as required by FAR 5.201. This action will result in an increase in contract ceiling to the existing contract identified above which is necessary to allow for continuity of critical contractor services.
Electronic transmissions must not exceed 5 megabytes and responses in the form of white papers should be limited to 10 pages in length and may include technical specifications and product sheets as deemed necessary. All material submitted in response to this RFI must be unclassified.
All responses must be received via email no later than 20 October 2026, 11:00 a.m. Central Time and should be submitted to Contract Specialist, Tristan Mitchell; at Tristan.a.mitchell7.civ@army.mil, AND Contracting Officer, James Pattullo; at james.h.pattullo.civ@army.mil. No telephone inquiries will be accepted.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
October 5, 2026
Sources sought
Due October 20, 2026 at 12:00 PM EDT. SAM.gov, notice d558e0fce8f24efe8281ecc5d54d254b
1 revision on SAM
- October 5, 2026: publish, sources sought
Points of contact
- Tristan MitchellTristan.a.mitchell7.civ@army.mil