Sources sought
Request for Information/Market Intelligence Notice: Multiple Projects at Vandenberg Space Force Base - Use of Progressive Design Build (PDB) with Other Transaction Authority (OTA)
VSFB-FY27-PDBOTA
Department of the Air Force, FA4610 30 Cons PK. Commercial and Institutional Building Construction.
Response deadline
October 20, 2026 at 5:00 PM EDT
Closed 36 days ago. Posted October 6, 2026. Scheduled to archive November 4, 2026.
Get the next one like this from Department of the Air Force by email, the day it is posted.Find my opportunities
This one closed 36 days ago
192 like it are open now in commercial and institutional building construction
- USBC Weinberger Lower Floor Kitchenette Upgrade
Public Buildings Service, PBS Project Delivery Zones 5-7 - Pacific Northwest & Pacific Southwest Branch
PresolicitationSmall businessNAICS 236220San Diego, CAEQPMBE-27-0019Due tomorrowNov 26 - MACH1_AOI_Military Working Dog Facility_ Vandenberg Space Force_LOE 1 and LOE 2
Department of the Air Force, FA8903 772 Ess PK
PresolicitationNAICS 236220Lompoc, CAFA8903-27-OT005Due in 5 daysNov 30 - Project No. 640A0-27-104, Replace Roof at Building 347 - Menlo Park
Department of Veterans Affairs, 261-Network Contract Office 21
Combined synopsis and solicitationSDVOSBNAICS 236220Menlo Park, CA36C26127Q0082Due in 6 daysDec 1
All 192 open in commercial and institutional building construction
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Sources sought. Market research. The agency wants to know who could do the work before it decides how to compete it. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 236220 (commercial and institutional building construction), means no more than $45 million in average annual receipts, counted with affiliates. What a set-aside is
- What comes next
- No solicitation has been published under this number yet. The sources sought of October 6, 2026 is the earliest notice of the purchase.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
REQUEST FOR INFORMATION (RFI) / MARKET RESEARCH NOTICE: This is a request for information (RFI) for market intelligence and for informational purposes only. This announcement does not constitute a solicitation or a request for proposal (RFP), and no solicitation is currently available. Participation in this RFI is strictly voluntary. The Government will not be obligated to award any agreement or contract because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal should a formal solicitation be issued in the future.
NAICS CODE:
236220 Commercial and Institutional Building Construction
237130 Power and Communication Line and Related Structures Construction
SMALL BUSINESS STANDARD: $45,000,000.00
NOTE: While Other Transaction Authority is not subject to FAR based small business regulations, these NAICS codes are provided for market research to help the Government understand the size and demographics of the interested industrial base.
PROGRAM/PROJECT OVERVIEW: The 30th Contracting Squadron has multiple infrastructure repair and construction projects planned in Fiscal Year 2027 including heating, ventilation and air conditioning (HVAC) repair, secure facility renovation, medium-high voltage electrical distribution line repair/replacement, airfield lighting repair, fitness track repair/replacement, and road repair/construction, fire alarm and elevator repair/replacement. The Government is evaluating the feasibility of executing these requirements via Progressive Design-Build (PDB) utilizing an Other Transaction (OT) Agreement under the statutory authority of 10 U.S.C. § 2808a in conjunction with the United States Space Force (USSF) Construction Commercial Solutions Opening (CSO) at https://sam.gov/workspace/contract/opp/68c3d9f987984f448cd067abaf2950d0/view.
Summaries of potential projects being considered for this acquisition strategy are as follows:
- HVAC Repair: Design and construct the repair and replacement of the HVAC for a multi-tenant office building.
- Secure Facility Renovation: Design and construction of renovations of a secure facility to meet revised mission requirements Renovation is expected to include wall relocation, electrical, communications, HVAC, and associated finished associated with a facility renovation.
- Medium-High Voltage Electrical Distribution: Design and construction of the replacement of an aged electrical distribution system ranging from 15kV to 70kV.
- Airfield Repair: Investigate, design, and construct repairs to various airfield infrastructure to bring it up to current FAA and military airfield code and standards.
- Outdoor Fitness Track Repair/Replacement: Design and construct repairs to stabilize the soil conditions and repair failing rubberized track surface.
- Road Repair/Construction: Design and construct road repairs to stabilize subsurface conditions and improve roadways to meet increasing haul capacity and traffic.
- Fire Suppression and Elevator Repair/Replacement: Design and construct the replacement of a freight elevator for personnel and freight access and the replacement of the existing fire alarm system to include connectivity with the new elevator.
INFORMATION REQUESTED: Interested industry partners are requested to respond to the following questions to help shape the final acquisition strategy:
Company Profile:
Q1. Business Name
Q2. Address
Q3. Point of Contract (Name, Title)
Q4. Phone Number
Q5. Email Address
Q6. Unique Entity ID
Q7. Cage Code
Q8. Socioeconomic Status (Other Than Small, Small, 8(a), SDVOSB, etc.)
Q9. Participating Role (Prime Contractor, Subcontractor, Design Firm, Other)
Q10: Which of the seven (7) projects your company may be interested in responding to if the projects are issued as PDB OT Agreements.
Other Transaction Authority (OTA) & Statutory Compliance:
Q11. OTA Experience – Describe your firm’s previous experience, if any, executing projects utilizing OTA. Please select from one of the following:
- No experience
- Limited Experience (1 – 5 projects completed)
- Very Experienced (5+ projects completed)
Q12. What project characteristics make PDB OTA particularly advantageous or disadvantageous for these requirements
Progressive Design-Build (PDB) / Early Contractor Involvement:
Q13. What minimum level of detail (e.g., Statement of Need, conceptual site plans, target budget) does your firm require prior to submitting a White Paper (Executive Summary, Outline of proposed construction method, estimated schedule, Rough Order of Magnitude (ROM) price)?
Q14. What minimum level of detail (e.g., Statement of Need, conceptual site plans, target budget) does your firm require prior to a Phase 1 award (Design/Pre-construction) to feel confident in the project's viability?
Q15. What collaborative mechanisms (such as joint design charrettes, target-value design workshops, or phased scoping approvals) do you recommend the Government implement in the first 30-90 days to rapidly transition from a "blank page" to a mutually agreed-upon baseline?
Q16. Describe your experience executing Progressive Design-Build, Construction Manager at Risk (CMAR), or other highly collaborative delivery methods where designer and builder worked collaboratively with the owner before locking in a Guaranteed Maximum Price (GMP).
Q17. Which of the following levels of designs would be the lowest level at which you would feel confident negotiating a GMP?
- Charrette (basic concept, floor plans, little to no engineering review completed)
- 35% Design (charrette documentation plus design narrative completed, list of projected codes, UFCs, and disciplines, initial site visit completed by engineering team)
- 65% Design (35% design documentation plus design analysis including investigation report, explanation of major design decisions, list of specifications, engineering data, environmental surveys)
- 95% Design (65% design brought to 100% design level except for administrative corrections and engineering stamps)
- 100% Design (100% complete signed and stamped drawings issued for construction)
Feedback on the Acquisition Strategy & Alternatives:
Q18. Does the proposed PDB-OTA strategy incentivize your firm to participate? Why or why not?
Q19. Are there alternative acquisition strategies, commercial phasing arrangements, or risk-sharing terms that the Government has not considered that would yield a higher quality facility, faster delivery, or lower cost?
Bonding Capability:
Q20. Specify your maximum bonding (single and aggregate) as a sole prime contractor and/or as a joint venture.
SUBMISSION INSTRUCTIONS: Please submit your responses by 20 October 2026 at 2:00 PM Pacific Daylight Time (PDT) to Jeffrey Grelck at jeffrey.grelck@spaceforce.mil and Alyson Kolding at alyson.kolding@spaceforce.mil
The Government welcomes candid industry feedback and recommendations regarding commercial practices, agreement terms, project phasing, risk sharing, governance, pricing approaches, and other considerations that could improve successful execution of these projects under 10 U.S.C. § 2808a. Upon completion of industry feedback and market intelligence the Government may or may issue a USSF CSO Area of Interest for one, some, all, or none of the projects.
Interested firms are encouraged to add themselves to the Interested Vendors List associated with this announcement on SAM.gov to receive future updates on thie RFI, however, any subsequent opportunties will be posted separately and not linked to this notice.
Note: Do not submit proprietary trade secrets, protected technologies, or classified information in your response. All feedback received will be handled as public market research to shape the Government's final acquisition approach.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
October 6, 2026
Sources sought
Due October 20, 2026 at 5:00 PM EDT. SAM.gov, notice fdbcf41cfbef450f9b4d290d1d1fd976
1 revision on SAM
- October 6, 2026: publish, sources sought
Points of contact
- Jeffrey Grelckjeffrey.grelck@spaceforce.mil
- Alyson KoldingAlyson.Kolding@spaceforce.mil