Combined synopsis and solicitation
System Intermediate Panels
RFQ401857
Department of Energy, ORNL Ut-Battelle LLC-DOE Contractor. Switchgear and Switchboard Apparatus Manufacturing.
Response deadline
September 2, 2025 at 5:00 PM EDT
Closed 449 days ago. Posted August 29, 2025, first published August 25, 2025. Scheduled to archive September 3, 2025.
Get the next one like this from Department of Energy by email, the day it is posted.Find my opportunities
This one closed in 2025
57 like it are open now in switchgear and switchboard apparatus manufacturing
- SWITCH
Department of the Navy, NAVSUP Weapon Systems Support Mech
SolicitationNAICS 335313Ship to the buyerN0010427QBB68Due in 2 daysNov 27 - LOCKING DEVICE,CIRCUIT
Defense Logistics Agency, DLA Weapons Support
Combined synopsis and solicitationSDVOSBNAICS 335313Ship to the buyerSPE7M527U0083Due in 3 daysNov 27 - SWITCH,ROTARY
Defense Logistics Agency, DLA Weapons Support
Combined synopsis and solicitationSmall businessNAICS 335313Ship to the buyerSPE7M827T0785Due in 3 daysNov 27
All 57 open in switchgear and switchboard apparatus manufacturing
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Combined synopsis and solicitation. A streamlined commercial-item buy where the notice itself is the solicitation. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 335313 (switchgear and switchboard apparatus manufacturing), means no more than 1,250 employees, counted with affiliates. What a set-aside is
- Time to respond
- Bidders had 8 days from the day the solicitation was posted, August 25, 2025, to the deadline.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
System Intermediate Panels
Oak Ridge National Laboratory is in need of 4 panel boards, 1 dry type transformer and 3 safety switches. Panel boards have to be surface mounted. Dry type transformer must be general purpose vented. Safety switches must be heavy duty, fusible. See Bill of Material for specific requirements.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- RFQ401857.pdf582 KB, August 25, 2025
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
August 25, 2025
Combined synopsis and solicitation
Due September 2, 2025 at 5:00 PM EDT. SAM.gov, notice c437918d251b4eb5a408cae6d8c6edf5
2 revisions on SAM
- August 29, 2025: publish, combined synopsis and solicitation
- August 25, 2025: publish, combined synopsis and solicitation
August 29, 2025
Combined synopsis and solicitation
Due September 2, 2025 at 5:00 PM EDT. SAM.gov, notice f96181c10d7b4e77b7ffa1cc7653c973
2 revisions on SAM
- August 29, 2025: publish, combined synopsis and solicitation
- August 25, 2025: publish, combined synopsis and solicitation
Points of contact
- Daria WangWangDS@ornl.gov865-341-4813