Special notice, total small business set-aside
Barge YC-1580 Repair and Overhaul Q & A
N3904024Q00042_Q_and_A
Department of the Navy, Portsmouth Naval Shipyard GF. Ship Building and Repairing.
Response deadline
August 8, 2024 at 12:30 PM EDT
Closed 840 days ago. Posted July 31, 2024. Scheduled to archive August 23, 2024.
Get the next one like this from Department of the Navy by email, the day it is posted.Find my opportunities
This one closed in 2024
107 like it are open now in ship building and repairing
- USCGC STURGEON (WPB-(87336) DS FY27
US Coast Guard, SFLC Procurement Branch 1
Combined synopsis and solicitationSmall businessNAICS 336611South Portland, ME70Z08026QPBPL0044Closes in 12 daysDec 8 - Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Contract (MAC) for Outsourcing Work on Availabilities on all Submarines
Department of the Navy, Team Submarine
SolicitationPartial small businessNAICS 336611Ship to Kittery, MEN0002427R4320Closes in 35 daysDec 31 - USNS CITY OF BISMARCK (T-EPF 9) VRA KR
Department of the Navy, NAVSUP FLT Log CTR Yokosuka
SolicitationNAICS 336611Outside the USN6264927RK003Due tomorrowNov 27
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Special notice. Industry days, draft requirements, program announcements and other notices that are not a solicitation. Glossary
- Who may compete
- Total small business set-aside. Only small businesses may compete. Small, under NAICS 336611 (ship building and repairing), means no more than 1,300 employees, counted with affiliates. Open Small business opportunities
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
Question 1: Will a thumb drive of general arrangement drawings, docking plan, railing systems components and other media be provided? Vessel “Drawing Package” whether via Thumb Drive or email in PDF format inclusive of vessel scantlings?
Answer 1: Will provide thumb drives on second site visit.
Question 2: Are the cleats being NDT inspected using Magnetic Particle Inspection Method? Please confirm that all deck hardware welds have to be blasted clean before MP testing is completed?
Answer 2: Yes, all mooring and towing fittings IAW Scope Question 3: Can pictures be provided (i.e pics of pad eye, barge dimensions)? Please provide pictures of YC-1580 deck and lettering on side shell if applicable and dogged hatch underside as well as raised coaming edge to show condition and areas that need to be straightened. Series of general photos of the vessels main deck, fore and aft and side shell would be helpful Answer 3: Pictures provided via e-mail Question 4: Do the Fenders get removed, and reinstalled?
Answer 4:
Per Statement of Work: In the section Underwater Hull and Freeboard Preservation, it states ”3.3 Mask, cover, and protect existing rubber fendering. Do not remove fendering for preservation requirements.”.
Question 5: Confirm what lettering is on the side of the Barge?
Answer 5: Lettering on the side of the barge is“U.S.
NAVY YC-1580” Questions 6: What is the thickness of the bottom plate? As well as side shell and deck.
Answer 6: Will be included in the vessel scantling drawings on thumb drive.
Questions 7: Can Subcontractor participate in the site visit?
Answer 7: Please advise requirements for a sub-contractor to be vetted for the visit Name, Company, Email, State of Residence, Phone number.
Question 8: Who is going to be performing the final inspection? Will Wade Eberhardt be the attending Owner’s Representative during the repair period?
Answer 8: HTC Wade Eberhardt will be the Owner Representative.
Question 9: Are the Hatches being replaced? If any hatches are being replaced are new welds to have MP testing completed ?
Answer 9: Yes, welds will require NDT inspection Question 10: After completion of 2nd site visit, what will be due date of bids ?
Answer 10: August 8th, 2024 @ 12:30 PM (EST)
Question 12: Item110-11-001, 3.3.3 – Please confirm this is crop and renewal plate insert and not double plates.
Answer 12: Crop and renewal plate insert Question 13: Item 123-21-001, 3.4.2 - Is the square footage of this area that receives hand tooling in lieu SP-10 blasting to be part of the 2000 sq. ft. listed in (3.4) or separate? If so, for bidding purposes what should we assign it for sq. ft.
Answer 13: Shall be included. 3.1.6 For touch-up, disturbed (terms are clarified in 3.6), and/or inaccessible areas, the minimum surface preparation must be that shown in Tables One through 8, except that an SSPC-SP 11 is acceptable for areas originally requiring a NACE 2/SSPC-SP 10 or NACE/SSPCSP WJ-2. The decision that an area is inaccessible must be determined by inspection and agreed to by the SUPERVISOR prior to surface preparation. The degree of surface preparation required would be the maximum possible for that area, but could include retention of existing tightly adherent paint in inaccessible areas as defined by the SUPERVISOR.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
July 31, 2024
Special notice, originally combined synopsis and solicitation
Due August 8, 2024 at 12:30 PM EDT. SAM.gov, notice 74d84910fa304cb484a248c095cbd841
Points of contact
- Bob Wattersrobert.watters@navy.mil2074382205