Presolicitation
Marshall Exploration Facility (MEF)
MSFCPS30-PROC-25001
National Aeronautics and Space Administration, NASA Marshall Space Flight Center. Commercial and Institutional Building Construction.
Response deadline
February 17, 2025 at 5:00 PM EST
Closed 647 days ago. Posted February 12, 2025, first published February 4, 2025. Scheduled to archive March 4, 2025.
Get the next one like this from National Aeronautics and Space Administration by email, the day it is posted.Find my opportunities
This one closed in 2025
184 like it are open now in commercial and institutional building construction
- Y1DA | 521-24-102 | Renovate Wards 2K and 2B for Optometry/Ophthalmology Clinical Use
Department of Veterans Affairs, 247-Network Contract Office 7
SolicitationSDVOSBNAICS 236220Alabama36C24726R0134Due todayNov 26 - Construction | 619-21-106 | EHRM Infrastructure Upgrades - Montgomery (VA-27-00002289)
Department of Veterans Affairs, Pcac
SolicitationSDVOSBNAICS 236220Montgomery, AL36C77626R0112Closes in 40 daysJan 5, 2027 - 614-326 Construct Parking Garage West Lot Addition Minor Construction
Department of Veterans Affairs, Pcac
PresolicitationSDVOSBNAICS 236220Memphis, TN36C77627B0003_1Due todayNov 26
All 184 open in commercial and institutional building construction
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Presolicitation. Advance notice that a solicitation is coming, usually within a few weeks. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 236220 (commercial and institutional building construction), means no more than $45 million in average annual receipts, counted with affiliates. What a set-aside is
- What comes next
- No solicitation was published under this number after the presolicitation of February 4, 2025. An agency sometimes issues the solicitation under a new number.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
RFI MSFCPS30-PROC-25001
Marshall Exploration Facility (MEF)
Marshall Space Flight Center (MSFC) is preparing to release a Design Build Request for Proposal (RFP) for an upcoming project to be completed at MSFC. The Government’s intent is to utilize Two-Phase Design-Build Selection Procedures (Phase 1 – Request for Qualifications / Phase 2 – RFP) with Best Value Trade-off Source Selection technique considering technical factors and price.
This is a request for information and is not to be construed as a commitment by the Government, implied or otherwise to issue a solicitation or ultimately award a contract. An award will not be made on offers received in response to this notice. This notice is not a request for proposal; it is a market research tool being utilized to determine the availability of qualified sources and receive comments on the below scope/description prior to issuing the RFQ and RFP.
Questions may be submitted via email on or before 4:00 p.m., Central Time, February 10, 2025 to the Contracting Officers Darlene Greene (darlene.greene@nasa.gov), Brian Speer (brian.a.speer@nasa.gov), Alicia Reynolds (alicia.r.reynolds) and Contract Specialist, Stephanie Darnell stephanie.darnell@nasa.gov.
The subject line shall contain ‘RFI Questions – MEF – [Company Name]. Any responses provided by NASA will be posted on SAM.gov as an amendment to the Request for Information.
The Government will not pay for effort expended in responding to this request.
Scope/Description
The National Aeronautics and Space Administration (NASA), Marshall Space Flight Center (MSFC) is requesting information on available Design-Build services for the complete design, and construction for the MEF. Architectural / Engineering (A&E) and Construction Services are required for the design and construction of MEF for NASA at MSFC located on Redstone Arsenal in Huntsville, AL. The estimated RFQ issuance date for this potential contract is Q3 2025.
The MEF will be approximately 50,000 to 80,000 gross square foot (GSF) and will accommodate a moderate number of full-time occupants mostly in an open office configuration with some private office space, and a large population of transient visitors utilizing the shared spaces. The overall building concept is a gateway and gathering space for to the MSFC campus with a large open event space, training spaces, meeting spaces, amenities, office and support spaces that will be flexible and adaptable to future program and technology changes.
The project should be designed to provide MSFC with a flexible collaborative environment that includes large event spaces, training spaces, meeting spaces, collaboration spaces, open office space, and administrative spaces. It will provide spaces for the NASA and MSFC communities to gather, work, and collaborate. The facility should be inviting and easily accessible from the primary courtyard and existing parking areas as it will become the home to many of the shared campus service. The second phase of the design-build solicitation will include more guidance on design and site requirements. The Phase 2 Solicitation will include a Program of Requirements to include Room Data Sheets, Division One Specifications, Campus Design Guide, Design and Construction Standards, Geotechnical Report, as well as the requirements for site access, site security, and construction logistics.
NASA is seeking a solution that enhances NASA’s footprint at Redstone Arsenal and compliments the completed campus development. The vision of the MSFC Campus is for the facilities and structures to provide a robust, creative, collaborative, forward-leaning environment for project development, training and active operations.
Interested offerors will be required to have a $55 million bonding capacity.
2-12-2025 MSFCPS30-PROC-25001 Amendment 1 includes the responses to submitted questions, provided as an attachment to the RFI.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- MEF RFI 2-3-25.pdf177 KB, February 4, 2025
- MEF RFI Amendment 1 Questions and Responses.pdf198 KB, February 12, 2025
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
February 4, 2025
Presolicitation
Due February 17, 2025 at 5:00 PM EST. SAM.gov, notice e536c6172fd444ca81e137d98fbad6b8
2 revisions on SAM
- February 12, 2025: publish, presolicitation
- February 4, 2025: publish, presolicitation
February 12, 2025
Presolicitation
Due February 17, 2025 at 5:00 PM EST. SAM.gov, notice 227ca2cccd394d2b9cb59111d69cfbe2
3 revisions on SAM
- May 7, 2025: publish, solicitation
- February 12, 2025: publish, presolicitation
- February 4, 2025: publish, presolicitation
Points of contact
- Darlene Greenedarlene.greene@nasa.gov2565442008
- Alicia Reynoldsalicia.r.reynolds@nasa.gov2565447923