Solicitation
Fermilab - Daycare Center Crawl Space Supports
ISD-357300-RYK
Department of Energy, Fermilab - DOE Contractor. Structural Steel and Precast Concrete Contractors.
Response deadline
October 11, 2024 at 4:00 PM EDT
Closed 775 days ago. Posted September 27, 2024. Scheduled to archive October 26, 2024.
Get the next one like this from Department of Energy by email, the day it is posted.Find my opportunities
This one closed in 2024
1 like it is open now in structural steel and precast concrete contractors
- FY27 NRM-Base (PROJ 516-23-604) BB - Install Temp Shoring in Crawl Space at Building 1
Department of Veterans Affairs, 248-Network Contract Office 8
PresolicitationSDVOSBNAICS 238120Bay Pines, FL36C24827R0028Closes in 55 daysJan 19, 2027
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Solicitation. A formal request for proposals, quotes or bids. Offers are due by the response deadline. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 238120 (structural steel and precast concrete contractors), means no more than $19 million in average annual receipts, counted with affiliates. What a set-aside is
- Time to respond
- Bidders had 14 days from the day the solicitation was posted, September 27, 2024, to the deadline.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
1.0 INTRODUCTION AND BACKGROUND Fermilab is requesting a proposal for removal and replacement of crawl space jack posts, demolition of existing concrete footings, and installation of new footings at the Daycare Center building. The existing jack posts are in various stages of deterioration and require replacement. Additionally, the existing footings are undersized and new footings are required. 2.0 SCOPE Provide all work as shown on : ? Drawing set for ISD Project 10-2-153 ?
Specification Sections: o 010010 GENERAL REQUIREMENTS o 013100 ENVIRONMENT, SAFETY, AND HEALTH REQUIREMENTS o 013300 SUBMITTALS o 014100 QUALITY REQUIREMENTS The Subcontractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications.
All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings and technical specifications. The Subcontractor’s scope of work is not limited to the general work outline described herein. The Subcontractor shall perform all work required to complete the construction work in accordance with the drawings and/or specifications.
The description and quantities listed are general in nature and are only intended to describe the range and complexity of this scope of work. The description and quantities provided below are not to be used as the basis for establishing a cost proposal. Specific quantities and definitions of the scope of work for providing a proposal shall be based solely on estimates developed by the Offer from the drawings, specifications, and the information obtained from examining of the project site.
Confined space training is required for work in the crawl spaces. 3.0 DELIVERABLES The Subcontractor shall perform all work required to complete the construction work in accordance with the drawings and specifications. 4.0 QUALITY ASSURANCE A Fermilab Construction Coordinator will be assigned to this project. See Specification Section 010010, GENERAL REQUIREMENTS. The Subcontractor is responsible for all activities necessary to manage, control, and document that work complies with the Subcontract documents. The Subcontractor’s responsibility includes ensuring adequate Quality Control services are provided for work accomplished on- and off-site by his/her organization,
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
September 27, 2024
Solicitation
Due October 11, 2024 at 4:00 PM EDT. SAM.gov, notice db31cc280ffe4d9d9d749c6131071bd8
Points of contact
- Richard Konanrkonan@fnal.gov6308402835