Solicitation, total small business set-aside, first published as presolicitation
TAFB MACC-BOA | Formal RFP for WWYK050751 - Repair/Replace Main Distribution & Branch Panel Boards, Bldg. 6002
FA813726R0038
Department of the Air Force, FA8137 AFSC Pzioc. Electrical Contractors and Other Wiring Installation Contractors.
Response deadline
July 3, 2026 at 6:00 PM EDT
Closed 145 days ago. Posted June 18, 2026, first published May 15, 2026. Scheduled to archive July 18, 2026.
Get the next one like this from Department of the Air Force by email, the day it is posted.Find my opportunities
This one closed in 2026
41 like it are open now in electrical contractors and other wiring installation contractors
- Electrical Construction Services IDIQ - MMAC
Federal Aviation Administration, 6973GH Franchise Acquisition SVCS
Sources soughtSmall businessNAICS 238210Oklahoma City, OKMRKTSVY-26-ElecIDIQCloses in 14 daysDec 9 - Electrical Installation of 5-Station Cubicle and One Single Hotel Desk Arrangement
Agricultural Research Service, USDA ARS Afm Apd
Combined synopsis and solicitationSmall businessNAICS 238210Madison, WI1232SA27Q0021Due todayNov 25 - USDA Forest Service - Hebgen Lake District Office Network Cabling and IT Room Improvements
Forest Service, Usda-Fs, Csa Intermountain 9
Combined synopsis and solicitationSmall businessNAICS 238210West Yellowstone, MT1240LU26Q0132Due tomorrowNov 26
All 41 open in electrical contractors and other wiring installation contractors
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Solicitation. A formal request for proposals, quotes or bids. Offers are due by the response deadline. Glossary
- Who may compete
- Total small business set-aside. Only small businesses may compete. Small, under NAICS 238210 (electrical contractors and other wiring installation contractors), means no more than $19 million in average annual receipts, counted with affiliates. Open Small business opportunities
- Time to respond
- Bidders had 35 days from the day the solicitation was posted, May 29, 2026, to the deadline. The deadline moved 2 times: it was first June 1, 2026 and ended as July 3, 2026.
- Before the solicitation
- The agency published a presolicitation on May 15, 2026, 14 days before the solicitation.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
This order proposal request is only available to current MACC-BOA holders.
The work to be performed under the terms of this Order consists of furnishing all materials, labor, plant, tools, transportation, equipment, testing services, quality control, and incidentals required to accomplish the repair/replacement of the main distribution & branch panel boards in building 6002 at Tinker Air Force Base (AFB), Oklahoma (reference the project drawings for additional location information). This is a construction-only order.
The Contractor shall perform a site investigation to verify existing conditions. If necessary, additional as-built drawings are available from 72 ABW/CE - Engineering Support, located in B400 on Tinker AFB.
The Contractor shall be responsible for identifying the necessary logistical, architectural, and structural work elements required to perform the work as described herein. Assemblies, framework, fixtures, or apparatus not readily identified on the project drawings, specifications, or the Statement of Work (SOW) shall be provided by the Contractor as required for a complete, fully operating, and functioning system or systems ready for use by the Government.
Information such as floor plan layouts and dimensions; structural, mechanical, and electrical data; and location of underground utilities provided by the Government for existing and new construction are based on available as-built documentation, field observation, and equipment selected as design basis by the Government. This information is to be considered approximate and shall be field verified by the Contractor.
This project will not require contractor personnel to perform work and/or operate vehicles on flight lines, runways, taxiways, parking ramps, or in aircraft hangers or maintenance areas. However, all contractor personnel are still required to receive FOD awareness training in accordance with Tinker Air Force Base Instruction (Tinker AFBI) 21-100.
IAW National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171, the requirement does not include CUI residing on or transiting through contractor and/or subcontractor systems.
Site visit attendance is mandatory to be considered eligible for submission of proposal. RSVP email confirmation of intent to attend the site visit to the primary and secondary points of contact with Entry Authorization List (EAL) information by 11:59 PM CST, Friday, May 22nd, 2026. If a Contractor/Subcontractor fails to meet this deadline, the site visit information will not be released to your organization. Order documents not able to be uploaded to SAM.gov will be provided to contractors who RSVP'd their intent to attend the initial site visit.
Attachments include an EAL spreadsheet. Please fill-in all information for individuals who will need/do not currently have Base access. Please ensure all information requested in the EAL is filled out accurately and full names matching state-issued IDs are utilized to assure Security Forces can process the requests for Base Access in a timely manner. If an individual has Base access, their name is all the information needed. Please try to limit your parties to seven attendees per Contractor.
The site visit is scheduled for June 3rd, 2026 at 10:00 A.M at the project performance site. More specific meeting details will be shared with contractors who have sent an RSVP.
The due date for the RFIs arising from the site visit is currently set for June 8th, 2026 at 5:00 PM CST. RFIs will be answered in a timely manner, and RFI responses will be shared with all site visit attendees.
This notice signifies the release of the formal RFP for Project No. WWYK050751 - Repair/Replace Main Distribution & Branch Panel Boards, Bldg. 6002. The due date for proposals is currently July 3rd, 2026 at 5:00 PM CST but is subject to be extended dependent upon RFI responses. Any extensions granted to the proposal due date will be updated to this posting. Please see the attachments for the formal RFP as well as the attachments referenced in the body of the formal RFP. Responses to received RFIs may warrant revisions to associated RFP documents so be sure to monitor this SAM posting for updates.
In lieu of the physical CD, some additional documents have been added to the attachments section including the Project Docs, Facility Standards, and some additional large files. Please contact the primary and secondary points of contact if you experience any difficulty downloading or accessing the documents.
All RFI responses have been received and compiled. Please see the attachments for the RFI responses. Utilize these in continuing to formulate your proposals. If RFI responses prompt a need for an extension to the proposal due date, please communicate that to the primary and secondary points of contact, and any extensions granted will be updated to this posting.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- 050751_SOW.pdf312 KB, May 15, 2026
- 050751_SOW.pdf312 KB, May 29, 2026
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
May 15, 2026
Presolicitation
TAFB MACC-BOA | Initial Site Visit for WWYK050751 - Repair/Replace Main Distribution & Branch Panel Boards, Bldg. 6002
Due June 1, 2026 at 11:00 AM EDT. SAM.gov, notice bcc16d0dc6a54f30be229d2f7f3494d3
2 revisions on SAM
- May 29, 2026: publish, presolicitation
- May 15, 2026: publish, presolicitation
May 29, 2026
Presolicitation
TAFB MACC-BOA | Initial Site Visit for WWYK050751 - Repair/Replace Main Distribution & Branch Panel Boards, Bldg. 6002
Due June 3, 2026 at 11:00 AM EDT. SAM.gov, notice 3e0a2f4970ed4ec8a12c94ea773510e3
3 revisions on SAM
- May 29, 2026: publish, presolicitation
- May 29, 2026: publish, solicitation
- May 15, 2026: publish, presolicitation
May 29, 2026
Solicitation, originally presolicitation
Due July 3, 2026 at 6:00 PM EDT. SAM.gov, notice f19004c99a95408ea2899e2beced43e3
5 revisions on SAM
- June 18, 2026: publish, solicitation
- May 29, 2026: publish, presolicitation
- June 3, 2026: publish, solicitation
- June 3, 2026: publish, solicitation
- May 29, 2026: publish, solicitation
June 3, 2026
Solicitation
Due July 3, 2026 at 6:00 PM EDT. SAM.gov, notice 10d6af1b44704e429d0f5499e83e6d73
5 revisions on SAM
- June 18, 2026: publish, solicitation
- May 29, 2026: publish, presolicitation
- June 3, 2026: publish, solicitation
- June 3, 2026: publish, solicitation
- May 29, 2026: publish, solicitation
June 3, 2026
Solicitation
Due July 3, 2026 at 6:00 PM EDT. SAM.gov, notice 4d93fcac604f4c869e3f907bb8ebefb3
5 revisions on SAM
- June 18, 2026: publish, solicitation
- May 29, 2026: publish, presolicitation
- June 3, 2026: publish, solicitation
- June 3, 2026: publish, solicitation
- May 29, 2026: publish, solicitation
June 18, 2026
Solicitation
Due July 3, 2026 at 6:00 PM EDT. SAM.gov, notice 971f5e4298434d9d878682f6c5296e67
5 revisions on SAM
- June 18, 2026: publish, solicitation
- May 29, 2026: publish, presolicitation
- June 3, 2026: publish, solicitation
- June 3, 2026: publish, solicitation
- May 29, 2026: publish, solicitation
Points of contact
- Sharla Flowerssharla.flowers_brandon.1@us.af.mil
- Michael Johnsonmichael.johnson.404@us.af.mil4056202913