Combined synopsis and solicitation, total small business set-aside
USCGC ALDER GALLEY VENT CLEANING
70Z085Q0987
US Coast Guard, SFLC Procurement Branch 2. Ship Building and Repairing.
Response deadline
May 2, 2025 at 11:00 AM EDT
Closed 572 days ago. Posted April 18, 2025. Scheduled to archive May 2, 2025.
Get the next one like this from US Coast Guard by email, the day it is posted.Find my opportunities
This one closed in 2025
105 like it are open now in ship building and repairing
- USCG STA SAN FRANCISCO (45667) FY27 DD REPAIRS
US Coast Guard, Cg-Sea-C23
Combined synopsis and solicitationSmall businessNAICS 336611San Francisco, CA70ZU0327QSBPL0001Due in 7 daysDec 2 - Dock-side (DS): USCGC WAESCHE Quarter 2 FY27 Repair
US Coast Guard, Cg-Sea-C22
Combined synopsis and solicitationSmall businessNAICS 336611Alameda, CA70Z08527QLREP0001Closes in 12 daysDec 7 - CGC NEAH BAY ANCHOR WINDLASS REPAIRS
US Coast Guard, Cg-Sea-C22
Combined synopsis and solicitationSmall businessNAICS 336611Ship to Cleveland, OH70ZU0227Q0001147Due todayNov 25
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Combined synopsis and solicitation. A streamlined commercial-item buy where the notice itself is the solicitation. Glossary
- Who may compete
- Total small business set-aside. Only small businesses may compete. Small, under NAICS 336611 (ship building and repairing), means no more than 1,300 employees, counted with affiliates. Open Small business opportunities
- Time to respond
- Bidders had 14 days from the day the solicitation was posted, April 18, 2025, to the deadline.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
SCOPE OF WORK U. S. COAST GUARD CUTTER ALDER
- ITEM 1: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the designated shipboard ventilation systems.
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings
Coast Guard Drawing 225B WLB 512-001, Rev K, HVAC Diagram
Coast Guard Drawing 225B WLB 512-007, Rev B, HVAC A&D, Fr 66-92, Innerbttm & 1st Platform
Coast Guard Drawing 225 WLB 259-005, Rev C, Combustion Intake & Exhaust A&D Hull Block 940
Coast Guard Publications
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean Shipboard Ventilation Systems
Coast Guard Technical Publication (TP) 3796, Section A, Aug 2006, Galley Hood – Model NBDL-60 (13’-4”)
Other References
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
- Ducting screens.
- Electric pre-heaters.
- Overhead sheathing/panels.
- Ventilation covers.
note
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard Personnel perform an initial operational test of the ventilation systems included in this work item, to demonstrate existing operational condition. Submit a CFR.
NOTE
It is recommended that the Contractor conduct a ship check to verify dimensions in the table below.
3.3 Cleaning requirements. The Contractor must clean and inspect the following ventilation systems, shown on Coast Guard Drawings 225B WLB 512-001, 225B WLB 512-007, and 225 WLB 259-005, in accordance with SFLC Std Spec 5100. Submit a CFR.
table – 1 system location
SYSTEM LOCATION
TYPE
Galley
Supply
1-57-1-Q (Galley)
Exhaust
3.4 Additional requirements. In addition to the above, the Contractor must accomplish the following:
3.4.1 Additional protective covering. In addition to providing protective covering as specified in SFLC Std Spec 5100, subsection 3.1.3 (Protective measures), provide additional protective covering for all food preparation and serving surfaces in the immediate work area, as applicable, to prevent contamination.
3.4.2 Avoidance of meal preparation and service. Ensure that cleaning of galley ventilation systems is scheduled between 1900 and 0530 so that it WILL NOT interfere with meal preparation and service.
**If unable to work between 1900 and 0530 ships force will work the KTR work schedule. **
note
Coast Guard personnel will operate all shipboard machinery and equipment.
3.5 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the ventilation systems included in this work item to be in satisfactory operating condition. Submit a CFR.
4. NOTES
CGC ALDER
USCGC ALDER (WLB-216)
1 Yerba Buena Island
San Francisco, CA 94130
Ph: (415) 399-3590
Chris Laterza, ENG2
Engineer Officer
Period of Performance 12 May to 27 May 2025
RDD/POP: 19 July to 31 July 2025
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- CGC ALDER GALLEY VENT CLEAN SOW.doc54 KB, April 18, 2025
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
April 18, 2025
Combined synopsis and solicitation
Due May 2, 2025 at 11:00 AM EDT. SAM.gov, notice 5b2ed51f7de94196bcc8161a1cf5fc59
1 revision on SAM
- April 18, 2025: publish, combined synopsis and solicitation
Points of contact
- BRENDEN COXBRENDEN.S.COX@USCG.MIL12068315347