Combined synopsis and solicitation, total small business set-aside
USCGC MUNRO LOAD BANK TESTING
70Z08526Q024134
US Coast Guard, SFLC Procurement Branch 2. Ship Building and Repairing.
Awarded
$58,845.00 obligated so far on USAspending
Get the next one like this from US Coast Guard by email, the day it is posted.Find my opportunities
This one was awarded in 2026
107 like it are open now in ship building and repairing
- USCG STA SAN FRANCISCO (45667) FY27 DD REPAIRS
US Coast Guard, Cg-Sea-C23
Combined synopsis and solicitationSmall businessNAICS 336611San Francisco, CA70ZU0327QSBPL0001Due in 7 daysDec 2 - Dock-side (DS): USCGC WAESCHE Quarter 2 FY27 Repair
US Coast Guard, Cg-Sea-C22
Combined synopsis and solicitationSmall businessNAICS 336611Alameda, CA70Z08527QLREP0001Closes in 12 daysDec 7 - USS HERSHEL WOODY WILLIAMS VRA
Department of the Navy, NAVSUP FLC Bahrain
SolicitationNAICS 336611Florida, PRN4033927RF502Due todayNov 25
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Combined synopsis and solicitation. A streamlined commercial-item buy where the notice itself is the solicitation. Glossary
- Who may compete
- Total small business set-aside. Only small businesses may compete. Small, under NAICS 336611 (ship building and repairing), means no more than 1,300 employees, counted with affiliates. Open Small business opportunities
- Time to respond
- Bidders had 11 days from the day the solicitation was posted, April 16, 2026, to the deadline.
- How it ended
- Awarded to Stilten, Ltd. Co. on April 29, 2026, 2 days after offers were due. The contracting office reported 7 offers (competed under simplified acquisition procedures).
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
This is a combined synopsis/solicitation
This is a combined synopsis/solicitation for commercial items/services prepared in accordance with the format in FAR Subpart 12.6 as supplemented with additional information included in this notice. Request for Quotations number is 70Z08526Q024134 and is issued as a request for quotations (RFQ). This announcement constitutes only solicitation; quotations are being requested, and a written solicitation will not be issued. This Request for Quotations incorporates provisions and clauses in effect through Federal Acquisition Circular 2005-65 dated January 29, 2013. The NAICS Code is 336611. The small business size standard is 1250. This is a totally small business set aside. All responsible sources may submit proposals that will be considered by the agency. The contract will be awarded on a firm-fixed-price basis using simplified acquisition procedures in accordance with FAR Part 13.5. All responses from interested vendors must be received on/before 0800 Pacific Time, April 27, 2026, and will be reviewed by the Government.
The United States Coast Guard Surface Force Logistics Center has a requirement for the following:
Contractor shall provide parts requested for USCGC Munro Load Bank Testing:
SOW for #2 & #3 SSDGs Load Bank Testing
USCGC MUNRO (WMSL-755)
- This solicitation is to provide:
Load bank testing of the #1 & #2 SSDGs for CGC MUNRO
- Vendor to Perform work at ships homeport:
CGC MUNRO
UNITED STATES COAST GUARD BASE ALAMEDA
1 EAGLE ROAD ALAMEDA, CA 94501
- Security requirements: No special security requirements needed. Vendor will only require base and ship access during POP.
- POP: 28APR2026 – 26MAY2026
- POC:
- MUNRO Engineer Officer:
- LCDR John Hamel
- (571) 608-4553
- MUNRO Port Engineer:
- LTJG Bethani Hartman
- (571) 608-9108
- MUNRO APM:
- LTJG David Robbins
- (808) 373-6155
31100_BEC_0924_418
- ITEM 1: WORK ITEM 1: Ship Service Diesel Generator, Load testing, perform
1. SCOPE
z
1.1 Intent. This work item describes the requirements for the Contractor to perform load testing of designated Ship Service Diesel Generator (i.e., SSDG) listed in Table 1.
TABLE 1 – LIST OF SHIP SERVICE GENERATOR
CATERPILLAR mODEL NO.
DESCRIPTION
location
3512B
No.02 Ship Service Diesel Generator (NSC 009), 1360 KW, 450 Volt AC, 3 Phase, 60 Hz
Auxiliary Machinery Room (5-36-01-E)
3512B
No.03 Ship Service Diesel Generator (NSC 009), 1360 KW, 450 Volt AC, 3 Phase, 60 Hz
Ship Service Diesel Generator Room
(7-76-5-Q)
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings
Coast Guard Drawing 750-WMSL-501-002, Rev E, Machinery Arrangements (ASC501001)
Coast Guard Drawing 418A-WMSL-801-002, Rev A, Booklet of General Plans
Coast Guard Publications
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Coast Guard Technical Publication (TP) 7119, Ship Service Diesel Generator - Model 3512B
Coast Guard Technical Publication (TP) 7165B, Ship Service Switchboards 1S, 2S, 3S & 1SP Shore Power – Operation, Maintenance & Installation – Volume 1
Coast Guard Technical Publication (TP) 7166B, Ship Service Switchboards 1S, 2S, 3S & 1SP Shore Power – Operation, Maintenance & Installation – Volume 2 & 4
Coast Guard Technical Publication (TP) 7167, Ship Service Switchboards 1S, 2S, 3S & 1SP Shore Power – Operation, Maintenance & Installation – Volume 3
Other References
COMDTINST 9077.1 (series) Equipment Lockout-Tags-Plus Instruction
MIL-STD-1310, Sep 2009, Shipboard Bonding, Grounding, and Other Techniques for Electromagnetic Compatibility and Safety
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
- Piping
- Electrical Cables
- Switchboard Enclosure
- Vent Ducting
- Motor Operated Valves
3.1.5 Background information. SSDG listed in Table 1 will be modified by the Coast Guard for the following task:
- Generator Bearing Replacement
- Shaft Alignment
- Pinning and Machine Work
- Diesel Engine Top-end Overhaul
3.1.5.1 After completion of above listed tasks, this Work Item is to be used for the Contractor to perform load testing of designated SSDG listed in Table 1.
3.2 Work location. The concerned work area is listed in Table 1. See the applicable drawings in References in Paragraph 2 for guidance, locations, and details.
3.2.1 Proposed temporary cable routing must be developed using USCG Dwg 418A-WMSL-801-001. Submit a CFR.
3.2.1.1 Temporary load bank cables must be routed from the switchboard to the load bank via a single route, and must not be routed separately by any method which would lead to unbalanced phase cables to transit through hull or bulkhead openings.
3.3 Grounding. The Contractor must ensure conductive surfaces of the load bank enclosure are appropriately bonded and grounded for protection of personnel.
3.4 Contractor Furnished Materials (CFM). The Contractor must furnish materials listed in the Table 2 for load testing of the SSDG listed in Table 1.
TABLE 2 – CONTRACTOR furnish MATERIALS
MATERIALS
description
SOURCE OF SUPPLY
Load Bank
1500 KW, 450 Volt AC, 3 Phase, 60 Hz, Resistive
Electrical Equipment’s Rental Company
Load Bank Cables
Approximate length of 300 Feet Cables with ring tongue compression lugs, 6 Paralleled #4/0 copper (single conductor) per phase (18 Total x 300 Feet) and one additional length for the equipment grounding conductor or Six LSTSGU-400
Tony Santiago
Murray Benjamin Electric
397 West Ave.
Stamford CT 06902
(203-705-2100) OR Any Electrical Cable Supplier
3.4.1 The contractor must provide miscellaneous hardware required for electrical installation (i.e. Nylon Stuffing Tubes, Chafing Gear, Box Connectors, Lugs, Fasteners, Wire Nuts, Tapes, Cable ties & Cable Mounting Brackets, etc) of the electrical equipment.
3.5 Load testing. The Contractor must provide labor and crane services as necessary for placing load bank at suitable location (i.e., On the pier or the ship). After completion of load bank testing of SSDG, the Contractor must remove all installed equipment and cables used during testing.
3.5.1 Testing plan. The Contractor must submit a plan for load testing of the SSDG in accordance with TP 7119.
3.5.1.1 The plan must cover the following topics at a minimum:
- Steady increase of load in multiple steps up to 100% real power load
- No less than 2 hours of continuous testing at 100% load
- Simulated start of 450 HP load (assume no more than 200% FLA)
- Emergency shutdown procedures
- Load bank specification and location
- Cable locations for load bank
- No-load tests
- Data to be collected during tests
- All proposed connections, cable and load bank configurations
3.5.1.2 The Contractor must start testing of the SSDG after COR Approval of submitted Test Plan and official acceptance by the Contract Officer (KO).
3.5.2 After placing load bank at suitable location (i.e., On the pier or the ship) the Contractor must install the cables from the load bank to associated SS Switchboard bus bars (i.e. Back side of SS Switchboard No.2S), according to the agreed upon cable routing.
CAUTION
THE BACK SIDE OF THE SWITCHBOARD SHOULD BE ROPED OFF AS A PERSONNEL EXCLUSION AREA (APPROXIMATELY 10 FOOT RADIUS FROM ANY VISIBLE LIVE BUS
3.5.2.1 The Contractor must route the cables from designated SSDG to load bank through hatches and passageway. The Contractor must run cables in overheads as much as possible to avoid trip hazards.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
SAFETY
At any point in the load test or operational testing period if the need presents itself the engine – Prime mover may be shut down by the Tech rep with communication to the USCG operational Engineer utilizing the local EOS, E stop or shut down from the switch gear. Any of the three options will automatically open the SSDG buss breaker
3.5.3 After warmup of SSDG until coolant temperature reaching 140 Degree F, the Contractor must perform the load testing of designated SSDG listed in Table 1 at following load condition.
TABLE 3 – LOAD TESTING
LOAD
HOURS
*No Load
0.5 Hrs
25 % Load
0.5 Hrs
50 % Load
0.5 Hrs
75 % Load
0.5 Hrs
100 % Load
2.0 Hrs
No Load
0.5 Hrs
- Running no load testing. No load testing will consist of running the engine at idle rpm until the engine coolant temperature reaches 140 deg. F during that warmup time safety testing will be performed for oil pressure, temp warning, emergency shut down conditions, and coolant temp. warning and shutdown. Shipboard alarm verification will be observed at that time as well.
3.5.3.1 Engine parameter readings during the load bank test must be taken every 15 minutes including, but not limited to the bullet points in this paragraph. Submit a CFR.
- Engine temp, Coolant temp, oil pressure, boost pressure, intake air temp after the aftercooler, exhaust stack temp, left and right bank exhaust temperatures.
- In addition to the generator load test form, a Caterpillar steady state engine performance file shall be recorded on the engine ECM all related available information.
- Generator information, voltage reading per phase, amperage readings per phase, HZ, bearing and winding temps.
- Pre and post-test PSSRP shall be saved on the ECM to provide verification of all available diagnostic codes and events.
- All electronic files and reports must be submitted via CFR.
3.6 Load test documentation. After completion of testing, the Contractor must provide all collected data sheets to the Contracting Officer.
4. NOTES
This section is not applicable to this work item.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- This is a combined synopsis solicitation 70Z08526Q024134.docx40 KB, April 16, 2026
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Stilten, Ltd. Co.
- UEI
- RN65DQEQK1M6
- CAGE
- 7DHF2
- Vendor location
- Houston, TX
- Contract
- 70Z08526PLREP0146, purchase order
- Obligated
- $58,845.00
- Actions
- 1 between April 29, 2026 and April 29, 2026
- Competition
- Competed Under SAP, 7 offers received
- Set-aside reported
- Small Business Set Aside - Total
- Described as
- CGC Munro - Load Bank Test SSDG #2 and #3
- Match
- solicitation number 70Z08526Q024134 equals the FPDS solicitation identifier; same awarding office 70Z085 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
April 16, 2026
Combined synopsis and solicitation
Due April 27, 2026 at 11:00 AM EDT. SAM.gov, notice 6ba2de62f2b8453380b0b209ff626ef5
1 revision on SAM
- April 16, 2026: publish, combined synopsis and solicitation
Points of contact
- McTague, SeanSean.P.McTague@uscg.mil15716143888
- ULISES BALMACEDAUlises.O.Balmaceda@uscg.mil2068200307