Special notice, total small business set-aside
USCGC Hollyhock Davit repair
70Z08525Q0020749
US Coast Guard, SFLC Procurement Branch 2. Ship Building and Repairing.
Response deadline
July 21, 2025 at 8:00 AM EDT
Closed 493 days ago. Posted July 16, 2025. Scheduled to archive August 5, 2025.
Get the next one like this from US Coast Guard by email, the day it is posted.Find my opportunities
This one closed in 2025
107 like it are open now in ship building and repairing
- Request for Information: U.S. Shipyard and Vessel Construction Manager Capability for Floating Drydock Construction
US Coast Guard, Cg-Sea-C11
Sources soughtNAICS 336611Ship to Baltimore, MDCG-SEA-C11-FDD-RFI-2027Due in 6 daysDec 2 - POWER TRIM TILT ASSY
US Coast Guard, Cg-Sea-C23
Combined synopsis and solicitationSmall businessNAICS 336611Ship to MD70ZU0327Q50205B00Due in 7 daysDec 3 - NONSKID AND DECK PRESERVATION
US Coast Guard, Cg-Sea-C23
Combined synopsis and solicitationSmall businessNAICS 336611Maryland70ZU0327Q60520Y00Closes in 8 daysDec 4
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Special notice. Industry days, draft requirements, program announcements and other notices that are not a solicitation. Glossary
- Who may compete
- Total small business set-aside. Only small businesses may compete. Small, under NAICS 336611 (ship building and repairing), means no more than 1,300 employees, counted with affiliates. Open Small business opportunities
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
This is for informational purposes only. This was awarded VIA JOTFOC due to urgency.
STATEMENT OF WORK (SOW)
- BACKGROUND
CGC Hollyhock recently had a discrepancy of water intrusion inside the cabinet of their Welin Lambie Dual Point Davit. The discrepancy required a replacement main inverter to correct the issues. However, the crew was unable to determine the root cause or potential of cascading issues from the casualty. CGC Hollyhock requires a Welin Lambie certified Tech-Rep to go through and reevaluate and test the system. In addition to recertifying the system, CTR must replace the adjustable elbow fitting outlined below which cause a major hydraulic leak due to a failed O-Ring.
- REFERENCE
- REQUIREMENTS
-
-
-
- PROPOSAL TO PROVIDE (1) SENIOR FIELD SERVICE TECHNICIAN WORKING (10) HOURS PER DAY FOR (1) DAY - TECH REP TO ASSIST WITH PARTS INSTALL, CONDUCT DAVIT ASSESMENT, AND WITNESS DAVIT OPERATIONS. ANY NOTED DISCREPANCIES WILL BE REPORTED VIA CFR PROCESS.
-
-
-
-
-
- SUPPLY AND INSTALL THE FOLLOWING PARTS WHILE ON SITE:
-
-
- 4.0 ADMINISTRATION.
4.1 CONTRACTOR PERSONELL
4.1.1 Qualified Personnel.
The Contractor shall provide qualified personnel and subject matter experts to perform all required tasks specified in this SOW.
4.1.2 Employee Conduct.
Contractor employees shall present a professional appearance, and their conduct shall not reflect discredit upon the U.S. Government, and any involved Departments or Agencies. Contractor employees shall comply with all applicable Government regulations, policies, and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of military uniforms, and possession of weapons) when visiting or working at Government facilities.
4.1.3 Conflict of Interest.
The Contractor shall not employ any person who is an employee of the U.S. Government if that employment would, or would appear to cause, a conflict of interest. The Contractor shall take appropriate precautions as delineated in the Federal Acquisition Regulation (FAR) to preclude actual or apparent conflicts of interest.
4.1.4 Base Access
U.S Coast Guard Yard requires registration for guest access from contractors. Contractor must provide a valid I.D and name to the USCG POC’s no later than one week prior to the commencement of the contract to gain base access.
4.2 PERIOD OF PERFORMANCE.
One day on site between 18JULY-01AUG
4.3 PLACE OF PERFORMANCE.
CGC Hollyhock
2401 Hawkins Point Rd Baltimore, MD.
Pier 1
5.0 USCG POC’S
CGC HOLLYHOCK
2401 Hawkins Point Rd
Baltimore, MD 21226
POC Adam D. Barton, ENG4 Engineer Officer
571-607-5222
Email: Adam.D.Barton@uscg.mil
Product Line Support:
ENS Marcos Saldarriaga
marcos.a.saldarriaga@uscg.mil
667-419-5729
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- Scope of Work - Hollyhock WL parts and service.pdf124 KB, July 16, 2025
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
July 16, 2025
Special notice
Due July 21, 2025 at 8:00 AM EDT. SAM.gov, notice a51b9e20d278416d84bccdd38601e9b6
1 revision on SAM
- July 16, 2025: publish, special notice
Points of contact
- Justin Wooldridgejustin.r.wooldridge2@uscg.mil2068205327
- Lindsay Mongiovilindsay.n.mongiovi@uscg.mil5716086752