Special notice, total small business set-aside
USCGC Stone- Supply Fan motor repair
70Z08525Q00020128
US Coast Guard, SFLC Procurement Branch 2. Ship Building and Repairing.
Response deadline
June 28, 2025 at 11:00 AM EDT
Closed 516 days ago. Posted June 23, 2025. Scheduled to archive July 13, 2025.
Get the next one like this from US Coast Guard by email, the day it is posted.Find my opportunities
This one closed in 2025
107 like it are open now in ship building and repairing
- Announcement for Upcoming 2027 NSRP Panel Project Solicitation
Department of the Navy, NAVSEA HQ
SolicitationNAICS 336611Summerville, SCNSRP-PP-27Due in 5 daysDec 1 - USCGC HAMILTON (WMSL 753) DS, FY27, FQ3
US Coast Guard, Cg-Sea-C22
Combined synopsis and solicitationSmall businessNAICS 336611North Charleston, SC70ZU0227QLREP0001Closes in 14 daysDec 10 - FM 200
US Coast Guard, SFLC Procurement Branch 3
Combined synopsis and solicitationSmall businessNAICS 336611Charleston, SC52000PR260001597Closes in 30 daysDec 26
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Special notice. Industry days, draft requirements, program announcements and other notices that are not a solicitation. Glossary
- Who may compete
- Total small business set-aside. Only small businesses may compete. Small, under NAICS 336611 (ship building and repairing), means no more than 1,300 employees, counted with affiliates. Open Small business opportunities
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
Statement of Work (SOW) for supply fan motor for CGC Stone.
- Background. The supply fan motor onboard CGC Stone has bad windings requiring the motor to be repaired.
- Scope. Conduct repair on Qty: 1, P/N: XA20A4W5, NIIN: 016035356, Name: FAN 3 PHASE, 440 VAC, 60HZ, CCW ROTATION, 1800 CFM. 6 IMP BLADES, 20/6 HP.
- Objective. The objective of this requirement is to repair the supply fan after findings of failed motor windings. Conduct at least the following to return to the Coast Guard a working motor: must be returned to the below address by 07JUL25.
- Disassemble and visually inspect
- Mechanical inspection
- Incoming electrical testing
- Thoroughly clean all parts
- Repair de bearing journal
- Take winding data
- Strip winding
- Core loss test
- Sandblast
- Repair/replace leads
- Rewind/repair stator
- Manufacture coils
- Dip/bake/vpi
- Post bake - clean parts
- Dynamically balance
- Re-assemble
- Post testing no-load run
- Paint
- Pre-ship quality inspection
Materials: 6210 ball bearing 1, 6212 ball bearing 1, Seal 1, Winding wire and materials
- Security Requirement. FLETC Base Charleston access is required. Vendor shall have a valid Real ID compliant form of ID and show identification. Forms will be provided for base access. A CG representative from the cutter may sponsor and escort vendor to the cutter.
- Delivery Address:
USCGC STONE (WMSL 758)
ATTN: Discrep 25042
1050 Register St.
N. Charleston, SC 29405
- Required Delivery Date. 07JUL25
- Points of Contact.
USCG-SFLC-LREPL Asset Management:
MKCM Bryan Briggs
Bryan.P.Briggs@uscg.mil
(510) 418-2223
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- SOW - 25042 - supply fan repair.docx28 KB, June 23, 2025
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
June 23, 2025
Special notice
Due June 28, 2025 at 11:00 AM EDT. SAM.gov, notice 60bc504a05f74faaafc29fdef86d6d63
1 revision on SAM
- June 23, 2025: publish, special notice
Points of contact
- Justin Wooldridgejustin.r.wooldridge2@uscg.mil2068205327
- Lindsay Mongiovilindsay.n.mongiovi@uscg.mil5716086752