Solicitation
ANTI-SWEAT INSULATION REMOVAL AND REPLACEMENT (CGC RESOLUTE)
70Z080SSNINSULATION
US Coast Guard, SFLC Procurement Branch 1. Drywall and Insulation Contractors.
Response deadline
September 23, 2024 at 9:00 AM EDT
Closed 793 days ago. Posted September 18, 2024, first published September 2, 2024. Scheduled to archive November 1, 2024.
Get the next one like this from US Coast Guard by email, the day it is posted.Find my opportunities
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Solicitation. A formal request for proposals, quotes or bids. Offers are due by the response deadline. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 238310 (drywall and insulation contractors), means no more than $19 million in average annual receipts, counted with affiliates. What a set-aside is
- Time to respond
- Bidders had 21 days from the day the solicitation was posted, September 2, 2024, to the deadline. The deadline moved once: it was first October 20, 2024 and ended as September 23, 2024.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
ANIT-SWEAT INSULATION REMOVAL AND REPLACEMENT FOR CGC RESOLUTE.
5.2 Detailed Tasks: 5.2.1 The contractor shall remove and dispose of existing insulation in select areas. 5.2.2 Install approx. 680 feet of new insulation around select chill water and other lines ranging from ½” – 4” in diameter in accordance with the publications listed in section 7 of this document. Insulation should be rated to minimize heat transfer over a 60? 5.2.3 Valves?
Approx 20 CHW alone temperature differential with no condensation on the piping or exterior / interior of the insulation material.that may need replacing 5.2.4 Treat approx. 770 square feet of interior compartment vertical bulkheads to prevent all sweating in accordance with the publications in section 7. Bulkheads separating compartments with large temperature differences will be prioritized. 5.2.5 Replace and properly insulate approx. 20 linear feet of ducting that has corroded due to condensation.
5.2 Detailed Tasks: 5.2.1 The contractor shall remove and dispose of existing insulation in select areas. 5.2.2 Install approx. 680 feet of new insulation around select chill water and other lines ranging from ½” – 4” in diameter in accordance with the publications listed in section 7 of this document. Insulation should be rated to minimize heat transfer over a 60? 5.2.3 Valves?
Approx 20 CHW alone temperature differential with no condensation on the piping or exterior / interior of the insulation material.that may need replacing 5.2.4 Treat approx. 770 square feet of interior compartment vertical bulkheads to prevent all sweating in accordance with the publications in section 7. Bulkheads separating compartments with large temperature differences will be prioritized. 5.2.5 Replace and properly insulate approx. 20 linear feet of ducting that has corroded due to condensation.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
Points of contact
- Malicia Smithmalicia.c.smith@uscg.mil7275021555
- JOSEPH RIZZARDIJOSEPH.A.RIZZARDI@USCG.MIL7275021555