Award notice, first published as solicitation
UT FLAP 73(2) La Sal Mountain Loop Road
6982AF23B000027
Federal Highway Administration, 6982AF Central Federal Lands Divisi. Highway, Street, and Bridge Construction.
Awarded
$20,631,490.73 obligated so far on USAspending
Get the next one like this from Federal Highway Administration by email, the day it is posted.Find my opportunities
This one was awarded in 2023
36 like it are open now in highway, street, and bridge construction
- UT NP ARCH 100(2) Bridges on Delicate Arch Road
Federal Highway Administration, 6982AF Central Federal Lands Divisi
SolicitationNAICS 237310Moab, UT6982AF27B000005Due in 7 daysDec 3 - AL-WHEELER NWR-WATERMAN GATE
Departmental Offices, FWS Contracting Activity
SolicitationNAICS 237310Ship to the buyer140FF027Q0077Due tomorrowNov 27 - W912EK27BA003 - Detroit Project Office Detroit, MI Wayne County Roads, Parking, and Grounds Renovation
Department of the Army, W07V Endist Rock Island
Presolicitation8(a)NAICS 237310MichiganW912EK27BA003Due in 4 daysNov 30
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Award notice. Who won, when, and for how much. Glossary
- How it ended
- Awarded to Kilgore Companies, LLC on February 6, 2024, 49 days after offers were due. The contracting office reported 5 offers (full and open competition).
Description
As published on SAM.gov with the solicitation of January 8, 2024.
PROJECT NUMBER: UT FLAP 73(2)
PROJECT NAME:
La Sal Mountain Loop Road PROJECT DESCRIPTION: The UT FLAP 73(2), La Sal Mountain Loop Road Project is located approximately 8 miles southeast of Moab, UT in Eastern Utah. The project crosses through Utah State School and Institutional Trust Lands (SITLA), Bureau of Land Management (BLM), private, and United States Forest Service (USFS) lands, providing access to the Manti – La Sal National Forest and Bureau of Land Management lands.
The route is categorized as a major rural collector in mountainous terrain and is maintained by San Juan County. This project rehabilitates and reconstructs the existing road with minor superelevation correction, profile adjustments, curve widening, ditch reconstruction, culvert replacements, asphalt surfacing, erosion control, signing, and pavement markings. The existing pavement is in poor condition with significant rutting, cracking, and potholing apparent along the route.
To complete the proposed widening and realignment, rock and soil cuts and fills are expected. Due to the mountainous terrain, significant boulders and areas with noted seepage or soft subgrade will be encountered. The project consists of two segments, broken into Schedule A and Option X. Segment 1 (Option X) – Segment 1 goes from the intersection of Old Airport Road 11+62 to 147+00 at the intersection of Pack Creek Cutoff.
Rehabilitation and widening consists of pulverizing the existing pavement, widening the road to 30 feet from the beginning to 45+00 and 26 feet for the remainder of the road, placing aggregate base and asphalt concrete pavement, and drainage improvements. Segment 2 (Schedule A) – Segment 2 goes from 147+00 at the intersection of Pack Creek Cutoff, and goes to 650+91, the boundary with the previous project UT PFH 46-1(2) and UT FLAP 73(1).
Rehabilitation consists of pulverizing the existing pavement, placing new aggregate base leveling, asphalt concrete pavement, and drainage improvements to narrow the roadway width to 26 feet. Five locations will be reconstructed requiring raising or lowering profile, placing aggregate base, asphalt concrete pavement, and drainage improvements to widen the roadway width to 26 feet.
PRINCIPAL WORK ITEMS (Schedule A):
20401-0000 Roadway Excavation:
75,000 CUYD 30101-0000 Aggregate Base:
55,000 TON 30401-5500 Full Depth Reclamation: 9.45 Miles 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch or 3/4-Inch Nominal Maximum Size Aggregate, 0.3 to <3 Million ESAL:
31,000 TON 60201-1000 Culverts:
4000 LNFT 63501-1000 Temporary Traffic Control:
LPSM PRINCIPAL WORK ITEMS (Option X):
20401-0000 Roadway Excavation:
16,000 CUYD 30101-0000 Aggregate Base:
25,000 TON 30401-5500 Full Depth Reclamation: 2.56 Miles 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch or 3/4-Inch Nominal Maximum Size Aggregate, 0.3 to <3 Million ESAL:
9,600 TON 63501-1000 Temporary Traffic Control:
LPSM ESTIMATED COST RANGE: Total estimated cost between $20,000,000 and $30,000,000 This is a full and open competition.
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Kilgore Companies, LLC
- UEI
- KN9MADJQ8H69
- CAGE
- 6DYA6
- Vendor location
- West Valley City, UT
- Contract
- 6982AF24C000009, definitive contract
- Obligated
- $20,631,490.73
- Actions
- 2 between February 6, 2024 and October 14, 2026
- Competition
- Full and Open Competition, 5 offers received
- Set-aside reported
- No Set Aside Used.
- Described as
- Ut Flap 73(2) La Sal Mountain Loop Road Roadway Rehabilitation and Reconstruction
- Match
- award number 6982AF24C000009 equals the contract number; same awarding office 6982AF (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
Points of contact
- Eric GrosskreuzCFLConracts@dot.gov
- Ryan PhillipsCFLContracts@dot.gov