Award notice, first published as solicitation
-Award Notice: Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
6973GH-25-R-00132
Federal Aviation Administration, 6973GH Franchise Acquisition SVCS. Commercial and Institutional Building Construction.
Awarded
Southwind Construction Services, LLC
$7,628,107.18 obligated so far on USAspending
Get the next one like this from Federal Aviation Administration by email, the day it is posted.Find my opportunities
This one was awarded in 2025
193 like it are open now in commercial and institutional building construction
- Child Development Center (CDC), Tinker Air Force Base, Oklahoma
Department of the Army, W076 Endist Tulsa
Due in 5 daysDec 1 - Thomas P. Stafford Building (TPS) Restroom Upgrades at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Federal Aviation Administration, 6973GH Franchise Acquisition SVCS
Sources soughtNAICS 236220OklahomaTPSBathroomUpgradesCloses in 8 daysDec 4 - McGee Creek Natural Scenic Recreation Area (NSRA) Improvements
Departmental Offices, Reclamation Contracting Activity
Sources soughtNAICS 236220Oklahoma140RR027R0020Closes in 8 daysDec 4
All 193 open in commercial and institutional building construction
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Award notice. Who won, when, and for how much. Glossary
- Time to respond
- Bidders had 68 days from the day the solicitation was posted, May 9, 2025, to the deadline. The deadline moved 7 times: it was first June 10, 2025 and ended as July 16, 2025.
- How it ended
- Awarded to Southwind Construction Services, LLC on September 15, 2025, 61 days after offers were due. The contracting office reported 6 offers (full and open competition).
Description
As published on SAM.gov with the solicitation of July 16, 2025.
The Federal Aviation Administration (FAA), Mike Monroney Aeronautical Center (MMAC) is seeking proposals from sources capable of completing CONSTRUCTION PROJECT: Hangar 9 Renovation at the Mike Monroney Aeronautical Center in accordance with the attached specifications and drawings
This procurement is Full and Open
The Estimate Price Range: $5,000,000 and $10,000,000
Please read the attached Solicitation in it's entirety and all other Attachments. Follow the instructions outlined in Sections L & M for submitting a responsive proposal. Please include the solicitation number 6973GH-25-R-00132 in the subject line of all email correspondence as indicated in Section L of the SIR
***ATTENTION: PLEASE SECTION L.1 OF THE SIR FOR THE MANDATORY SITE VISIT INSTRUCTIONS***
Prospective offerors are required to attend a MANDATORY pre-proposal conference/site visit to be held at 1:00 p.m. Central Time, Tuesday, May 20th, 2025 via site visit at the Mike Monroney Aeronautical Center. The conference will be held for the purpose of site investigation and permit general discussions regarding this Screening Information Request.
IMPORTANT NOTICE: Proposals from offerors who did not attend the pre-proposal conference WILL NOT be considered for award.
Offerors are allowed to send a maximum of THREE (3) individuals to represent their proposal (to include proposal teams, if applicable). Please advise the Contracting Officer, Andre Casiano, at andre.casiano@faa.gov in writing of your intent to attend by 2:00 p.m. Central Time, Monday, May 19th, 2025. Telephone requests will NOT count as notification of attendance. The Contracting Officer will send out information regarding visitor/vehicle passes and initial meetup location, no later than 4:00 p.m. Central Time, Monday, May 19th, 2025. Central Time to ONLY those that have provided the required response information. Your request should include the following information:
(1) Name of company represented
(2) Name and title of representative
(3) Phone number of representative
(4) Email address of representative
-------UPDATE May 16, 2025-----
Question and Answer Log #1 is hereby posted
See file: Q&A Log.1 25-R-00132 H9 Reno 5.16.25 H9 Reno 5.16.25
*Note: Paragraph formatting has been adjusted to enhance readability of this posting
-------UPDATE May 20, 2025-------
Please see file "Attendance List Hanger 9 May 20 Site Visit" for the list of May 20th, 2025 Site Visit attendees .
It is requested that all questions derived from the site visit be submitted by Thursday May 22nd, 2025, 4:00 p.m.
----------------------------------------------
-------UPDATE May 27, 2025-------
RFIs/Questions are currently being reviewed and any answers/clarifications will be posted as Q&A Logs
!!PLEASE NOTE: The FAA requested questions be submitted by May 22nd, 2025. This DOES NOT preclude offerors from asking further questions. The FAA is REQUESTING that any further questions be submitted as soon as possible
----------------------------------------------
-------UPDATE June 4, 2025-------
There will be a forthcoming Amendment to extend the proposal due date. The RFI/Questions that have been submitted are still being reviewed. Once answers have been formulated, the Question and Answer/RFI Log will be posted
----------------------------------------------
-------UPDATE June 9, 2025-------
Please see attachment 6973GH-25-R-00132 Amend0001
The proposal due date is hereby extended to June 18, 2025 at 4:30 p.m. Central Time.
The FAA is still formulating responses to the Questions/RFI posed in response to this project. I will post the Q&A Log as soon as it is available
----------------------------------------------
-------UPDATE June 13, 2025-------
The FAA anticipates posting responses to Questions/RFIs by Tuesday, June 17, 2025 along with an amendment to extend the proposal due date.
Additionally, there will be a forthcoming amendment to revise the specifications
----------------------------------------------
-------UPDATE June 17, 2025-------
The Proposal Due Date is hereby extended to June 24, 2025 at 4:30 p.m. Central, See Amendment 0002
A Q&A Log and revised specifications will be posted as soon as possible
----------------------------------------------
-------UPDATE June 23, 2025-------
The Proposal Due Date is hereby extended to July 1, 2025 at 4:30 p.m. Central, See Amendment 0003
The specification revisions and Q&A Log are still being processed, There is no current ETA on when an amendment with those attachments will be posted, but they will be posted as soon as possible.
----------------------------------------------
------UPDATE June 30, 2025-----
Amendment 0004 is hereby posted which extends the proposal due date and provides answers to some of the questions/RFIs submitted. Additionally this amendment incorporates packages for revised/added specifications and drawings.
The proposal due date is hereby extended to July 8, 2025 at 4:30 p.m. Central Time
Attachment 1(c) Revised & Additional Drawings Hangar 9 Renovation_6.17.2025 contains the following revised/added drawings:
Drawing G-004 - INDEX OF DRAWINGS Rev 1 dated 6.17.25
Drawing A-110a - LEVEL 1 - SLAB THICKNESS PLAN Rev 1 dated 6.17.25
Drawing A-301 - BUILDING SECTIONS Rev 1 dated 6.17.25
Drawing A-502 – DETAILS Rev 1 dated 6.17.25
Drawing I-111 - LEVEL 1 FINISH PLAN - SECTORS 1 & 2 Rev 1 dated 6.17.25
Drawing I-112 - LEVEL 1 FINISH PLAN - SECTORS 3 & 4 Rev 1 dated 6.17.25
Drawing I-121 - LEVEL 2 FINISH PLAN - SECTORS 1 & 2 Rev 1 dated 6.17.25
Drawing I-122 - LEVEL 2 FINISH PLAN -SECTORS 3 & 4 Rev 1 dated 6.17.25
Drawing I-131 - LEVEL 3 FINISH PLAN - SECTORS 1 & 2 Rev 1 dated 6.17.25
Drawing I-132 - LEVEL 3 FINISH PLAN - SECTORS 3 & 4 Rev 1 dated 6.17.25
Drawing IN603 - MATERIALS & FINISH LEGEND Rev 1 dated 6.17.25
Drawing FA001 - FIRE ALARM LEGEND AND GENERAL NOTES Rev 1 dated 6.17.25
Drawing FA111 - FIRE ALARM PLAN LEVEL 1 - SECTORS 1 & 2 Rev 1 dated 6.17.25
Drawing M-111 - LEVEL 1 - MECHANICAL PLAN - SECTORS 1 AND 2 Rev 1 dated 6.17.25
Drawing M-112 - LEVEL 1 - MECHANICAL PLAN - SECTORS 3 AND 4 Rev 1 dated 6.17.25
Drawing M-121 - LEVEL 2 - MECHANICAL PLAN - SECTORS 1 AND 2 Rev 1 dated 6.17.25
Drawing M-122 - LEVEL 2 - MECHANICAL PLAN - SECTORS 3 AND 4 Rev 1 dated 6.17.25
Drawing M-131 - LEVEL 3 - MECHANICAL PLAN - SECTORS 1 AND 2 Rev 1 dated 6.17.25
Drawing M-132 - LEVEL 3 - MECHANICAL PLAN - SECTORS 3 AND 4 Rev 1 dated 6.17.25
Attachment 1(d) Amended Specifications_Am01_6.17.25 contains the following revised/added specification sections
Specification 064116 - PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS_Am01
Specification 102113.17 - PHENOLIC-CORE TOILET COMPARTMENTS_Am01
Specification 102600 - WALL AND DOOR PROTECTION_Am01
Specification 260010 - SUPPLEMENTAL REQUIREMENTS FOR ELECTRICAL_100_Am01
Specification 260800 FL - COMMISSIONING OF ELECTRICAL SYSTEMS_Am01
This amendment also provides Attachment 12 Furniture Equipment Moving Diagram Hangar 9 6.17.25 which is a diagram of the furniture and equipment in the building
Finally Q&A Log #2 is posted as QA Log.2 25-R-00132 H9 Reno 6.30.25
The construction completion period is changed to 584 days after receiving the Notice to Proceed
Please note the Q&A Log has a partial answer list, there will be another amendment to complete the Q&A Log and incoporate the final round of revised drawings/specs.
-----UPDATE July 3, 2025-----
Amendment 0005 is hereby posted which extends the proposal due date until July 16, 2025 at 4:30 p.m. Central Time
An amendment is currently being finalized to incorporate the final revised drawings and specifications, to include a Q&A Log for the remaining unanswered questions and will be posted July 7, 2025.
-----UPDATE July 7, 2025-----
Amendment 0006 is hereby posted.
This amendment adds the final drawing/specification revisions/updates in Attachment 1e Revised.Additional Drawings Hangar 9 Renovation_6.26.2025 and Attachment 1f Amended Specifications_Am02_6.26.25. This amendment includes 44 revised/updated drawings and 14 revised/updated specifications.
This amendment also includes badge/escort/ramp permit requirement details under Section H of the SIR.
The final Q&A log with answers is also posted as Q&A Log - Answers - 25-R-00132 H9 Reno 7.7.25 Final
Reminder: Acknowledge all amendments in your proposal submission as identified in "Block 19. Acknowledgement of Amendments" located on Page 2 of the SIR
-----UPDATE July 15, 2025-----
The following Question was posed regarding references to Hangar 8 and floor finishing
"Are you expecting the high bay area to get a new floor coating?
Also, The revised SOW says to paint and restripe Hangar 8 in am02
Do you have drawings for that? Are we to include Hangar 8 at all for this project? Should this say hangar 9?"
Please see attached Amendment which states:
The purpose of this amendment is to identify an error in the Specifications regarding Hangar 8
FIRST: "Repaint and restripe the Hangar 8 High Bay floors to match existing." identified at SECTION 010100 - SUMMARY OF WORK in "Attachment 1f Amended Specifications_Am02_6.26.25" was included in error. This work is not within the scope of renovating Hangar 9. The "Repaint and restripe the Hangar 8 High Bay floors to match existing." work is hereby removed
Contractors shall refer to Drawing IN601 which identifies no finish work on the high bay floor
---------
----July 16, 2025, @ 8:50 a.m. Central Time---
The following RFI has been received regarding "Bid Option #1" for sprinklers that was referenced on the initial drawings posted with the SIR.
Question: "We are having difficulties locating the updated bid schedule containing Option 1. You referenced in the Q&A (Question 108) that Amendment 0006 would contain new documents, but I was not able to locate the bid schedule there. Can you advise if we are just missing that or if it needs to be issued?"
Answer: The sprinklers are to be included in the full scope of work as identified in the revised drawings that were posted with Amendment 0004 and Amendment 0006 which removed references to "Bid Option". Offerors are to include the sprinklers in price proposal for the project.
----July 16, 2025, @ 2:45 a.m. Central Time---
Please see attached amendment 0008 which corrects the proposal submission email address to andre.casiano@faa.gov. All proposal submissions must be email to andre.casiano@faa.gov
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- Attachment 11 Chapter 33 Construction Safety.pdf71 KB, May 9, 2025
- Attachment 10 AMP400-ENV-OC-2.4.3-CC.pdf303 KB, May 9, 2025
- Attachment 9 Contractor Release.pdf963 KB, May 9, 2025
- Attachment 8 Client Authorization Letter.docx17 KB, May 9, 2025
- Attachment 7 Past Performance Experience Form.docx18 KB, May 9, 2025
- Attachment 6 Past Performance Survey 4.23.25.docx30 KB, May 9, 2025
- Attachment 5 SF24 Bid Bond.pdf724 KB, May 9, 2025
- Attachment 4 SF25A Payment Bond.pdf733 KB, May 9, 2025
- Attachment 3 SF25 Performance Bond.pdf743 KB, May 9, 2025
- Attachment 2 Wage Determination OK20250049 03.14.2025.pdf465 KB, May 9, 2025
- Attachment 1b Hangar_9_High_Bay_Lights_100_Drawings.3.14.2025.pdf6.5 MB, May 9, 2025
- Attachment 1a Hangar 9_Renovation_100_Drawings_3.14.2025.pdf32.2 MB, May 9, 2025
- Attachment 1 Hangar 09_Combined Specs_3.14.2025.pdf6.5 MB, May 9, 2025
- 6973GH-25-R-00132.pdf513 KB, May 9, 2025
- QA Log.1 25-R-00132 H9 Reno 5.16.25.pdf61 KB, May 16, 2025
- Attendance List Hanger 9 May 20 Site Visit.pdf66 KB, May 20, 2025
- 6973GH-25-R-00132 Amend0001.pdf149 KB, June 9, 2025
- 6973GH-25-R-00132 Amend0002.pdf115 KB, June 17, 2025
- 6973GH-25-R-00132 Amend0003.pdf135 KB, June 23, 2025
- QA Log.2 25-R-00132 H9 Reno 6.30.25.pdf241 KB, June 30, 2025
- Attachment 12 Furniture Equipment Moving Diagram Hangar 9 6.17.25.pdf1.2 MB, June 30, 2025
- Attachment 1d Amended Specifications_Am01_6.17.25.pdf508 KB, June 30, 2025
- Attachment 1c Revised.Additional Drawings Hangar 9 Renovation_6.17.2025.pdf5.9 MB, June 30, 2025
- 6973GH-25-R-00132 Amend0004.pdf247 KB, June 30, 2025
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Southwind Construction Services, LLC
- UEI
- K9REEC338KM7
- CAGE
- 54FQ8
- Vendor location
- Edmond, OK
- Contract
- 6973GH25C00197, definitive contract
- Obligated
- $7,628,107.18
- Actions
- 15 between September 15, 2025 and November 12, 2026
- Competition
- Full and Open Competition, 6 offers received
- Set-aside reported
- No Set Aside Used.
- Described as
- WO#21-019348 Hangar 9 Renovation
- Match
- award number 6973GH25C00197 equals the contract number; same awarding office 6973GH (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
May 9, 2025
Solicitation, originally sources sought
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due June 10, 2025 at 5:30 PM EDT. SAM.gov, notice 2408b626a204488c8d79f964ab797efe
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
May 16, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due June 10, 2025 at 5:30 PM EDT. SAM.gov, notice 3a7c831b87ec41a29fa0295e57a1aee2
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
May 20, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due June 10, 2025 at 5:30 PM EDT. SAM.gov, notice 5e953d40602c44c787bb2d91bf09f58d
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
May 27, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due June 10, 2025 at 5:30 PM EDT. SAM.gov, notice 784ab06c6baa4ae7b01e329dcc5dbea0
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
June 4, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due June 10, 2025 at 5:30 PM EDT. SAM.gov, notice 1b67849ca76847638892dac46914657d
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
June 9, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due June 18, 2025 at 5:30 PM EDT. SAM.gov, notice bdf49391757147699624586fcc084747
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
June 13, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due June 18, 2025 at 5:30 PM EDT. SAM.gov, notice a6f47246c8a040789294f5c706320f2a
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
June 17, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due June 24, 2025 at 5:30 PM EDT. SAM.gov, notice 7f2d57597e0a495a88609afe04f8685a
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
June 23, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due July 1, 2025 at 5:30 PM EDT. SAM.gov, notice 21fb11daa605428c9567e0877aee6b84
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
June 30, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due July 8, 2025 at 5:30 PM EDT. SAM.gov, notice 1db46b142c214a4297b54a0a9f12f5fd
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
July 3, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due July 16, 2025 at 5:30 PM EDT. SAM.gov, notice 9a64eb87021047cca0816284000653fe
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
July 7, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due July 16, 2025 at 5:30 PM EDT. SAM.gov, notice 778ae1a1596240178d64e339e470abb7
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
July 15, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due July 16, 2025 at 5:30 PM EDT. SAM.gov, notice ed423239dd544e9d91b9434ff3bbe04e
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
July 16, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due July 16, 2025 at 5:30 PM EDT. SAM.gov, notice 0b83b3436d244005843accc5d8167404
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
July 16, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due July 17, 2025 at 5:30 PM EDT. SAM.gov, notice 694a60020aad4bc1a721e538b9ffa284
18 revisions on SAM
- September 15, 2025: publish, award notice
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
July 16, 2025
Solicitation
Solicitation - Hanger 9 Renovation at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK
Due July 16, 2025 at 5:30 PM EDT. SAM.gov, notice e950b38528674ee0aaf7ebf7d004a286
17 revisions on SAM
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 16, 2025: publish, solicitation
- July 15, 2025: publish, solicitation
- July 7, 2025: publish, solicitation
- July 3, 2025: publish, solicitation
- June 30, 2025: publish, solicitation
- June 23, 2025: publish, solicitation
- June 17, 2025: publish, solicitation
- June 13, 2025: publish, solicitation
- June 9, 2025: publish, solicitation
- June 4, 2025: publish, solicitation
- May 27, 2025: publish, solicitation
- May 20, 2025: publish, solicitation
- May 16, 2025: publish, solicitation
- May 9, 2025: publish, solicitation
- September 19, 2024: publish, sources sought
September 15, 2025
Award notice, originally solicitation
Awarded to Southwind Construction Services, LLC for $6,717,847. SAM.gov, notice 18e96cb8da184ddb983bdf3007db83ff
2 revisions on SAM
- September 15, 2025: publish, award notice
- July 16, 2025: publish, solicitation
Points of contact
- Andre Casianoandre.casiano@faa.gov4059547850