- Solicitation number: 6913G626Q300035
- Notice type: Combined synopsis and solicitation
- Status: Awarded to A-Zone Environmental Services, LLC
- Department: Department of Transportation
- Agency: Office of the Secretary
- Contracting office: 6913G6 Volpe Natl. Trans. Sys CNTR (6913G6)
- NAICS: 238910 Site Preparation Contractors
- Product or service code: F999 Other Environmental Services, Studies, and Analytical Support
- Set-aside: Total small business set-aside
- Small business size standard: $19 million in average annual receipts (13 CFR 121.201, NAICS 238910)
- Place of performance: Chantilly, Virginia
- County: Fairfax County (FIPS 51059). https://sealedbidder.com/counties/fairfax-county-va-51059
- City: Chantilly. https://sealedbidder.com/cities/chantilly-va-5114744
- First posted: June 15, 2026
- Last posted: June 23, 2026
- SAM.gov: https://sam.gov/workspace/contract/opp/69d122b086664e2bbe71a5f9a6e6a6d4/view

## Reading this notice

- Kind of notice: Combined synopsis and solicitation. A streamlined commercial-item buy where the notice itself is the solicitation.
- Who may compete: Total small business set-aside. Only small businesses may compete. Small, under NAICS 238910 (site preparation contractors), means no more than $19 million in average annual receipts, counted with affiliates.
- Time to respond: Bidders had 10 days from the day the solicitation was posted, June 15, 2026, to the deadline. The deadline moved once: it was first June 24, 2026 and ended as June 25, 2026.
- How it ended: Awarded to A-Zone Environmental Services, LLC on July 9, 2026, 14 days after offers were due. The contracting office reported 9 offers (full and open competition after exclusion of sources).

## Description

Under an Interagency Agreement, the U.S. Department of Transportation John A. Volpe National Transportation Systems Center (Volpe Center) is providing support to the Federal Aviation Administration (FAA) Facilities Environmental Cleanup (ECU) Program. As part of this effort, a Remedial Action (RA) will be conducted at three facilities in the FAA Eastern Service Area (ESA) to remove identified soil contamination. The sites requiring remediation for lead- and total petroleum hydrocarbon (TPH) -contaminated soils are listed below:

	BHM ASR &ndash; Birmingham, AL (33.57378&deg;, -86.75671&deg;)

	CXY LOM &ndash; New Cumberland, PA (40.178196&deg;, -77.005692&deg;)

	IADN NASEB &ndash; Chantilly, VA (38.958736&deg;, -77.43499&deg;)

The FAA's ECU Program has identified the potential for environmental and human health risks and/or liability associated with the facilities above based on prior research, known historic operations and practices, and required cleanup actions or previously identified sites.The Contractor shall conduct all work in accordance with Federal, State and local requirements.  Where inconsistencies exist, the Contractor shall follow the most stringent requirement. The Contractor shall submit a draft Remediation and Restoration work plan (Work Plan) (where applicable) within ten (10) business days of the project kick-off meeting that addresses the project requirements below.

This task involves the preparation and submission of a draft and final Work Plan. The Work Plan shall detail the technical approach and schedule for conducting all contaminated soil remediation, disposal, and site restoration activities described below. To assist with preparation of the Work Plan, the contractor shall thoroughly review the Government-furnished information (GFI) for pertinent information. Please note that the GFI Site Survey Report provided for the CXY site is for demolition activities. This document is provided because it contains soil sampling results for this site. There will be NO demolition or asbestos abatement required as part of this project. The removal quantities and depths in the Preliminary Assessment and/or Site Investigation and Site Survey reports (if provided) are to be used as a guide along with the estimated total quantities listed in this SOW Section 2.2.2.

The Work Plan shall describe methods and procedures for performing soil remediation, disposal, and restoration. Disposal methods must be detailed by the contractor for all sites including the identification of all disposal facilities where waste and debris is to be shipped. Disposal sampling and paperwork is the responsibility of the contractor. The government will perform ALL confirmatory sampling required at the sites. Additionally, the work plan shall also identify any required permits needed to perform the work.

Additional components required with the Work Plan are the Site Safety and Health Plan (SSHP), which shall include personnel health and safety precautions to be followed. The work plan shall also include a brief Risk Management Plan that identifies major risks and hazards on each site and discusses ways to minimize these risks.

An outline summarizing the required content of the work plan is shown below:

	Technical Approach

		Method and procedures for soil remediation, removal, disposal (all as required above in section 1.1), and restoration

		Identification of required work permits

	Site Safety Health Plan (SSHP)

	Risk Management Plan

		Identification of major risks

		Risk mitigation plan

The contractor should expect a 5-business day Volpe Center review period between submission of the Draft Work Plan and receipt of Volpe Center comments. The Volpe Center and the Contractor shall meet to discuss any comments and changes, if necessary. The contractor shall make the changes and submit a Final Work Plan within 5 business days of the receipt of comments.

Preliminary Assessment/Site Investigation (PA/SI), Site Investigation (SI) and Site Survey activities completed in 2024 found the below sites showing contamination above either FAA action levels or EPA/State regulatory limits. Examples include lead-in-soil concentrations above the FAA&rsquo;s cleanup standard of 200 mg/kg (ppm) or the applicable state standard, or TPHs in soil above EPA or State regulatory limits. For each site, prior to mobilizing to the site for the remedial activities, waste characterization samples shall be collected. Once these samples are analyzed, the proper landfill and disposal approvals shall be obtained. For each site, contaminated soil and/or equipment shall not be left at the site overnight unless previous permission is obtained by the contractor. Any equipment or material left at the site must be secured by the contractor and is not the responsibility of the government.

Adidtional details for requirement are found in the SOW.

## Attachments

- [Attachment XI Pricing.pdf](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/70333fd430d24919abd7047ed75bf725/download)

## Award on USAspending

- Recipient: A-Zone Environmental Services, LLC (UEI EDM5CVGEWMJ4)
- Contract: 6913G626P800037, purchase order
- Obligated: $75,087.00
- Competition: Full and Open Competition After Exclusion of Sources, 9 offers received
- Link: solicitation number 6913G626Q300035 equals the FPDS solicitation identifier; same awarding office 6913G6 (high confidence)
- Record: https://www.usaspending.gov/award/CONT_AWD_6913G626P800037_6901_-NONE-_-NONE-/


## Open now in the same industry

6 open in NAICS 238910.

- Camptonville Housing Decommissioning (127EAX26Q0076), due December 4, 2026 at 8:00 PM EST. https://sealedbidder.com/opportunities/127eax26q0076
- Forest Wide Decommissioning Project (127EAX27Q0013), due December 7, 2026 at 2:00 PM EST. https://sealedbidder.com/opportunities/127eax27q0013
- UTILITY EXCAVATION AND REPAIR SERVICES IDIQ (385439GMK), due December 7, 2026 at 4:00 PM EST. https://sealedbidder.com/opportunities/385439gmk

## Publications

- June 15, 2026: Combined synopsis and solicitation, due June 24, 2026 at 2:00 PM EDT. Notice fa1b4835174c4ab7a49614a6294afa6f. https://sam.gov/workspace/contract/opp/fa1b4835174c4ab7a49614a6294afa6f/view
- June 23, 2026: Combined synopsis and solicitation, due June 25, 2026 at 3:00 PM EDT. Notice 69d122b086664e2bbe71a5f9a6e6a6d4. https://sam.gov/workspace/contract/opp/69d122b086664e2bbe71a5f9a6e6a6d4/view