# Replace iDXA C211 539-26-505

Canonical: https://sealedbidder.com/opportunities/36c25026q0375

- Solicitation number: 36C25026Q0375
- Notice type: Solicitation (first published as presolicitation)
- Status: Awarded to Calvary Contracting Inc.
- Department: Department of Veterans Affairs
- Contracting office: 250-Network Contract Office 10 (36C250)
- NAICS: 236220 Commercial and Institutional Building Construction
- Product or service code: Z2DA Repair Or Alteration Of Hospitals And Infirmaries
- Set-aside: Service-disabled veteran-owned small business set-aside
- Small business size standard: $45 million in average annual receipts (13 CFR 121.201, NAICS 236220)
- County: Hamilton County (FIPS 39061). https://sealedbidder.com/counties/hamilton-county-oh-39061
- City: Cincinnati. https://sealedbidder.com/cities/cincinnati-oh-3915000
- First posted: March 12, 2026
- Last posted: April 20, 2026
- SAM.gov: https://sam.gov/workspace/contract/opp/fa3ec2698606494a9a5a3c0533536f29/view

## Reading this notice

- Kind of notice: Solicitation. A formal request for proposals, quotes or bids. Offers are due by the response deadline.
- Who may compete: Service-disabled veteran-owned small business set-aside. Reserved for service-disabled veteran-owned small businesses. Small, under NAICS 236220 (commercial and institutional building construction), means no more than $45 million in average annual receipts, counted with affiliates.
- Time to respond: Bidders had 32 days from the day the solicitation was posted, March 27, 2026, to the deadline.
- Before the solicitation: The agency published a presolicitation on March 12, 2026, 15 days before the solicitation.
- How it ended: Awarded to Calvary Contracting Inc. on May 14, 2026, 16 days after offers were due. The contracting office reported 2 offers (full and open competition after exclusion of sources).

## Description

REPLACE iDXA C211
FOR THE
VETERANS AFFAIRS MEDICAL CENTER (VAMC) CINCINNATI, OH
PROJECT NUMBER: 539-26-505
QUESTIONS AND ANSWERS (RFIs)
TO REQUEST FOR QUOTE (RFQ) NUMBER
36C25026Q0375

QUESTIONS AND ANSWERS

RFI #1 Question: Given the size of the project, is a dedicated SSHO and the CQ education requirements required?  Typically, the Superintendent can be the SSHO and CQC on this size of project, and a superintendent is not going to be a graduate engineer.

1.9 A - 01 35
The Prime Contractor shall provide a minimum of one  Full-Time  SSHO at each project site, for each shift (with no other duties) that holds as current, a professional safety certification with at least 3 years of dedicated
      construction safety related experience.
3.4 B   01 45
The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of PM or SRE to determine qualifications based on project complexity at construction review 5 years construction.
Answer: The superintendent may serve as the SSHO and CQC System Manager. A graduate degree is not required. SSHO must be 30 hours of OSHA training (see spec 01 35 26 parts 1.5F).
RFI #2 Question: The solicitation and drawings reference Room C211, while portions of the specifications reference C214. Could you please confirm the correct room designation and whether all documents apply to C211?

Answer: The majority of contract documents, including the Statement of Work and full drawing set, identify Room C211 as the correct project location. The specifications, however, contain an incorrect header reference to C214. This appears to be an error in the header only; the specifications do not assign any scope to C214.

RFI #3 Question: The SOW indicates that hazardous material testing and abatement will be performed  if required.
Has a hazardous materials survey already been completed?
Should bidders include abatement costs in the base bid, or will this be handled separately by the owner?

Answer:  The Statement of Work requires the contractor to perform hazardous materials testing and abatement  if required.  No hazardous materials survey is included in the solicitation, and bidders are not directed to include abatement in the base bid. Contractors should therefore include testing only in their proposals. If hazardous materials are identified during construction, the VA will address any required abatement separately at that time.

RFI #4 Question: The drawings don t describe anything about the fume hood for disconnecting.  There is power and some other type of gas or air ports and controls on the hood.  We need to know how the hood is connected and what is connected to it.  Is there piping or conduit behind the hood to be capped and or removed.  Is there a drawing of the hood to reference connections?

Answer: There are no existing as-built or construction drawings for this fume hood, and its installation date and project of origin are unknown.
The fume hood has electrical power and medical gas connections. These utilities must be disconnected and capped.

RFI #5 Question: Is there a fan on the roof?  If so, does that need to be removed along with any duct in the walls?

Answer: There is no roof-mounted fan associated with this fume hood. The hood is not currently connected to any exhaust fan and does not have ductwork running to the roof or through the walls that would require removal therefore no fan removal is required.

See picture below of disconnected unit.

## Attachments

- [36C25026Q0375.docx](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/d6865c59314e4dcaade0008729b537c2/download)
- [36C25026Q0375_1.docx](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/75f9d02e07a948a0aa1cb8e5f82ecb3b/download)

## Award on USAspending

- Recipient: Calvary Contracting Inc. (UEI JN57WU75KM29)
- Contract: 36C25026P0659, purchase order
- Obligated: $88,963.00
- Competition: Full and Open Competition After Exclusion of Sources, 2 offers received
- Link: solicitation number 36C25026Q0375 equals the FPDS solicitation identifier; same awarding office 36C250 (high confidence)
- Record: https://www.usaspending.gov/award/CONT_AWD_36C25026P0659_3600_-NONE-_-NONE-/


## Open now in the same industry

193 open in NAICS 236220.

- AFRL RISE 2808a AOI: Facility Alteration & Space Optimization – Bombers Directorate Hallway Project (Bldg 556) (FA2396-27-9CTBD), due December 4, 2026 at 11:59 PM EST. https://sealedbidder.com/opportunities/fa2396279ctbd
- B422 BREAKROOM, B300 BDOC (W50S8R27BA002), due December 10, 2026 at 1:00 PM EST. https://sealedbidder.com/opportunities/w50s8r27ba002
- United States Space Force Integration Facility (W912QR279A005), due December 24, 2026 at 1:00 AM EST. https://sealedbidder.com/opportunities/w912qr279a005

## Publications

- March 12, 2026: Presolicitation, due April 28, 2026 at 1:00 PM EDT. Notice 96808bd78a2b48a39f8cd275b3e99b01. https://sam.gov/workspace/contract/opp/96808bd78a2b48a39f8cd275b3e99b01/view
- March 27, 2026: Solicitation, due April 28, 2026 at 1:00 PM EDT. Notice e115266b892d4a42ab37c005243638d6. https://sam.gov/workspace/contract/opp/e115266b892d4a42ab37c005243638d6/view
- April 20, 2026: Solicitation, due April 28, 2026 at 1:00 PM EDT. Notice fa3ec2698606494a9a5a3c0533536f29. https://sam.gov/workspace/contract/opp/fa3ec2698606494a9a5a3c0533536f29/view