Combined synopsis and solicitation, total small business set-aside
Copy of AT RISK | Water System Testing and Maintenance | Water Management Program Services | (VA-24-00094196)
36C24424Q1010
Department of Veterans Affairs, 244-Network Contract Office 4. Testing Laboratories and Services.
Response deadline
September 16, 2024 at 10:00 AM EDT
Closed 800 days ago. Posted September 12, 2024, first published September 10, 2024. Scheduled to archive November 15, 2024.
Get the next one like this from Department of Veterans Affairs by email, the day it is posted.Find my opportunities
This one closed in 2024
34 like it are open now in testing laboratories and services
- Storage and monitoring of ManNac for FDA regulations
National Institutes of Health, National Institutes of Health Olao
PresolicitationNAICS 541380Ship to Bethesda, MD75N98027Q00086Due tomorrowNov 26 - APT Generator Switchgear Testing – Alvin C. York VA Medical Center
Department of Veterans Affairs, 249-Network Contract Office 9
Sources soughtNAICS 541380Murfreesboro, TN36C249-27-AP-1027Due tomorrowNov 26 - FY27 AASHTO ACCREDITATION AND INSPECTION SERVICES
Federal Highway Administration, 693C73 Eastern Fed Lands Division
Combined synopsis and solicitationNAICS 541380Sevierville, TN693C7327Q000004Due in 2 daysNov 27
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Combined synopsis and solicitation. A streamlined commercial-item buy where the notice itself is the solicitation. Glossary
- Who may compete
- Total small business set-aside. Only small businesses may compete. Small, under NAICS 541380 (testing laboratories and services), means no more than $19 million in average annual receipts, counted with affiliates. Open Small business opportunities
- Time to respond
- Bidders had 6 days from the day the solicitation was posted, September 10, 2024, to the deadline.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
Question and Answer Are you looking for the contractor to conduct regular (daily, monthly, quarterly, etc.) sampling as part of this solicitation, or to oversee the collection of these samples by facility personnel? No sampling is required. However observation of collection would be included in survey of of the SPS water system as referenced in 2.1 in the SOW.
The contractor will provide a database for the facility to log and track testing results as referenced in 3.19.5 Following the initial survey, should existing equipment be found in need of repair or replacement to comply with AAMI ST108 standards, will this work fall under this contract? No, when issues with equipment or parts of the water system are identified it will be the responsibility of the facility to fix or address these issues.
AAMI (Association for the Advancement of Medical Instrumentation) recently published a new standard that establishes the quality of water used to process reusable medical devices. Is one output of the Comprehensive Water Management Program to provide direction on the requirements for water quality necessary to effectively process medical devices intended for patient use?
Yes, please refer to 3.6 of the SOW Are there any VA-specific guidelines or preferences for determining control limits, or should we rely solely on industry standards like AAMI ST108:2023? AAMI ST108:2023 are the guidelines for the determining control limits. Is the VA Pittsburgh Healthcare System (VAPHS) currently experiencing consequences of using water that is of inadequate quality during the cleaning and sterilization of medical devices?
No, SPS has a contingency in place if water quality is inadequate by AAMI-ST108 guidelines. Can we successfully propose services in addition to the NAISC code specified - 541380 - Testing Laboratories and Services? Â Â This is the NAICS Code that will be applied to this RFQ, no other is necessary. Can the VA provide more details on the expected composition of the Water Management Team (WMT)? Are there specific roles or departments that must be represented/interviewed?
The contractor will provide a recommendation for the composition of the Water Management Team and suggest role to be filled by those suggested parties, refer to SOW section 3.1. The contractor should have experience with this type of work and the requirement for a facility Water Management Team. The facility will review the contractors suggestions for WMT involvement and roles and decide if those roles and actions are appropriate for our facility.
Concerning the technical capability requirements in the proposal instructions, can the VA clarify if certifications or specific qualifications are required for the "certified analyst" mentioned? What other certifications will be required from the contractor personnel? Certified Water Technologist (CWT) In section 3.18, the SOW mentions a 90-day work plan development, and 1 year program facilitation timeline.
Can the VA provide more details on the expected activities, milestones and deliverables within these timeframes? This timeline will be created by the contractor based off the deliverables listed in 3.0 in the SOW. The contractor will utilize the deliverables and plan a 90 implantation to present to the SPS Chief. This WMP include  implementation on continued support for the remainder of the contract year, refer to SOW section 3.19 for continued support references.