Solicitation
Trenching, Conduit and Ground-well Installation
19JM3727Q0002
Department of State, U.S. Embassy Kingston. Site Preparation Contractors.
Response deadline
November 25, 2026 at 2:00 PM EST
Closed today. Posted October 28, 2026. Scheduled to archive December 10, 2026.
Get the next one like this from Department of State by email, the day it is posted.Find my opportunities
This one closed today
6 like it are open now in site preparation contractors
- Camptonville Housing Decommissioning
Forest Service, USDA Forest Serivce
Combined synopsis and solicitationSmall businessNAICS 238910Nevada City, CA127EAX26Q0076Closes in 10 daysDec 5 - Forest Wide Decommissioning Project
Forest Service, Usda-Fs, Csa Southwest 7
Combined synopsis and solicitationSmall businessNAICS 238910Arizona127EAX27Q0013Closes in 12 daysDec 7 - UTILITY EXCAVATION AND REPAIR SERVICES IDIQ
Department of Energy, Fermilab - DOE Contractor
SolicitationSmall businessNAICS 238910Batavia, IL385439GMKCloses in 12 daysDec 7
Reading this notice
Worked out from the publications and the award on this page.
- Kind of notice
- Solicitation. A formal request for proposals, quotes or bids. Offers are due by the response deadline. Glossary
- Who may compete
- SAM.gov lists no set-aside on this notice, so it is not reserved for small businesses. Small, under NAICS 238910 (site preparation contractors), means no more than $19 million in average annual receipts, counted with affiliates. What a set-aside is
- Time to respond
- Bidders had 28 days from the day the solicitation was posted, October 28, 2026, to the deadline.
Size standard from 13 CFR 121.201. The solicitation itself is what binds: check the code and standard it states.
Description
As published on SAM.gov.
Description
The United Stated Embassy in Kingston is requesting proposals for Trenching, Conduit And Ground-Well Installation in various locations on the Embassy compound. The contractor will provide all labor, equipment, supervision, material specific to the back filling and compaction and management needed to complete the job
Infrastructure Support System - Handhole / Underground Conduit System
Trenching
- Nine locations have been identified requiring trench work.
- Thirteen locations have been identified requiring trench work.
- Before excavation, the Contractor shall locate and verify all existing utilities in the proposed trench alignment.
- If excavation interferes with existing drains, piping, or structures, the Contractor shall immediately notify, in writing, the COR and provide temporary protection for these systems before proceeding.
Trenching from Handholes
- The Contractor shall make wall penetrations into existing manholes/handholes as required for the number and size of conduits entering and exiting each structure, in accordance with the drawings.
Conduit
- Existing conduit shall remain in place unless the drawings specifically direct removal or modification.
- Under grass, soil, the Contractor shall install Schedule 80 PVC conduit with a minimum cover of 24 inches (610 mm) from finished grade to top of conduit, or as indicated on the drawings, whichever is greater.
- All underground 90 degree bends with a 12inch (305 mm) radius shall use prefabricated sweeping bends.
- Above grade, all underground PVC conduit shall transition to rigid galvanized steel (RGS) using PVC to RGS couplers.
- The Contractor shall install pull lines in all new conduit runs.
Soil and Backfill Materials
Soil Materials
The Contractor shall provide all labor and materials for soil and backfill, where required.
- Select Backfill: ASTM D 2487 soil classification groups SW, SP, and SM, or combinations thereof; free of rock or gravel larger than 3 inches (75 mm), debris, waste, frozen materials, vegetation, and other deleterious matter.
- Asphalt/Concrete Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 95% passing a 11/2inch (40 mm) sieve and not more than 8% passing a 1/4inch (6.4 mm) sieve.
- Base Gravel: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; 100% passing a 1inch (25 mm) sieve and not more than 8% passing a 1/4inch (6.4 mm) sieve.
- Sand Cushion: ASTM C 33 fine aggregate, natural or manufactured sand.
Placement and Compaction
- Place backfill and fill in layers not exceeding:
- 8 inches (203 mm) loose thickness for heavy compaction equipment;
- 4 inches (102 mm) loose thickness when compacted by hand-operated tampers.
- Place backfill and fill evenly to the required elevations, uniformly along their full length.
- Compact soil materials to not less than the following percentages of maximum dry unit weight per ASTM D 1557:
- Under lawns or unpaved areas: scarify and re-compact top 6 inches (152 mm) below subgrade and compact each layer to 85%.
- Utility trenches: compact each layer of initial and final backfill to 85%.
Anticipated Period of Performance: a base period of twenty-one (21) days after contract award
Eligibility and Registration
Offerors must hold an active registration in the System for Award Management (SAM.gov) when they submit a proposal and at award.
Local Insurance and Defense Based Act (DBA) Insurance.
A site visit has been scheduled for Friday, November 06, 2026 at 10 a.m.
Offeror interested in attending must email kingstonquotes@state.gov with the caption ‘TRENCHING - SITE VISIT’. To ensure access you are required to be approved prior to the visit. You are to provide the full names of the attendees, the vehicle information to include make, model, color and plate number of the vehicle being driven. The email must be sent no later than Wednesday, November 04, 2026 by 2 pm.
Completed proposal are to be email to kingstonquotes@state.gov in PDF format by the deadline stipulated.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- 19JM3727Q0002_Trenching and Conduit Installation .pdf1.7 MB, October 28, 2026
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
October 28, 2026
Solicitation
Due November 25, 2026 at 2:00 PM EST. SAM.gov, notice 79b69696ceed4090b5e4db5a94cb31be
1 revision on SAM
- October 28, 2026: publish, solicitation
Points of contact
- U.S. Embassy Kingston Procurement Officekingstonquotes@state.gov8767026000
- Handel BlakeBlakeHA@state.gov8767026393