# FCC Lompoc B&F Project 25Z6AXX Emergency Fire Escape Doors

Canonical: https://sealedbidder.com/opportunities/15b61727q00000002

- Solicitation number: 15B61727Q00000002
- Notice type: Combined synopsis and solicitation
- Status: Closed. Deadline was November 16, 2026 at 4:00 PM EST
- Department: Department of Justice
- Agency: Federal Prison System / Bureau of Prisons
- Contracting office: FCC Lompoc (15B617)
- NAICS: 332321 Metal Window and Door Manufacturing
- Product or service code: 1290 Miscellaneous Fire Control Equipment
- Set-aside: Total small business set-aside
- Small business size standard: 750 employees (13 CFR 121.201, NAICS 332321)
- Place of performance: California
- Who can bid, by location: Anywhere in the US. Location does not limit who can bid: a product shipped to the buyer, research at the performer's facility, or work at the contractor's site. A state shown is the delivery point.
- County: Santa Barbara County (FIPS 06083). https://sealedbidder.com/counties/santa-barbara-county-ca-06083
- First posted: November 5, 2026
- Last posted: November 10, 2026
- SAM.gov: https://sam.gov/workspace/contract/opp/b2b1451f15c44612a7284357613b5601/view

## Reading this notice

- Kind of notice: Combined synopsis and solicitation. A streamlined commercial-item buy where the notice itself is the solicitation.
- Who may compete: Total small business set-aside. Only small businesses may compete. Small, under NAICS 332321 (metal window and door manufacturing), means no more than 750 employees, counted with affiliates.
- Time to respond: Bidders had 11 days from the day the solicitation was posted, November 5, 2026, to the deadline.

## Description

STATEMENT OF WORK / REQUEST FOR QUOTE

A. INTRODUCTION:

1. The Federal Bureau of Prisons (FBOP), FCC Lompoc, 3901 Klein Blvd., Lompoc, CA 93436, is

seeking quotes from qualified vendors for the supply and delivery of nine (9) complete fire

escape door assemblies, including doors, frames, and all required hardware. The doors are for a

prison facility application and must meet all relevant local, state, and federal fire and life safety

codes.

2. "Equal or Better" Product Substitution: Proposals must meet or exceed the specified product

quality. If an alternative product or component is offered, the vendor must submit all technical

documentation, certifications, and test results for consideration.

3. Government's Right of Final Technical Acceptance: The government retains the sole and final

authority to determine technical acceptance for all submitted products, based on the provided

documentation and compliance with stated standards.

B. SCOPE OF WORK:

1. The vendor shall provide all materials as specified below. All components must be new, U.L.

Listed or labeled by a recognized testing agency acceptable to the Authority Having Jurisdiction

(AHJ) and conform to the standards referenced herein.

C. TECHNICAL SPECIFICATIONS:

TABLE 1: COMPONENTS: All units shall be identical unless otherwise noted.

	Component

		Requirement

	Quantity

		9 Complete Door Assemblies

	Door Size

		36" wide x 80" high x 2" thick

	Door Material

		Hollow Metal Door, minimum 12 Gauge galvanneal steel

	Core

		Ribbed and Insulated (mineral core for fire rating is acceptable/preferred)

	Fire Rating

		Rating must be compatible with the wall's fire resistance rating, typically 75% of the wall's rating. See required fire rating for correctional facilities on Table 2

	Handing

		4 Left Hand Outswing, 5 Right Hand Outswing.

	Frame Material

		Minimum 12 Gauge galvanneal steel, fire-rated and labeled

	Frame Type

		Knock-down (KD) for drywall/unit masonry or welded for masonry. Frames are

to be prepared for 80 series lock, keyed 2 sides strike, surface pull on both

sides and prepped for PA closer.

	Finish

		Factory primed for field painting

TABLE 2: FIRE RATING:

The complete door assembly (door, frame, and all hardware) shall be 90 minutes fire rated. This rating

must be compatible with the fire-resistance rating of the specific wall assembly in which the door will be

installed, as dictated by the building's fire safety plan and local code requirements.

Category Requirement Description Applicable Standards &

Agencies

	Listing & Labeling

		All components must be listed and labeled by a recognized third-party testing agency acceptable to the Authority Having Jurisdiction (AHJ).

		Underwriters Laboratories (UL), Intertek (WH), Factory Mutual (FM)

	Testing Standard

		Assemblies shall be tested under positive pressure conditions.

NFPA 252, ANSI/UL 10C

	Labeling Visibility

		A permanent, legible fire rating label must be affixed to both the door and the frame and remain visible after installation for inspection purposes.

		N/A

	Code Compliance

		Vendor must confirm that all components, when installed as an assembly, comply with relevant building and safety codes for correctional facilities (Group I-3 Occupancies, IBC).

		NFPA 80 (Standard for Fire Doors and Other Opening Protectives)

		International Building Code (IBC)

TABLE 3: HARDWARE SPECIFICATIONS:

All hardware must be "listed" or "labeled" for use on a fire-rated assembly, compatible with the specified fire rating, and factory-prepped for ANSI/BHMA Grade 1 standards.

Item Requirement Quantity

per Door

Notes

	Hinges

		Heavy-duty steel ball bearing hinges, UL Listed

		3

	Exit Device

		Panic Hardware/Fire Exit Hardware (rim or mortise type) self-latching

		1 set

		Must be a crossbar or touch bar device, operable with an applied force of 15 lbs or less.

	Locking

		Must be openable from the egress side at all times without special knowledge or tools. Keyed access from the exterior is permitted.

		1 set

		80 series lock, keyed 2 sides strike, surface pull on both sides and prepped for PA closer.

	Door Closer

		Heavy-duty, adjustable, surface-mounted, UL Listed

		1 unit

		Must be self-closing and ensure positive latching.

	Seals

		Smoke and draft control gasketing/seals

		1 set

		Required for a complete smoke-rated assembly.

	Threshold

		[Specify if required, e.g., 1/2" beveled aluminum, non-combustible]

		1 unit (if required)

D. CODE AND STANDARD REQUIREMENTS:

1. All supplied materials and the complete assembly must comply with the latest editions of the

following codes and standards (or local equivalents as adopted by the AHJ):

	NFPA 80: Standard for Fire Doors and Other Opening Protectives

	NFPA 101: Life Safety Code

	International Building Code (IBC)

	International Fire Code (IFC)

	OSHA requirements for exit routes

	UL 10C or NFPA 252: Standard for positive pressure fire testing of door assemblies

	UL 1784: Standard for Air Leakage Tests of Door Assemblies (if smoke rating is required)

2. Vendors must confirm that all components, when installed as an assembly, will bear a permanent,

legible label from a recognized third-party testing agency (e.g., UL, Intertek/WH, FM).

E. SUBMISSION REQUIREMENTS:

1. Itemized pricing for doors, frames, hardware, and any included accessories.

2. Proposed lead time for manufacturing and delivery to FCC Lompoc

3. Confirmation of compliance with all referenced codes and standards.

4. Cut sheets/product data for all proposed items.

F. DELIVERY OF MATERIALS:

1. Deliveries shipped directly to FCC LOMPOC can only be received between 7:30 a.m. and 2:00

p.m., Monday through Friday, excluding Federal Holidays.

2. POC: Mr. Fernando Pena, BOP Engineering Technician, FXPena@bop.gov, or 805-735-2771

3. FBOP will be responsible for receiving or signing deliveries.

4. FCC LOMPOC will provide resources for loading and unloading materials or equipment upon

arrival.

## Attachments

- [LOX 26Z6AL1 RplFireEscapeDoors FCI 1_SOW_Approved..pdf](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/18c7ae5f8f1b474fb5f77ad3bc239235/download)
- [15B61727Q00000002-BRQ.pdf](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/14ccf12eb2c54251af712a455db7ac07/download)
- [FCC Lompoc Fire Door Assembly Combined Synopsis.pdf](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/cc9e07ede4db43589bf5425adad42d53/download)

## Open now in the same industry

8 open in NAICS 332321.

- Dumpster Area Roll Up Door Replacement (36C24627Q0149), due November 27, 2026 at 9:00 AM EST. https://sealedbidder.com/opportunities/36c24627q0149
- BOLT,SHEAR (SPE4A727T4493), due November 27, 2026. https://sealedbidder.com/opportunities/spe4a727t4493
- Sole Source to Jered LLC - Hanger Door Replacement Parts (N0040627Q0017), due December 1, 2026 at 5:00 PM EST. https://sealedbidder.com/opportunities/n0040627q0017

## Publications

- November 5, 2026: Combined synopsis and solicitation, due November 16, 2026 at 4:00 PM EST. Notice 889b960037f64c288fd031fb8d5c49e3. https://sam.gov/workspace/contract/opp/889b960037f64c288fd031fb8d5c49e3/view
- November 10, 2026: Combined synopsis and solicitation, due November 16, 2026 at 4:00 PM EST. Notice 85dc0988f46f456f9a3b64348199eba0. https://sam.gov/workspace/contract/opp/85dc0988f46f456f9a3b64348199eba0/view
- November 10, 2026: Combined synopsis and solicitation, due November 16, 2026 at 4:00 PM EST. Notice b2b1451f15c44612a7284357613b5601. https://sam.gov/workspace/contract/opp/b2b1451f15c44612a7284357613b5601/view

## Points of contact

- Tammy LaMirand, tlamirand@bop.gov

---
Source: SAM.gov Contract Opportunities bulk extract. Confirm deadlines on SAM.gov before responding. Cite https://sealedbidder.com/opportunities/15b61727q00000002.